塔吊基础及安装施工方案

正弘蓝堡湾二期

9#楼

目录------------------------------------------------------------------------------------------------------1 1、编制依据-------------------------------------------------------------------------------------------3 2、工程概况-------------------------------------------------------------------------------------------3 3、工程项目简介-------------------------------------------------------------------------------------3 4、施工部署-------------------------------------------------------------------------------------------3 4、1塔吊选型-----------------------------------------------------------------------------------------4 4、2塔吊基础选型-----------------------------------------------------------------------------------4 4、3塔吊基础埋置深度-----------------------------------------------------------------------------5 5、施工准备-------------------------------------------------------------------------------------------5 5、1技术准备-----------------------------------------------------------------------------------------5 5、2施工队伍的选择--------------------------------------------------------------------------------5 5、3材料、人员及机具准备-----------------------------------------------------------------------6 6、具体施工方法及措施----------------------------------------------------------------------------6 6、1塔吊基础施工工艺-----------------------------------------------------------------------------6 6、2塔吊安装施工-----------------------------------------------------------------------------------7 6、3塔吊拆卸施工-----------------------------------------------------------------------------------9 6、4塔吊附着施工-----------------------------------------------------------------------------------9 6、5塔吊爬升施工-----------------------------------------------------------------------------------9 6、6塔吊的使用-------------------------------------------------------------------------------------10 7、安全施工措施------------------------------------------------------------------------------------10 7、1塔吊安装安全措施----------------------------------------------------------------------------10 7、2塔吊顶升安全措施----------------------------------------------------------------------------11 7、3塔吊安全操作----------------------------------------------------------------------------------12 7、4塔吊防撞措施----------------------------------------------------------------------------------12 7、5塔吊的维修与保养----------------------------------------------------------------------------12 8、塔吊稳定性计算---------------------------------------------------------------------------------13

正弘蓝堡湾二期

9#楼

8、1地基承载能力验算----------------------------------------------------------------------------13 8、2基础底板抗弯能力验算----------------------------------------------------------------------14

正弘蓝堡湾二期

9#楼

1、编制依据 ✧ 工程施工图纸 ✧ 岩土工程勘察报告 ✧ 塔吊使用说明书 ✧ 施工现场平面布置图

✧ 混凝土结构工程施工及验收规范 ✧ 简明施工计算手册

✧ 郑州一建土方、混凝土施工作业指导书 2、工程概况

本工程位于东风路南、文博路以东、金基路以北区域;为一座高层综合楼。本工程地下2层,地上31层,总建筑面积为62301.77㎡,建筑高度98. 75米。地下室为停车场及设备用房,一~三层裙房为商业用房,四层及四层以上为住宅。结构型式:钢筋混凝土剪力墙结构。主塔楼下采用平板式桩筏基础,基础混凝土强度等级为C40。裙房及外扩全埋地下室(考虑抗浮要求),部分采用柱下独立承台桩基。 3、工程项目简介

4、施工部署

正弘蓝堡湾二期

9#楼

4、1塔吊选型

结合工程形状及施工要求和现场场地情况,使用两部塔吊,分别选在主楼北侧d6~~d7轴及d16~~d17轴之间,塔吊型号选用QTZ80(5513),两塔均为固定自升式塔式起重机,塔吊臂长均为60m ,各主要技术性能、参数如下:

QTZ80(5513)两塔吊满足施工需要,臂长均为60m 最大起重量6T ,第一次附着前吊钧最大自由高度为40m ,第一次附着点高度距地面32m ,第二次附着距第一次附着是24m ,标准节的规格为1.65×1.65×2.5m 。 4、2塔吊基础选型

根据塔吊说明书中地基承载能力需大于fka=0.2Mpa的要求及现场地基承载力,基础选用天然地基承台基础,外型尺寸为6×6×1.35m ,塔吊基础承台配筋

正弘蓝堡湾二期

9#楼

为Ⅱ级钢Φ20@170双层双向,两网片之间连接筋为Φ12@510梅花型布置,基础混凝土标号为大于等于C35。 4、3塔吊基础埋置深度

由于施工现场场地狭小,大量材料、设备不能直接运至堆放地点,需要塔吊二次转运,因此塔吊只有在正式施工前抢先安装使用,才能保证工程正常进行。同时,为不影响主楼筏板基础底标高以下部位,座落在基底土第11层细砂上,天然土的承载能力特征值为fka=260Kpa,塔吊基础底标高为-12.07m 。 5、施工准备 5、1技术准备

✧ 根据塔吊使用说明书及施工规范要求编制本施工方案,并进行报批,在方案审批

合格后方可进行施工。

✧ 塔吊基础施工及安装运行前,应认真阅读使用说明书,熟悉塔机的基础、安装、

使用、安全维护等各项内容的技术要求,以便塔机能顺利安装及安全运行。 ✧ 对所有进场人员进行技术交底,使作业人员熟悉塔机安装程序和要点。具体内容

如下:

1)安装工必须要了解塔吊的性能、安装程序、安装部件的质量和吊点的正确吊挂方法。

2)安装之前,本机组人员必须在场,同时当面进行交底本机械电气设备情况。 3)安装塔机时,严禁只安装一个臂就中断作业。

4)顶升进,严格按说明书规定的要求使塔机处于最佳平衡状态。 5)在顶升过程中,应有专人看护电缆,以防被刮伤、挤断。

6)凡风力超过4级,或者遇到大雨、大雾等恶劣天气均禁止进行顶升作业。 7)在顶升作业时,禁止转动起重臂、移动小车及吊钩进行起升或下降动作。 5、2施工队伍的选择

本工程的塔吊基础施工由我单位根据方案内容施工。2台塔吊均委托给与我公司有常年合作关系,并且具有相应安拆资质的公司负责。 5、3材料、人员及机具准备

正弘蓝堡湾二期

9#楼

✧ 基础施工前,应提前准备并加工好基础钢筋,联系好混凝土厂家并确定混凝土用

量,做好钢筋绑扎及浇混凝土的准备工作。

✧ 塔吊安装人员应配备齐全、合理分工,有效的发挥每个人的作用,尽可能的提高

工效。

6、具体施工方法及措施 6、1塔吊基础施工工艺

塔吊定位、放线→土方开挖→浇筑混凝土垫层→砌砖模及内粉→防水处理→基础钢筋绑扎→预埋、固定塔吊基座→浇筑混凝土→养护

基础钢筋:塔吊基础承台配筋为Ⅱ级钢Φ20@170双层双向,两面网片之间连接筋为Φ14@510梅花型布置。基础钢筋施工时应事先留置接地极,用Φ16钢筋打入地基土内并与钢筋网片和塔吊基座电气连接,保证接地电阻不大于4Ω.

