泰安市自来水公司职工食堂及活动中心
一般抹灰和内外墙涂饰施工专项施工方案
编制: 张吉孟
审核: 王刚
批准: 戚树宏
2011-9-19
目 录
一、 二、 三、 四、 五、 六、 七、 八、
工程概况 ·························································································· 2 基本安全措施 ·················································································· 2 编制依据 ·························································································· 2 施工准备 ·························································································· 2 施工进度计划 ·················································································· 3 施工过程 ·························································································· 3 施工安全措施 ·················································································· 6 危险源清单及控制措施··································································· 6
一般抹灰和内外墙涂饰工程施工方案
一、 工程概况
本工程为位泰安市自来水公司“职工食堂及活动中心”位于泰安市迎胜东路以北自来水院内。
基本安全措施
1、施工前必须要向有关作业人员逐级进行安全技术及施工方案交底,并作好记录。 2、所有人员进场前,必须接受三级安全教育,否则,拒绝入场。
3、所有施工人员必须穿戴好合格的劳保用品(安全帽、防护眼镜、带钢头的工作 鞋,戴工作手套)后,才能进入施工现场。
4、所有施工设备必须经过安全工程师检查合格后,才能进场作业。 5、严禁随意随地抽烟,必须在现场指定的吸烟区抽烟。 6、严禁酒后上岗作业。 7、不得在施工场地奔跑。
二、 编制依据
施工图纸和施工验收规范。
三、 施工准备
(一)技术准备
组织施工人员掌握和了解施工中的细节,对作业人员进行技术、安全交底,让作业人员了解作业情况,应注意的事项。
(二)劳动力准备
作业人员计划,根据施工进度定。 (三) 机具工具准备
一般抹灰:磅秤、孔径5mm 筛子、手推车、铁板、铁锹、平锹、大桶、灰槽、胶皮管、水勺、灰勺、小水桶、喷壶、托灰板、木抹子、铁抹子、阴(阳) 角抹子、塑料抹子、大杠、中杠、2m 靠尺板、托线板、八字尺、5~7mm 厚方口靠尺、软刮尺、方尺、铁制水平尺、盒尺、钢丝刷、长毛刷、鸡腿刷、笤帚、粉线包、小白线、錾子、锤子、钳子、钉子、钢筋卡子、线坠、胶鞋、工具袋等。
内外墙面天棚涂饰涂饰:脚手板、腻子托板、滚筒、刷子、排笔、小漆桶、砂纸、橡皮刮板、腻子槽、擦布、棉丝、半截大桶等。 (四)材料准备
水泥、中砂、石灰膏、钢丝网、大白粉、苯丙涂料、外墙涂料等。
四、 施工进度计划
根据施工进度实际情况。
五、 施工过程
(一)一般抹灰工程
基层处理(凿除原粉刷层)→清理基层(砼面淋水拉毛)→砼与砖墙交接位置挂钢丝网→吊直、套方、找规矩、贴灰饼→墙面冲筋(设置标筋) →做护角→抹水泥窗台板→抹底灰→抹中层灰→抹水泥砂浆罩面灰(包括水泥踢脚板、墙裙等) →抹墙面罩面灰→养护
1、抹灰前基层表面的尘土、污垢等应清除干净,并应洒水润湿,砼表面要用 1:1水泥砂浆提前2-3天甩浆,并浇水养护。外墙抹灰施工前应先安装门窗框,并应将原墙体裂缝修补完毕。
