施工现场临时用电负荷计算
一、临时设备用电量统计表
二、临时用电计算
塔吊:13台
Pe=56.7kw,kx=0.65,cos=0.65,JC=15%tg=1.17 P js =2Pe
=2×56.7×0.39=44.2kw×13台=574.6kw
外跨电梯:5部
Pe=44kw,kx=0.7, cos=0.7,Jc=30% ,tg=1.02 Pjs=2·Pe ·kx ·
=2×44×0.7×0.54=33.3kw×26部=865.8kw
Qjs=Pjs·tq =33.3×1.02=34kvAr×5部=170kvAr 钢筋切断机:
Pe=4kw,kx=0.7, cos=0.75,tg =0.88 Pjs=kx·Pe=0.7×4=2.8kw×8台=22.4kw Qjs=Pjs·tq =2.8×0.88=2.5kvAr×3台=5kvAr 钢筋弯曲机:
Pe=3kw,kx=0.7, cos=0.75,tg =0.88 Pjs=kx·Pe=0.7×3=2.1kw×8台=16.8kw
Qjs=Pjs·tq =2.1×0.88=1.85kvAr×8台=14.8kvAr 钢筋对焊焊机:
Pe=100kvA, cos=0.45,Jc=65%, P js = cos·
·
380V tg=1.98
=100×0.45×0.8×1.73=62.3kw
Q js =Pjs ·tq =62.3kw×1.98=123.4kvAr 交流电焊机:
Pe=21kvA, cos=0.45,Jc=65%,P js = Pe·cos ·
380V tg=1.98
·=21×0.45×0.8×1.73=13×6=78kw
Q js =Pjs ·tq =13×1.98=25.7kvAr×6=154.2kvAr 木工电锯: Pe=3KW
Kx=0.7
Pjs=Kx·Pe=0.7×8=5.6kw Pjs=Pjs·无齿锯: Pe=2.1kw
Kx=0.6
=2.1×0.88=1.85kw
Pjs=Kx·Pe=0.6×2.2=1.32kw Pjs=Pjs·套丝机: Pe=2.2kw
Kx=0.7
=1.32×0.88=1.16kvAr
Pjs=Kx·Pe=0.7×2.2=1.54kw Pjs=Pjs·
=1.54×0.88=1.34kvAr
插入式振动器: Pe=2.2kw
Kx=0.75
Pjs=Kx·Pe=2.2×0.75=1.65kw×4=6.6kw Pjs=Pjs·
=1.65×0.88=1.45×60台=29kvAr
镇镝灯照明:20具 Pe=3.5kw
Kx=1.1
Pjs=Kx·Pe=3.5×1.1=3.85kw×20具=77kw 生活用电蒸箱:2台 Pe=24kw
Pjs=24KW×2=48KW
办公室照明:
Pe=10kw Pj s =33KW分在380V 三相上 现场照明: Pe=12kw
Kx=1.1 Pjs=12×11=13.2KW
生活用电热水箱 Pe=9kw Pjs =9KW 行灯变压器:3台 Pe=5KVA Pjs=Pe·
Jc=65% cos =0.87
380v
=3.48×1.33=4.6×3台=43.8kvAr
取总有无功率总系数为Kx=0.47 则 Pjz=
Pe=88.4+99.9+5.6+4.2+62.3+74.8+78+2.1+1.32+1.54+6.6+2.1+23.1+48+33+13.2+9+43.8=587.96KW×0.47=276.34KW.
Qjz=
Qj=103.4+102+5+3.7+123.4+148+154.2+1.85+1.16+1.34+5.8+2.27+23.1+43.8=719.02kvAr ×0.47=837.94kvAr
总视在计算负荷: Sj2=
变压器容量:
Sb=
因此,现场提供2台415KV 的变压器方可满足施工用电的要求。 总计算线电流:
Ij2=
按允许电压损失核算导线堆面积(导线按箱总线考虑) C=83 电压损失按5%,则
S=
三、电缆埋地及接地要求
本工程按JGJ46-2005《施工现场临时用电安全技术规范》的有关规定进行施工。临时配电系统采用三级配电保护,线路采用埋地和架空敷设两种方式。
本工程所使用临电设施应符合国家及地方有关临时用电管理规定,配电箱、柜符合三相五线制接零保护系统TN-S 要求。
二级低压配电柜处PE 线各做一组重复接地。重复接地
从总箱到配电柜的电缆沿护拦边明敷设固定,并加设可靠保护,电缆经过施工大门和建筑物临建处埋地深度0.8米敷设,并穿铁管保护。
固定式配电柜距地面0.3米,二级电箱的下底与地面的垂直距离应大于1.3米。
埋设要求:电缆埋设深度不小800mm, 并在电缆上下均铺不小于5mm 厚细砂, 然后覆盖红砖保护层, 埋地电缆线路与附近热力管线平行间距不小于1.2m, 交叉
间距不小于1m ,与其它管线平行间距不小于0.5m 。埋地电缆穿过马路须加套管保护套, 电缆接头必须牢固可靠, 并做好绝缘包扎,保持足够的绝缘强度, 不得承受张力。埋地电缆的接头设在地面的接线盒时,接线盒应防水、防机械损伤、远离易燃易腐蚀场所。