基础模板:本工程塔吊基础模板均采用砖模,每个基础表面均预留250×250×400mm 的集水坑,以确保基础内排水。

基础混凝土:塔吊基础混凝土使用商品混凝土,标号为C40,单个基础混凝土方量为48.6立方。为了满足塔吊安装要求,尽早开始塔吊安装,混凝土标号可根据实际情

正弘蓝堡湾二期

9#楼

况提高一级,待混凝土强度达到设计强度的75%后即可开始塔吊安装。混凝土浇时每个基础各留置两组试块,一组用于安装强度检验,一组用于标准强度检验。 6、2塔吊安装施工 6、2、1安装准备工作

1)清理现场障碍物,在基坑边安装塔吊时,安装车辆距坑边不少于3米水平距离。

2)立塔期间,现场安全员在现场作好现场安全协调工作,特别是塔吊安装周围不得有外人及其它车辆穿行。

3)夜间工作时必须有足够的照明。

4)塔吊安装时,塔吊基础混凝土强度必须达到设计强度75%以上,本工程塔吊基础混凝土的使用强度按C40考虑,其强度值以试块为准。

5)塔吊安装期间,基坑内土方作业暂停施工。 6、2、2具本安装方法

1)在地面上先将4块塔身基节片拼装成基节,然后将塔身基节吊装与预埋的基础节相连。

2)在地面上先将爬升架拼装成整体,然后将爬升架吊装,套在塔基节外面,并安装好液压油缸和液压系统并使用油缸的顶升横梁顶在基节的最后一个踏步上。(应注意的是爬升架的开口应与建筑物平行,以便施工完成后拆塔)

3)在地面上,将上下支座以及回转支承、回转机构等用螺栓联成一体后,吊装到塔身和套上,用16个M24和8个M36高强螺栓将上下支座代分别与爬升架和塔身锁紧。

4)在地面上将平衡臂拉杆的第一节与塔帽用销轴连接起来,然后吊装塔帽到上支座上,并用四个销轴相连。

5)在地面上拼好平衡臂,并将卷扬机、配电箱、电阻箱等安装到平衡臂上,接好各部分所需的电线,然后将平衡臂拉杆的安装位置,安装好平衡臂拉杆后,再吊装一块平衡重压在前端(距塔身近端)。

6)吊装起重臂,起重臂拉杆安装

正弘蓝堡湾二期

9#楼

不同臂长的起重臂拉杆,其臂节和拉杆节的配置根据各型号塔吊厂家说明要

求。

按照施工需要组合吊臂长度,本工程塔臂长60m 。用相应的销轴把每节装配

在一起,把第一节臂和第二节臂连接后,安装上小车和吊钩,并把小车和吊钩固定在臂根部。

按照臂长组合吊臂拉杆长度,用销轴把它们连接起来,固定在吊臂上选杆的

的相应架上。

检查吊臂上的电路是否完善,并穿绕小车牵引钢丝绳。

用汽车吊将吊臂总成平稳提升。提升过程中必须保持吊臂处于水平位置,使

得吊臂能够顺利的安培育到上支座的吊臂点上。可先进行试吊,并在吊臂的两端系上较长的绳子已促使吊臂平衡。

在吊臂与上支座连接完毕后,继续提升吊臂,使吊臂的头部稍稍抬起,并使

用起升机构通过塔顶和吊臂拉杆上的一组滑轮拉起拉杆,使短杆的连接板能够用销轴连接到塔顶相庆的拉板上。然后在调整长拉杆的高度位置,使得长拉杆的连接板能够用销轴连接到塔顶相应的拉板上。

松弛起升机构的钢丝绳。把吊臂缓缓放下,使拉杆处于拉紧城市态,并要求

检查是否上翘1/100,否则更换一组拉杆的连接板,直到满足为止。最后,松脱滑轮组上的起升钢丝绳。

7)吊装司机室(根据塔机型号,可在塔顶安装后进行)。在地面上将司机室内的电气设检查以后,将司机室吊起至上支座的上平面,然后用销轴将司机室与上支座连接好。

8)吊装平衡重。根据所使用的臂架长度,按规定安装不同重量的平衡重。 9)检查整机的机械部分,结构连接部分,电报导和液压部分。

10)当整机安装完毕后,在无风的状态下,检查塔身轴线的垂直度,允许误差为2/1000,再按电路图的要求接通所有电路的电源,试开动各机构进行运转,检查各机构运转是否正确,同时检查各处钢丝绳是否处于正常工作状态,是否与结构件有摩擦,所有不正常情况均应予以排除,并按要求调整好安全装置。

正弘蓝堡湾二期

9#楼

6、3塔吊拆卸施工

塔式起重机的拆卸与安装想反,拆卸时注意先装的后拆,后装的先拆。塔吊拆卸时编制《塔吊拆卸方案》。 6、4塔吊附着施工

塔吊附着是由四个撑杆和一套环梁等组成,它主要是把塔机固定在建筑物的柱子上,起着依附作用,使用时环梁套在标准节上,四角用八个调节螺栓通过顶块把标准节顶牢,其撑杆长度可以调整。四根撑杆端部有大耳环与建筑物附着处铰接。四根撑杆应保持在同一水平内,调整顶块及撑杆长度使得塔身轴线铅垂。 6、5塔吊爬升施工