2、为了控制抹灰的平整度,先在基层拉水平和垂直控制线,在基层做平面控制标记的砂浆灰饼40*40@2000左右,待控制灰饼6-7成干时开始批灰,批灰厚度20mm ,批灰过程中随时检查的粉刷表面的垂直度和平整度,发现问题及时修正。
3、批灰所用的材料的品种和性能应复核设计要求,外墙(楼梯间等)用1:3水泥砂浆厚做基层,1:2水泥砂浆光面。内墙和天棚批灰用1:1:6混合砂浆打底,1:1:4混合砂浆光面。
4、抹灰层应分层进行,当抹灰总厚度大于或等于35mm 时,应采取加强措施,不同材料基体交接处的批灰,应采取防开裂加强措施,当采用加强网时,加强网与各基体的搭接宽度不应小于100mm 。
5、抹灰层与基层之间及各抹灰层之间必须粘结牢固,抹灰层应无脱层、空鼓,面层应无爆灰和裂缝。 6、应注意的质量问题
(1)粘结不牢、空鼓、裂缝:加气混凝土墙面抹灰,最常见通病之一就是次层与基体之间粘结不牢、空鼓、裂缝。主要原因是基层清扫不干净,用水冲刷,湿润不够,
不刮素水泥浆。由于砂浆在强度增长、硬化过程,自身产生不均匀的收缩应力,形成干缩裂缝。改进措施,可采用喷洒防裂剂或涂刷掺801胶的素水泥浆,增加粘结作用,减少砂浆的收缩应力,提高砂浆早期抗拉强度,改进抹灰基层处理及砂浆配合比是解决加气混凝土墙面抹面空鼓、裂缝的关键。同时砂浆表面抗拉强度的提高,足以抗拒砂浆表面的收缩应力,待砂浆强度增长以后,就足以承受收缩应力的影响,从而阻止空鼓、干缩、裂缝的出现。
(2)抹灰层过厚:抹灰层的厚度大大超过规定,尤其是一次成活,将抹灰层坠裂。抹灰层的厚度应通过冲筋进行控制,保持15~20mm 为宜。操作时应分层、间歇抹灰,每遍厚度宜为7~8mm ,应在第一遍灰终凝后再抹第二遍,切忌一遍成活。
(3)门窗框边缝不塞灰或塞灰不实,预埋木砖间距大,木砖松动,反复开关振动, 在窗框两侧产生空鼓、裂缝:应把门窗塞缝当作一个工序由专人负责,木砖必须预埋在混凝土砌块内,随着墙体砌筑按规定间距摆放。加气混凝土墙体的门框周边宜做成钢筋混凝土小柱,小柱内预埋木砖最为妥当。
6、质量要求符合《建筑装饰装修工程施工质量验收规范》(GB50210-2001)的规定。
(二)涂饰工程
检查验收墙面基层→按设计图纸要求配制内外墙饰面基层腻子→修阴阳角洞口边 砂纸打磨→涂料配制→油第一层涂料→油第二层涂料 1、基层处理:
铲除装修表面的灰块、浮渣等杂物,用清洗剂和清水洗净表面油污,干燥后再用棕刷将表面灰尘清扫干净。
2、刮腻子补孔:用腻子将墙面的麻面、蜂窝、洞眼等缺残处刮平补好。
3、刮腻子前在混凝土墙面上先喷、刷一道胶水(水:乳液为5:1)要喷刷均匀, 不得有遗
漏。满刮腻子, 刮腻子时应横竖刮, 即第一遍腻子横向刮, 第二遍腻子竖向刮。注意按搓和收头时腻子要刮净, 每道腻子干燥后应用砂纸打磨, 将腻子磨平后并将浮尘擦净。 4、涂刷第一遍涂料, 涂刷时应先上后下。干燥后复补腻子, 待复补腻子干燥后用砂纸磨光。隔1天后, 可涂刷第二遍。
5、在第二遍操作时不宜来回多次涂刷, 以避免溶松第一遍漆膜, 或出现显著的漆刷涂饰痕迹, 影响质量。
6、在第三遍涂料施工时, 注意涂料遮盖力情况, 以便随时掌握和调整涂饰的松紧, 确保涂料色泽的均匀性。
7、清扫:清扫飞溅乳胶、清除施工准备时预先覆盖在踢脚板、水暖电气设备及门窗等部位的遮盖物。 8、质量验收
(1)、水性涂料涂饰工程所用涂料的品种型号和性能应符合设计要求 检验方法:检查产品合格证书性能检测报告和进场验收记录 (2)、 水性涂料涂饰工程的颜色图案应符合设计要求 检验方法:观察
(3)、 水性涂料涂饰工程应涂饰均匀粘结牢固不得漏涂透底起皮和掉粉 检验方法:观察手摸检查
(4)、 水性涂料涂饰工程的基层处理应符合下表的要求
六、 施工安全措施 1、用警示带隔离施工区域, 2、戴好防护眼镜,手套等PPE 。
3、抹灰及涂料用脚手架操作层外侧要挂安全网。
七、 危险源清单及控制措施
1、电气伤害
控制措施:检查机械性能,要有防漏电装置; 2、脚手架倾塌
控制措施:脚手架与墙体要有拉结杆,要有剪刀撑,架子不能随便乱拆,架子搭设后要经业主验收合格后才能使用。