施工现场临时用电负荷计算
一、临时设备用电量统计表
二、临时用电计算
塔吊:13台
Pe=56.7kw,kx=0.65,cos=0.65,JC=15%tg=1.17 P js =2Pe
=2×56.7×0.39=44.2kw×13台=574.6kw
外跨电梯:5部
Pe=44kw,kx=0.7, cos=0.7,Jc=30% ,tg=1.02 Pjs=2·Pe ·kx ·
=2×44×0.7×0.54=33.3kw×26部=865.8kw
Qjs=Pjs·tq =33.3×1.02=34kvAr×5部=170kvAr 钢筋切断机:
Pe=4kw,kx=0.7, cos=0.75,tg =0.88 Pjs=kx·Pe=0.7×4=2.8kw×8台=22.4kw Qjs=Pjs·tq =2.8×0.88=2.5kvAr×3台=5kvAr 钢筋弯曲机:
Pe=3kw,kx=0.7, cos=0.75,tg =0.88 Pjs=kx·Pe=0.7×3=2.1kw×8台=16.8kw
Qjs=Pjs·tq =2.1×0.88=1.85kvAr×8台=14.8kvAr 钢筋对焊焊机:
Pe=100kvA, cos=0.45,Jc=65%, P js = cos·
·
380V tg=1.98
=100×0.45×0.8×1.73=62.3kw
Q js =Pjs ·tq =62.3kw×1.98=123.4kvAr 交流电焊机:
Pe=21kvA, cos=0.45,Jc=65%,P js = Pe·cos ·
380V tg=1.98
·=21×0.45×0.8×1.73=13×6=78kw
Q js =Pjs ·tq =13×1.98=25.7kvAr×6=154.2kvAr 木工电锯: Pe=3KW
Kx=0.7
Pjs=Kx·Pe=0.7×8=5.6kw Pjs=Pjs·无齿锯: Pe=2.1kw
Kx=0.6
=2.1×0.88=1.85kw
Pjs=Kx·Pe=0.6×2.2=1.32kw Pjs=Pjs·套丝机: Pe=2.2kw
Kx=0.7
=1.32×0.88=1.16kvAr
Pjs=Kx·Pe=0.7×2.2=1.54kw Pjs=Pjs·
=1.54×0.88=1.34kvAr
插入式振动器: Pe=2.2kw
Kx=0.75
Pjs=Kx·Pe=2.2×0.75=1.65kw×4=6.6kw Pjs=Pjs·
=1.65×0.88=1.45×60台=29kvAr
镇镝灯照明:20具 Pe=3.5kw
Kx=1.1
Pjs=Kx·Pe=3.5×1.1=3.85kw×20具=77kw 生活用电蒸箱:2台 Pe=24kw
Pjs=24KW×2=48KW
办公室照明:
Pe=10kw Pj s =33KW分在380V 三相上 现场照明: Pe=12kw
Kx=1.1 Pjs=12×11=13.2KW
生活用电热水箱 Pe=9kw Pjs =9KW 行灯变压器:3台 Pe=5KVA Pjs=Pe·
Jc=65% cos =0.87
380v
=3.48×1.33=4.6×3台=43.8kvAr
取总有无功率总系数为Kx=0.47 则 Pjz=
Pe=88.4+99.9+5.6+4.2+62.3+74.8+78+2.1+1.32+1.54+6.6+2.1+23.1+48+33+13.2+9+43.8=587.96KW×0.47=276.34KW.
Qjz=
Qj=103.4+102+5+3.7+123.4+148+154.2+1.85+1.16+1.34+5.8+2.27+23.1+43.8=719.02kvAr ×0.47=837.94kvAr
总视在计算负荷: Sj2=
变压器容量:
Sb=
因此,现场提供2台415KV 的变压器方可满足施工用电的要求。 总计算线电流:
Ij2=
按允许电压损失核算导线堆面积(导线按箱总线考虑) C=83 电压损失按5%,则
S=
三、电缆埋地及接地要求
本工程按JGJ46-2005《施工现场临时用电安全技术规范》的有关规定进行施工。临时配电系统采用三级配电保护,线路采用埋地和架空敷设两种方式。
本工程所使用临电设施应符合国家及地方有关临时用电管理规定,配电箱、柜符合三相五线制接零保护系统TN-S 要求。
二级低压配电柜处PE 线各做一组重复接地。重复接地
从总箱到配电柜的电缆沿护拦边明敷设固定,并加设可靠保护,电缆经过施工大门和建筑物临建处埋地深度0.8米敷设,并穿铁管保护。
固定式配电柜距地面0.3米,二级电箱的下底与地面的垂直距离应大于1.3米。
埋设要求:电缆埋设深度不小800mm, 并在电缆上下均铺不小于5mm 厚细砂, 然后覆盖红砖保护层, 埋地电缆线路与附近热力管线平行间距不小于1.2m, 交叉
间距不小于1m ,与其它管线平行间距不小于0.5m 。埋地电缆穿过马路须加套管保护套, 电缆接头必须牢固可靠, 并做好绝缘包扎,保持足够的绝缘强度, 不得承受张力。埋地电缆的接头设在地面的接线盒时,接线盒应防水、防机械损伤、远离易燃易腐蚀场所。