随着建筑物的升高,要求塔机起升高度也随之升高,当起升高度达不到要求时应进行塔机爬升施工。

✧ 将吊臂固定于垂直横梁的方向,这时,平衡臂位于顶升油缸正上方,调整小车幅

度,使得塔机重心垂直平面通过踏身踏步。

✧ 松开各爬升架上的顶块,将油缸活塞头的扁担梁支撑在踏身踏步上,操纵油缸将

踏身上移1.5米左右,将爬升框架上的两根撑杆支撑在踏身踏步上。

✧ 收回油缸,将活塞头部的扁担梁挑在下面一对踏步上,操纵油缸向上顶升1.5米

左右,然后在用撑住另一对踏步,这样周而复始。

✧ 当基础节的四支腿超过第二爬升框架平面时,拉出支腿缩回油缸,将塔机座落在

爬升框架上。

✧ 将8根撑杆支撑与最上面一个框架拉于同一水平的踏身四周,适当顶紧。用爬升

框架上的顶块调整塔身的垂直度至1/1000以内。然后适当顶紧顶块,锁住顶块螺母。

✧ 将下面那个已脱离塔身的框架及支撑架钢梁提升至施工楼层并安装好,以便下一

次顶升。安装时保证8个导向轮与塔身部隙基本一致后,才能拧紧连接螺栓,但此框架上的各块顶块不能顶紧。

✧ 调整起升机构幅度限位置,使吊钩上升至离吊臂2米处自动停车。 6、6塔吊使用

正弘蓝堡湾二期

9#楼

✧ 塔吊必须在符合设计规定的基础上工作。

✧ 塔吊的操作人员必须经过训练,了解机械的构造和使用,必须熟知机械的保养和

安全操作规程,非安装、维护人员未经许可不得攀蹬塔机。

✧ 起重机每转移一次工地重新安装后,必须进行空载、静载、动载试验后方能进行

吊装作业,其静载试验吊重为额定荷载的125%,动载试验吊重采用额定荷载的110%。

✧ 在夜间工作时,除塔身本身照明外,施工现场必须具备充分的照明设备。 ✧ 司机室内禁止存放润滑油,棉纱及其他易燃、易爆物品,冬季用电器设备取暖时

应注意安全和防火。

✧ 工作前应检查各控制的转动装置、制动器闸瓦、传动部位润滑油、钢丝绳磨损情

况及电源电压等,如有不符合要求,应及时修整。

✧ 塔机应定机定人,专机专人负责制。非机组人员不得进入司机室和擅自操作,在

处理电气事故时候必须严格按照额定起重起吊,不得超载,不准吊运人员,斜拉重物、拔除地下物等,并应严格遵守塔吊“十不吊”的规定。 ✧ 起重作业后应做到以下几点:

臂杆转到顺风方向,并放松回转制动器。小车及平衡重应移动到非工作状态。

吊钩提升到离臂杆顶2-3m 处。

将每个控制开关拔至零位,依次断一各路开关,切断电源总开关,打开高空

指示灯。

如有六级以上大风,应另拉揽风绳与地面或建筑物结构固定。 7、安全施工措施 7、1塔吊安装安全措施

✧ 安装现场所有人员必须戴好安全帽,高空作业人员必须系好安全带,带工具要求

做到:扳后带绳,锤子、螺丝刀带包,严禁往下扔东西。安装现场用绳子围设安全警示区,并安排人员在附近看护,确保安装过程中塔机下面禁止有人穿行。 ✧ 统一指挥,工作人员必须服从命令,严禁酒后作业。

正弘蓝堡湾二期9#楼 ✧ 吊装人员要掌握重量,适当选用吊索的长度和直径,选择好被吊物的重心,吊索

要正确挂在吊点上。

✧ 塔吊安装工作应在塔机最高处风速不大于8m/s时进行。

✧ 必须遵循立塔程序。

✧ 注意吊具的选择,根据吊装部件的外形尺寸,重量等选及长度适当、重量可靠的

吊具。

✧ 塔机各部件所有可拆的销轴、塔身连接的螺栓、螺母均是特制零件,不得随意代

换。

✧ 必须安装并使用扶梯、平台、护栏等安全保护装置。

✧ 装好起重臂后,平衡臂上未装够规定的平衡重前,严禁起重臂吊载物件。 ✧ 标准节的安装不得任意交换方位,否则无法进行顶升。

7、2塔吊顶升安全措施

✧ 在顶升过程中必须有专人指挥,专人照看电源,专人操作液压系统,专人紧固螺

栓,非操作人员不得蹬上爬升套架的操作平台,更不得启动液压系统的油泵、阀开关或其它电器设备。

✧ 顶升作业应尽量在白天进行,特殊情况下需在夜间进行作业时,应有足够的照明。 ✧ 风力在四级以上时,不得进行顶升作业。在作业过程中如遇风力突然加大时必须

停止顶作业,并紧固连接螺栓。

✧ 顶升前应事先放松电缆,其长度应略大于总爬升高度,并做好电缆卷筒的固定工

作。

✧ 顶升过程中,并将回转机构制动住,严禁回转塔身及其它作业。

✧ 每次顶升后必须认真做好准备和检查工作,特别是顶升后应认真检查各连接螺栓

是否按规定扭力拧紧紧固,爬升套架内的滚轮与塔身标准节间的间隙是否调整好,操作杆是否回到是中间位置以及液压系统的电源是否切断。

7、3塔吊安全操作

✧ 操作人员必须在接到指挥信号后方可进行操作,操作前必须鸣笛,操作时应集中

精力。

正弘蓝堡湾二期9#楼 ✧ 司机必须严格按照起重性能表中规定的幅度和起重量进行工作,不许超载使用。 ✧ 起重机不许斜拉和斜吊物品,并禁止用于拨桩等类似用于拔桩等类似的作业。严