泰安市自来水公司职工食堂及活动中心
一般抹灰和内外墙涂饰施工专项施工方案
编制: 张吉孟
审核: 王刚
批准: 戚树宏
2011-9-19
目 录
一、 二、 三、 四、 五、 六、 七、 八、
工程概况 ·························································································· 2 基本安全措施 ·················································································· 2 编制依据 ·························································································· 2 施工准备 ·························································································· 2 施工进度计划 ·················································································· 3 施工过程 ·························································································· 3 施工安全措施 ·················································································· 6 危险源清单及控制措施··································································· 6
一般抹灰和内外墙涂饰工程施工方案
一、 工程概况
本工程为位泰安市自来水公司“职工食堂及活动中心”位于泰安市迎胜东路以北自来水院内。
基本安全措施
1、施工前必须要向有关作业人员逐级进行安全技术及施工方案交底,并作好记录。 2、所有人员进场前,必须接受三级安全教育,否则,拒绝入场。
3、所有施工人员必须穿戴好合格的劳保用品(安全帽、防护眼镜、带钢头的工作 鞋,戴工作手套)后,才能进入施工现场。
4、所有施工设备必须经过安全工程师检查合格后,才能进场作业。 5、严禁随意随地抽烟,必须在现场指定的吸烟区抽烟。 6、严禁酒后上岗作业。 7、不得在施工场地奔跑。
二、 编制依据
施工图纸和施工验收规范。
三、 施工准备
(一)技术准备
组织施工人员掌握和了解施工中的细节,对作业人员进行技术、安全交底,让作业人员了解作业情况,应注意的事项。
(二)劳动力准备
作业人员计划,根据施工进度定。 (三) 机具工具准备
一般抹灰:磅秤、孔径5mm 筛子、手推车、铁板、铁锹、平锹、大桶、灰槽、胶皮管、水勺、灰勺、小水桶、喷壶、托灰板、木抹子、铁抹子、阴(阳) 角抹子、塑料抹子、大杠、中杠、2m 靠尺板、托线板、八字尺、5~7mm 厚方口靠尺、软刮尺、方尺、铁制水平尺、盒尺、钢丝刷、长毛刷、鸡腿刷、笤帚、粉线包、小白线、錾子、锤子、钳子、钉子、钢筋卡子、线坠、胶鞋、工具袋等。
内外墙面天棚涂饰涂饰:脚手板、腻子托板、滚筒、刷子、排笔、小漆桶、砂纸、橡皮刮板、腻子槽、擦布、棉丝、半截大桶等。 (四)材料准备
水泥、中砂、石灰膏、钢丝网、大白粉、苯丙涂料、外墙涂料等。
四、 施工进度计划
根据施工进度实际情况。
五、 施工过程
(一)一般抹灰工程
基层处理(凿除原粉刷层)→清理基层(砼面淋水拉毛)→砼与砖墙交接位置挂钢丝网→吊直、套方、找规矩、贴灰饼→墙面冲筋(设置标筋) →做护角→抹水泥窗台板→抹底灰→抹中层灰→抹水泥砂浆罩面灰(包括水泥踢脚板、墙裙等) →抹墙面罩面灰→养护
1、抹灰前基层表面的尘土、污垢等应清除干净,并应洒水润湿,砼表面要用 1:1水泥砂浆提前2-3天甩浆,并浇水养护。外墙抹灰施工前应先安装门窗框,并应将原墙体裂缝修补完毕。