格遵守塔吊“十不准”的规定。

✧ 工作中塔机梯上严禁有人,并不得在工作中进行调整或维修等作业。

✧ 工作时严禁闲人走进臂架活动范围以内。

✧ 液压系统安全阀的数值、电器系统保护装置的调整什及其它机械、结构部件的调

整什均不得随意改动。

7、4塔吊防撞措施

✧ B 塔机工作时应注意相互之间的位置,并在安装过程中采取不同的安装高度,以

避免两塔机的起重相互碰撞。

✧ 受周围建筑的影响,特别是B 塔在回转半径内不能自由回转,如遇大风等恶劣天

气影响,塔臂必会撞到东侧相临建筑物上造成事故。因此必须在适当位置设置地锚,在塔吊停止后,及时将吊钩挂在地锚上,以限制塔臂自由摆动,防止塔臂旋转撞击相临建筑物。

7、5塔吊应经常进行查检查、维修和保养,传动部分应有足够的润滑油,对易损件必须经常进行检查、维修或更换。对机械的螺栓,特别是经常振动的部位零件,如塔身连接螺栓应检查是否松动,如有松动则必须拧紧或更换。

7、5、1机械设备的维护和保养

各机构的制动器应经常进行检查和调整,制动瓦和制动轮的间隙,保证灵活可靠,

其间隙保证0.5-1.0mm 之间,在摩擦面上不应有污物存在,遇有污物必须用汽油或稀料洗掉。

减速箱、变速箱、啮合齿轮等各部分的润滑以及液压油均按规定要求进行。

要注意检查各部分钢丝绳有无断丝和松动现象,如有超过规定,必须立即更换。 经常检查各部位的连接情况,如有松动应及时拧紧。塔身连接螺栓应在塔身受压

时检查松紧度。所有连接必须装有开口销,并需张开。

经常检查各机构运转是否正常和有无噪音。

正弘蓝堡湾二期9#楼 装、拆和调整回转机构时,要注意保证回转机构行走齿轮减速器的中心与齿轮的

中心平行,间隙要适中。

7、5、2电气系统维护和保养

经常检查所有的电线、电缆有无损伤,要及时的包扎和更换已损伤的部分。

遇到电动机有过热的现象要及明停车,排除故障后在继续进行作业,电机轴承润

滑要良好。

集电环及其它部分电刷,其接触面要保持清洁,调整电刷压力,使其接触面积不

小于50%。

各控制箱、配电箱要经常保持清洁,及时清扫电器设备上的灰尘。

各安全装置的行程开关的触点开闭必须可靠,触点弧坑应及时磨光。

每年定期摇侧保护接地电阻两次,保证不大于4欧姆。

7、5、3液压爬升系统的维护和保养

使用液压油严格按照润滑表中的规定进行加油、换油并清洗油箱内部。

溢流阀的压力调整后,不得随意更动,每次进行爬升前,应用油压表检查其压力

是否正常。

应经常检查各部件接是否紧固严密,不准有漏油现象。

滤油器应经常检查是否堵塞,检查安全阀的使用调整值是否有变动。

油缸、油泵和控制阀,如发现有渗漏应及时检修。

在冬季启动时,要启动、停止反复数次,待油温上升和控制阀转动灵活后再正式

使用。

8、塔吊稳定性计算

8、1地基承载能力验算

本工程两台塔吊基础均座落在裙楼基础筏板以下,根据河南工程水文地质有限公司勘察院工程勘察报告中-12.07米处的承载能力特征值fa 大于要求的地基承载力200Kpa 。因此,地基承载能力满足要求。

8、2基础底板抗弯能力验算

按塔吊使用说明书中要求基础底板所受弯矩最大值为:

正弘蓝堡湾二期9#楼 Mmax=190T ·m

基础底板截面积为6000×1350,设计仅考虑底部钢筋的作用,混凝土保护层按70mm 考虑,即

As=Mmax/fy h o =190×107/(310×1280)=4788.31(mm2)

按Φ20@170配置,35Φ20(公称截面积为314mm 2)钢筋截面积为

As=35×314=10990(mm2)

满足要求。

施工现场平面布置图见下页:

正弘蓝堡湾二期9#楼

郑州一建第二十二项目部

2010年9月16日

正弘蓝堡湾二期

9#楼

目录------------------------------------------------------------------------------------------------------1 1、编制依据-------------------------------------------------------------------------------------------3 2、工程概况-------------------------------------------------------------------------------------------3 3、工程项目简介-------------------------------------------------------------------------------------3 4、施工部署-------------------------------------------------------------------------------------------3 4、1塔吊选型-----------------------------------------------------------------------------------------4 4、2塔吊基础选型-----------------------------------------------------------------------------------4 4、3塔吊基础埋置深度-----------------------------------------------------------------------------5 5、施工准备-------------------------------------------------------------------------------------------5 5、1技术准备-----------------------------------------------------------------------------------------5 5、2施工队伍的选择--------------------------------------------------------------------------------5 5、3材料、人员及机具准备-----------------------------------------------------------------------6 6、具体施工方法及措施----------------------------------------------------------------------------6 6、1塔吊基础施工工艺-----------------------------------------------------------------------------6 6、2塔吊安装施工-----------------------------------------------------------------------------------7 6、3塔吊拆卸施工-----------------------------------------------------------------------------------9 6、4塔吊附着施工-----------------------------------------------------------------------------------9 6、5塔吊爬升施工-----------------------------------------------------------------------------------9 6、6塔吊的使用-------------------------------------------------------------------------------------10 7、安全施工措施------------------------------------------------------------------------------------10 7、1塔吊安装安全措施----------------------------------------------------------------------------10 7、2塔吊顶升安全措施----------------------------------------------------------------------------11 7、3塔吊安全操作----------------------------------------------------------------------------------12 7、4塔吊防撞措施----------------------------------------------------------------------------------12 7、5塔吊的维修与保养----------------------------------------------------------------------------12 8、塔吊稳定性计算---------------------------------------------------------------------------------13

正弘蓝堡湾二期

9#楼

8、1地基承载能力验算----------------------------------------------------------------------------13 8、2基础底板抗弯能力验算----------------------------------------------------------------------14

正弘蓝堡湾二期

9#楼

1、编制依据 ✧ 工程施工图纸 ✧ 岩土工程勘察报告 ✧ 塔吊使用说明书 ✧ 施工现场平面布置图

✧ 混凝土结构工程施工及验收规范 ✧ 简明施工计算手册

✧ 郑州一建土方、混凝土施工作业指导书 2、工程概况

本工程位于东风路南、文博路以东、金基路以北区域;为一座高层综合楼。本工程地下2层,地上31层,总建筑面积为62301.77㎡,建筑高度98. 75米。地下室为停车场及设备用房,一~三层裙房为商业用房,四层及四层以上为住宅。结构型式:钢筋混凝土剪力墙结构。主塔楼下采用平板式桩筏基础,基础混凝土强度等级为C40。裙房及外扩全埋地下室(考虑抗浮要求),部分采用柱下独立承台桩基。 3、工程项目简介

4、施工部署

正弘蓝堡湾二期

9#楼

4、1塔吊选型

结合工程形状及施工要求和现场场地情况,使用两部塔吊,分别选在主楼北侧d6~~d7轴及d16~~d17轴之间,塔吊型号选用QTZ80(5513),两塔均为固定自升式塔式起重机,塔吊臂长均为60m ,各主要技术性能、参数如下:

QTZ80(5513)两塔吊满足施工需要,臂长均为60m 最大起重量6T ,第一次附着前吊钧最大自由高度为40m ,第一次附着点高度距地面32m ,第二次附着距第一次附着是24m ,标准节的规格为1.65×1.65×2.5m 。 4、2塔吊基础选型

根据塔吊说明书中地基承载能力需大于fka=0.2Mpa的要求及现场地基承载力,基础选用天然地基承台基础,外型尺寸为6×6×1.35m ,塔吊基础承台配筋

正弘蓝堡湾二期

9#楼

为Ⅱ级钢Φ20@170双层双向,两网片之间连接筋为Φ12@510梅花型布置,基础混凝土标号为大于等于C35。 4、3塔吊基础埋置深度

由于施工现场场地狭小,大量材料、设备不能直接运至堆放地点,需要塔吊二次转运,因此塔吊只有在正式施工前抢先安装使用,才能保证工程正常进行。同时,为不影响主楼筏板基础底标高以下部位,座落在基底土第11层细砂上,天然土的承载能力特征值为fka=260Kpa,塔吊基础底标高为-12.07m 。 5、施工准备 5、1技术准备

✧ 根据塔吊使用说明书及施工规范要求编制本施工方案,并进行报批,在方案审批

合格后方可进行施工。

✧ 塔吊基础施工及安装运行前,应认真阅读使用说明书,熟悉塔机的基础、安装、

使用、安全维护等各项内容的技术要求,以便塔机能顺利安装及安全运行。 ✧ 对所有进场人员进行技术交底,使作业人员熟悉塔机安装程序和要点。具体内容

如下:

1)安装工必须要了解塔吊的性能、安装程序、安装部件的质量和吊点的正确吊挂方法。

2)安装之前,本机组人员必须在场,同时当面进行交底本机械电气设备情况。 3)安装塔机时,严禁只安装一个臂就中断作业。

4)顶升进,严格按说明书规定的要求使塔机处于最佳平衡状态。 5)在顶升过程中,应有专人看护电缆,以防被刮伤、挤断。

6)凡风力超过4级,或者遇到大雨、大雾等恶劣天气均禁止进行顶升作业。 7)在顶升作业时,禁止转动起重臂、移动小车及吊钩进行起升或下降动作。 5、2施工队伍的选择

本工程的塔吊基础施工由我单位根据方案内容施工。2台塔吊均委托给与我公司有常年合作关系,并且具有相应安拆资质的公司负责。 5、3材料、人员及机具准备

正弘蓝堡湾二期

9#楼

✧ 基础施工前,应提前准备并加工好基础钢筋,联系好混凝土厂家并确定混凝土用

量,做好钢筋绑扎及浇混凝土的准备工作。

✧ 塔吊安装人员应配备齐全、合理分工,有效的发挥每个人的作用,尽可能的提高

工效。

6、具体施工方法及措施 6、1塔吊基础施工工艺

塔吊定位、放线→土方开挖→浇筑混凝土垫层→砌砖模及内粉→防水处理→基础钢筋绑扎→预埋、固定塔吊基座→浇筑混凝土→养护

基础钢筋:塔吊基础承台配筋为Ⅱ级钢Φ20@170双层双向,两面网片之间连接筋为Φ14@510梅花型布置。基础钢筋施工时应事先留置接地极,用Φ16钢筋打入地基土内并与钢筋网片和塔吊基座电气连接,保证接地电阻不大于4Ω.