2、为了控制抹灰的平整度,先在基层拉水平和垂直控制线,在基层做平面控制标记的砂浆灰饼40*40@2000左右,待控制灰饼6-7成干时开始批灰,批灰厚度20mm ,批灰过程中随时检查的粉刷表面的垂直度和平整度,发现问题及时修正。
3、批灰所用的材料的品种和性能应复核设计要求,外墙(楼梯间等)用1:3水泥砂浆厚做基层,1:2水泥砂浆光面。内墙和天棚批灰用1:1:6混合砂浆打底,1:1:4混合砂浆光面。
4、抹灰层应分层进行,当抹灰总厚度大于或等于35mm 时,应采取加强措施,不同材料基体交接处的批灰,应采取防开裂加强措施,当采用加强网时,加强网与各基体的搭接宽度不应小于100mm 。
5、抹灰层与基层之间及各抹灰层之间必须粘结牢固,抹灰层应无脱层、空鼓,面层应无爆灰和裂缝。 6、应注意的质量问题
(1)粘结不牢、空鼓、裂缝:加气混凝土墙面抹灰,最常见通病之一就是次层与基体之间粘结不牢、空鼓、裂缝。主要原因是基层清扫不干净,用水冲刷,湿润不够,
不刮素水泥浆。由于砂浆在强度增长、硬化过程,自身产生不均匀的收缩应力,形成干缩裂缝。改进措施,可采用喷洒防裂剂或涂刷掺801胶的素水泥浆,增加粘结作用,减少砂浆的收缩应力,提高砂浆早期抗拉强度,改进抹灰基层处理及砂浆配合比是解决加气混凝土墙面抹面空鼓、裂缝的关键。同时砂浆表面抗拉强度的提高,足以抗拒砂浆表面的收缩应力,待砂浆强度增长以后,就足以承受收缩应力的影响,从而阻止空鼓、干缩、裂缝的出现。
(2)抹灰层过厚:抹灰层的厚度大大超过规定,尤其是一次成活,将抹灰层坠裂。抹灰层的厚度应通过冲筋进行控制,保持15~20mm 为宜。操作时应分层、间歇抹灰,每遍厚度宜为7~8mm ,应在第一遍灰终凝后再抹第二遍,切忌一遍成活。
(3)门窗框边缝不塞灰或塞灰不实,预埋木砖间距大,木砖松动,反复开关振动, 在窗框两侧产生空鼓、裂缝:应把门窗塞缝当作一个工序由专人负责,木砖必须预埋在混凝土砌块内,随着墙体砌筑按规定间距摆放。加气混凝土墙体的门框周边宜做成钢筋混凝土小柱,小柱内预埋木砖最为妥当。
6、质量要求符合《建筑装饰装修工程施工质量验收规范》(GB50210-2001)的规定。
(二)涂饰工程
检查验收墙面基层→按设计图纸要求配制内外墙饰面基层腻子→修阴阳角洞口边 砂纸打磨→涂料配制→油第一层涂料→油第二层涂料 1、基层处理:
铲除装修表面的灰块、浮渣等杂物,用清洗剂和清水洗净表面油污,干燥后再用棕刷将表面灰尘清扫干净。
2、刮腻子补孔:用腻子将墙面的麻面、蜂窝、洞眼等缺残处刮平补好。
3、刮腻子前在混凝土墙面上先喷、刷一道胶水(水:乳液为5:1)要喷刷均匀, 不得有遗
漏。满刮腻子, 刮腻子时应横竖刮, 即第一遍腻子横向刮, 第二遍腻子竖向刮。注意按搓和收头时腻子要刮净, 每道腻子干燥后应用砂纸打磨, 将腻子磨平后并将浮尘擦净。 4、涂刷第一遍涂料, 涂刷时应先上后下。干燥后复补腻子, 待复补腻子干燥后用砂纸磨光。隔1天后, 可涂刷第二遍。
5、在第二遍操作时不宜来回多次涂刷, 以避免溶松第一遍漆膜, 或出现显著的漆刷涂饰痕迹, 影响质量。
6、在第三遍涂料施工时, 注意涂料遮盖力情况, 以便随时掌握和调整涂饰的松紧, 确保涂料色泽的均匀性。
7、清扫:清扫飞溅乳胶、清除施工准备时预先覆盖在踢脚板、水暖电气设备及门窗等部位的遮盖物。 8、质量验收
(1)、水性涂料涂饰工程所用涂料的品种型号和性能应符合设计要求 检验方法:检查产品合格证书性能检测报告和进场验收记录 (2)、 水性涂料涂饰工程的颜色图案应符合设计要求 检验方法:观察
(3)、 水性涂料涂饰工程应涂饰均匀粘结牢固不得漏涂透底起皮和掉粉 检验方法:观察手摸检查
(4)、 水性涂料涂饰工程的基层处理应符合下表的要求
六、 施工安全措施 1、用警示带隔离施工区域, 2、戴好防护眼镜,手套等PPE 。
3、抹灰及涂料用脚手架操作层外侧要挂安全网。
七、 危险源清单及控制措施
1、电气伤害
控制措施:检查机械性能,要有防漏电装置; 2、脚手架倾塌
控制措施:脚手架与墙体要有拉结杆,要有剪刀撑,架子不能随便乱拆,架子搭设后要经业主验收合格后才能使用。