基础模板:本工程塔吊基础模板均采用砖模,每个基础表面均预留250×250×400mm 的集水坑,以确保基础内排水。

基础混凝土:塔吊基础混凝土使用商品混凝土,标号为C40,单个基础混凝土方量为48.6立方。为了满足塔吊安装要求,尽早开始塔吊安装,混凝土标号可根据实际情

正弘蓝堡湾二期

9#楼

况提高一级,待混凝土强度达到设计强度的75%后即可开始塔吊安装。混凝土浇时每个基础各留置两组试块,一组用于安装强度检验,一组用于标准强度检验。 6、2塔吊安装施工 6、2、1安装准备工作

1)清理现场障碍物,在基坑边安装塔吊时,安装车辆距坑边不少于3米水平距离。

2)立塔期间,现场安全员在现场作好现场安全协调工作,特别是塔吊安装周围不得有外人及其它车辆穿行。

3)夜间工作时必须有足够的照明。

4)塔吊安装时,塔吊基础混凝土强度必须达到设计强度75%以上,本工程塔吊基础混凝土的使用强度按C40考虑,其强度值以试块为准。

5)塔吊安装期间,基坑内土方作业暂停施工。 6、2、2具本安装方法

1)在地面上先将4块塔身基节片拼装成基节,然后将塔身基节吊装与预埋的基础节相连。

2)在地面上先将爬升架拼装成整体,然后将爬升架吊装,套在塔基节外面,并安装好液压油缸和液压系统并使用油缸的顶升横梁顶在基节的最后一个踏步上。(应注意的是爬升架的开口应与建筑物平行,以便施工完成后拆塔)

3)在地面上,将上下支座以及回转支承、回转机构等用螺栓联成一体后,吊装到塔身和套上,用16个M24和8个M36高强螺栓将上下支座代分别与爬升架和塔身锁紧。

4)在地面上将平衡臂拉杆的第一节与塔帽用销轴连接起来,然后吊装塔帽到上支座上,并用四个销轴相连。

5)在地面上拼好平衡臂,并将卷扬机、配电箱、电阻箱等安装到平衡臂上,接好各部分所需的电线,然后将平衡臂拉杆的安装位置,安装好平衡臂拉杆后,再吊装一块平衡重压在前端(距塔身近端)。

6)吊装起重臂,起重臂拉杆安装

正弘蓝堡湾二期

9#楼

不同臂长的起重臂拉杆,其臂节和拉杆节的配置根据各型号塔吊厂家说明要

求。

按照施工需要组合吊臂长度,本工程塔臂长60m 。用相应的销轴把每节装配

在一起,把第一节臂和第二节臂连接后,安装上小车和吊钩,并把小车和吊钩固定在臂根部。

按照臂长组合吊臂拉杆长度,用销轴把它们连接起来,固定在吊臂上选杆的

的相应架上。

检查吊臂上的电路是否完善,并穿绕小车牵引钢丝绳。

用汽车吊将吊臂总成平稳提升。提升过程中必须保持吊臂处于水平位置,使

得吊臂能够顺利的安培育到上支座的吊臂点上。可先进行试吊,并在吊臂的两端系上较长的绳子已促使吊臂平衡。

在吊臂与上支座连接完毕后,继续提升吊臂,使吊臂的头部稍稍抬起,并使

用起升机构通过塔顶和吊臂拉杆上的一组滑轮拉起拉杆,使短杆的连接板能够用销轴连接到塔顶相庆的拉板上。然后在调整长拉杆的高度位置,使得长拉杆的连接板能够用销轴连接到塔顶相应的拉板上。

松弛起升机构的钢丝绳。把吊臂缓缓放下,使拉杆处于拉紧城市态,并要求

检查是否上翘1/100,否则更换一组拉杆的连接板,直到满足为止。最后,松脱滑轮组上的起升钢丝绳。

7)吊装司机室(根据塔机型号,可在塔顶安装后进行)。在地面上将司机室内的电气设检查以后,将司机室吊起至上支座的上平面,然后用销轴将司机室与上支座连接好。

8)吊装平衡重。根据所使用的臂架长度,按规定安装不同重量的平衡重。 9)检查整机的机械部分,结构连接部分,电报导和液压部分。

10)当整机安装完毕后,在无风的状态下,检查塔身轴线的垂直度,允许误差为2/1000,再按电路图的要求接通所有电路的电源,试开动各机构进行运转,检查各机构运转是否正确,同时检查各处钢丝绳是否处于正常工作状态,是否与结构件有摩擦,所有不正常情况均应予以排除,并按要求调整好安全装置。

正弘蓝堡湾二期

9#楼

6、3塔吊拆卸施工

塔式起重机的拆卸与安装想反,拆卸时注意先装的后拆,后装的先拆。塔吊拆卸时编制《塔吊拆卸方案》。 6、4塔吊附着施工

塔吊附着是由四个撑杆和一套环梁等组成,它主要是把塔机固定在建筑物的柱子上,起着依附作用,使用时环梁套在标准节上,四角用八个调节螺栓通过顶块把标准节顶牢,其撑杆长度可以调整。四根撑杆端部有大耳环与建筑物附着处铰接。四根撑杆应保持在同一水平内,调整顶块及撑杆长度使得塔身轴线铅垂。 6、5塔吊爬升施工

随着建筑物的升高,要求塔机起升高度也随之升高,当起升高度达不到要求时应进行塔机爬升施工。

✧ 将吊臂固定于垂直横梁的方向,这时,平衡臂位于顶升油缸正上方,调整小车幅

度,使得塔机重心垂直平面通过踏身踏步。

✧ 松开各爬升架上的顶块,将油缸活塞头的扁担梁支撑在踏身踏步上,操纵油缸将

踏身上移1.5米左右,将爬升框架上的两根撑杆支撑在踏身踏步上。

✧ 收回油缸,将活塞头部的扁担梁挑在下面一对踏步上,操纵油缸向上顶升1.5米

左右,然后在用撑住另一对踏步,这样周而复始。

✧ 当基础节的四支腿超过第二爬升框架平面时,拉出支腿缩回油缸,将塔机座落在

爬升框架上。

✧ 将8根撑杆支撑与最上面一个框架拉于同一水平的踏身四周,适当顶紧。用爬升

框架上的顶块调整塔身的垂直度至1/1000以内。然后适当顶紧顶块,锁住顶块螺母。

✧ 将下面那个已脱离塔身的框架及支撑架钢梁提升至施工楼层并安装好,以便下一

次顶升。安装时保证8个导向轮与塔身部隙基本一致后,才能拧紧连接螺栓,但此框架上的各块顶块不能顶紧。

✧ 调整起升机构幅度限位置,使吊钩上升至离吊臂2米处自动停车。 6、6塔吊使用

正弘蓝堡湾二期

9#楼

✧ 塔吊必须在符合设计规定的基础上工作。

✧ 塔吊的操作人员必须经过训练,了解机械的构造和使用,必须熟知机械的保养和

安全操作规程,非安装、维护人员未经许可不得攀蹬塔机。

✧ 起重机每转移一次工地重新安装后,必须进行空载、静载、动载试验后方能进行

吊装作业,其静载试验吊重为额定荷载的125%,动载试验吊重采用额定荷载的110%。

✧ 在夜间工作时,除塔身本身照明外,施工现场必须具备充分的照明设备。 ✧ 司机室内禁止存放润滑油,棉纱及其他易燃、易爆物品,冬季用电器设备取暖时

应注意安全和防火。

✧ 工作前应检查各控制的转动装置、制动器闸瓦、传动部位润滑油、钢丝绳磨损情

况及电源电压等,如有不符合要求,应及时修整。

✧ 塔机应定机定人,专机专人负责制。非机组人员不得进入司机室和擅自操作,在

处理电气事故时候必须严格按照额定起重起吊,不得超载,不准吊运人员,斜拉重物、拔除地下物等,并应严格遵守塔吊“十不吊”的规定。 ✧ 起重作业后应做到以下几点:

臂杆转到顺风方向,并放松回转制动器。小车及平衡重应移动到非工作状态。

吊钩提升到离臂杆顶2-3m 处。

将每个控制开关拔至零位,依次断一各路开关,切断电源总开关,打开高空

指示灯。

如有六级以上大风,应另拉揽风绳与地面或建筑物结构固定。 7、安全施工措施 7、1塔吊安装安全措施

✧ 安装现场所有人员必须戴好安全帽,高空作业人员必须系好安全带,带工具要求

做到:扳后带绳,锤子、螺丝刀带包,严禁往下扔东西。安装现场用绳子围设安全警示区,并安排人员在附近看护,确保安装过程中塔机下面禁止有人穿行。 ✧ 统一指挥,工作人员必须服从命令,严禁酒后作业。

正弘蓝堡湾二期9#楼 ✧ 吊装人员要掌握重量,适当选用吊索的长度和直径,选择好被吊物的重心,吊索

要正确挂在吊点上。

✧ 塔吊安装工作应在塔机最高处风速不大于8m/s时进行。

✧ 必须遵循立塔程序。

✧ 注意吊具的选择,根据吊装部件的外形尺寸,重量等选及长度适当、重量可靠的

吊具。

✧ 塔机各部件所有可拆的销轴、塔身连接的螺栓、螺母均是特制零件,不得随意代

换。

✧ 必须安装并使用扶梯、平台、护栏等安全保护装置。

✧ 装好起重臂后,平衡臂上未装够规定的平衡重前,严禁起重臂吊载物件。 ✧ 标准节的安装不得任意交换方位,否则无法进行顶升。

7、2塔吊顶升安全措施

✧ 在顶升过程中必须有专人指挥,专人照看电源,专人操作液压系统,专人紧固螺

栓,非操作人员不得蹬上爬升套架的操作平台,更不得启动液压系统的油泵、阀开关或其它电器设备。

✧ 顶升作业应尽量在白天进行,特殊情况下需在夜间进行作业时,应有足够的照明。 ✧ 风力在四级以上时,不得进行顶升作业。在作业过程中如遇风力突然加大时必须

停止顶作业,并紧固连接螺栓。

✧ 顶升前应事先放松电缆,其长度应略大于总爬升高度,并做好电缆卷筒的固定工

作。

✧ 顶升过程中,并将回转机构制动住,严禁回转塔身及其它作业。

✧ 每次顶升后必须认真做好准备和检查工作,特别是顶升后应认真检查各连接螺栓

是否按规定扭力拧紧紧固,爬升套架内的滚轮与塔身标准节间的间隙是否调整好,操作杆是否回到是中间位置以及液压系统的电源是否切断。

7、3塔吊安全操作

✧ 操作人员必须在接到指挥信号后方可进行操作,操作前必须鸣笛,操作时应集中

精力。

正弘蓝堡湾二期9#楼 ✧ 司机必须严格按照起重性能表中规定的幅度和起重量进行工作,不许超载使用。 ✧ 起重机不许斜拉和斜吊物品,并禁止用于拨桩等类似用于拔桩等类似的作业。严

格遵守塔吊“十不准”的规定。

✧ 工作中塔机梯上严禁有人,并不得在工作中进行调整或维修等作业。

✧ 工作时严禁闲人走进臂架活动范围以内。

✧ 液压系统安全阀的数值、电器系统保护装置的调整什及其它机械、结构部件的调

整什均不得随意改动。

7、4塔吊防撞措施

✧ B 塔机工作时应注意相互之间的位置,并在安装过程中采取不同的安装高度,以

避免两塔机的起重相互碰撞。

✧ 受周围建筑的影响,特别是B 塔在回转半径内不能自由回转,如遇大风等恶劣天

气影响,塔臂必会撞到东侧相临建筑物上造成事故。因此必须在适当位置设置地锚,在塔吊停止后,及时将吊钩挂在地锚上,以限制塔臂自由摆动,防止塔臂旋转撞击相临建筑物。

7、5塔吊应经常进行查检查、维修和保养,传动部分应有足够的润滑油,对易损件必须经常进行检查、维修或更换。对机械的螺栓,特别是经常振动的部位零件,如塔身连接螺栓应检查是否松动,如有松动则必须拧紧或更换。

7、5、1机械设备的维护和保养

各机构的制动器应经常进行检查和调整,制动瓦和制动轮的间隙,保证灵活可靠,

其间隙保证0.5-1.0mm 之间,在摩擦面上不应有污物存在,遇有污物必须用汽油或稀料洗掉。

减速箱、变速箱、啮合齿轮等各部分的润滑以及液压油均按规定要求进行。

要注意检查各部分钢丝绳有无断丝和松动现象,如有超过规定,必须立即更换。 经常检查各部位的连接情况,如有松动应及时拧紧。塔身连接螺栓应在塔身受压

时检查松紧度。所有连接必须装有开口销,并需张开。

经常检查各机构运转是否正常和有无噪音。

正弘蓝堡湾二期9#楼 装、拆和调整回转机构时,要注意保证回转机构行走齿轮减速器的中心与齿轮的

中心平行,间隙要适中。

7、5、2电气系统维护和保养

经常检查所有的电线、电缆有无损伤,要及时的包扎和更换已损伤的部分。

遇到电动机有过热的现象要及明停车,排除故障后在继续进行作业,电机轴承润

滑要良好。

集电环及其它部分电刷,其接触面要保持清洁,调整电刷压力,使其接触面积不

小于50%。

各控制箱、配电箱要经常保持清洁,及时清扫电器设备上的灰尘。

各安全装置的行程开关的触点开闭必须可靠,触点弧坑应及时磨光。

每年定期摇侧保护接地电阻两次,保证不大于4欧姆。

7、5、3液压爬升系统的维护和保养

使用液压油严格按照润滑表中的规定进行加油、换油并清洗油箱内部。

溢流阀的压力调整后,不得随意更动,每次进行爬升前,应用油压表检查其压力

是否正常。

应经常检查各部件接是否紧固严密,不准有漏油现象。

滤油器应经常检查是否堵塞,检查安全阀的使用调整值是否有变动。

油缸、油泵和控制阀,如发现有渗漏应及时检修。

在冬季启动时,要启动、停止反复数次,待油温上升和控制阀转动灵活后再正式

使用。

8、塔吊稳定性计算

8、1地基承载能力验算

本工程两台塔吊基础均座落在裙楼基础筏板以下,根据河南工程水文地质有限公司勘察院工程勘察报告中-12.07米处的承载能力特征值fa 大于要求的地基承载力200Kpa 。因此,地基承载能力满足要求。

8、2基础底板抗弯能力验算

按塔吊使用说明书中要求基础底板所受弯矩最大值为:

正弘蓝堡湾二期9#楼 Mmax=190T ·m

基础底板截面积为6000×1350,设计仅考虑底部钢筋的作用,混凝土保护层按70mm 考虑,即

As=Mmax/fy h o =190×107/(310×1280)=4788.31(mm2)

按Φ20@170配置,35Φ20(公称截面积为314mm 2)钢筋截面积为

As=35×314=10990(mm2)

满足要求。

施工现场平面布置图见下页:

正弘蓝堡湾二期9#楼

郑州一建第二十二项目部

2010年9月16日


相关内容

  • 多台塔吊交叉作业方案
  • 多台塔吊交叉作业方案 目 录 目 录.................................................................................................................................... ...

  • 塔吊设计.安装施工方案
  • 目 录 1.塔吊选型及需用量 ............................................................................................. 1 2.塔吊的平面布置 ............................. ...

  • 4结构内设置塔吊基础的施工方法
  • 结构内设置塔吊基础的施工方法 张 哲 江苏省苏中建设集团股份有限公司 邮编:226600 [摘 要]:本文介绍了结构内设置塔吊的塔基施工的几种做法,同时对各种做法的施工方法.难点.工艺效果等进行了分析和对比. [关键词]:塔吊 塔基 基础下沉 防水 随着社会经济和建筑行业的迅速发展,大型公建项目呈现 ...

  • 大型起重机械安拆监理实施细则
  • 目 录 第一章 工程概况--------------------------------------------------------- 1 第二章 监理工作依据----------------------------------------------------- 1 第三章 安全监理人员职责 ...

  • 塔吊安装.检测报验流程
  • 塔吊安装报验流程 塔吊安装报验流程 一.建筑施工单位现场确定塔吊(施工升降机)型号 1.建筑施工单位施工现场确定塔吊(施工升降机)型号,(项目部 提前1个月报计划新设备备案需要时间): 2.确定租赁单位,租赁单位确定设备厂家,购买设备,租赁单位负 责质安站备案(设备备案等费用租赁单位承担): 3.项 ...

  • 630.80.40塔吊施工方案
  • 松原坤茂大厦 施工方案 编制人: 审批人: 二○一一年五月 塔吊及人货电梯 目 录 第一节 塔吊施工方案 一.塔吊平面布置 二.现场塔机使用部位及参数 三.QTZ80.63塔吊基础地耐力验算 四.QTZ40塔吊基础地耐力验算 五.塔吊安装 六.安装塔吊安全注意事项 七.多台塔吊安全作业防碰撞措施 八 ...

  • QTZ40塔吊安装施工方案
  • 1. 目的 为保证红沿河核电华兴生活营地一期工程QTZ40C塔吊安全顺利地安装,达到规范标准要求,根据QTZ40C塔机的技术性能和施工现场作业环境,特制定本施工方案. 2. 适用范围 本施工方案适用于红沿河核电华兴生活营地一期工程QTZ40C平臂自升式塔式起重机的安装.顶升作业. 3. 参考文件 Q ...

  • 塔吊安装安全监理细则
  • 平安金融中心 6#塔吊安装 安全监理实施细则 编 制 : 审 批 : 上海市建设工程监理有限公司 平安金融中心监理项目部 批准时间: 年 月 日 目 录 一.危险性较大的分部分项工程安全监理工作的特点和施工现场的环境状况„„„3 二.编制依据„„„„„„„„„„„„„„„„„„„„„„„„„„„„„ ...

  • 塔式起重机安装拆除专项施工方案
  • 目 录 一.编制依据............................................................................................. 2 二.工程概况...................................... ...