楼地面防渗漏节点做法

楼地面防渗漏节点做法

集团工程采购与成本管理部 二○○九年十一月十八日

楼地面防渗漏节点做法

目录

1.一般要求........................................................1

1.1 楼板压槽...........................................................................................................................1 1.2 防水材料...........................................................................................................................1 1.3 内保温防水.......................................................................................................................1

2.厨房地面防渗漏做法..............................................1

2.1 无防水厨房地面...............................................................................................................1 2.2 有防水厨房地面...............................................................................................................2

3.卫生间地面防渗漏做法............................................3

3.1 一般卫生间防渗漏做法...................................................................................................3 3.2 沉箱式卫生间防渗漏做法...............................................................................................5

4.穿楼板管道防渗漏做法............................................8

4.1 无套管穿楼板管道...........................................................................................................8 4.2 有套管穿楼板管道.........................................................................................................10 4.3 穿楼板管道止水节做法.................................................................................................11

5.地漏节点防渗漏做法.............................................13 6.穿楼板烟风道防渗漏做法.........................................15

6.1 厨房、卫生间烟风道做法(1)...................................................................................15 6.2 厨房、卫生间烟风道做法(2)...................................................................................16 6.3 沉箱式卫生间烟风道做法(1)...................................................................................18 6.4 沉箱式卫生间烟风道做法(2)...................................................................................19

7.管道井防渗漏做法...............................................21

楼地面防渗漏节点做法

1.一般要求

1.1 楼板压槽

室内管道不宜采用在结构楼板上压槽埋设的做法,以免对结构楼板造成破坏。

当不得不在结构楼板上采用压槽的方法埋设管道时,压槽深度不得超过钢筋保护层厚度且必须经过结构安全确认,埋管后必须用水泥砂浆填实。 1.2 防水材料

当厨房、卫生间采用地热采暖时,防水层不可采用聚氨酯等可挥发性防水材料。

墙面防水材料应选用与砂浆粘结较好的JS等防水材料,不得使用与砂浆粘结不好的防水材料,以免出现空鼓。 1.3 内保温防水

采用内保温做法时,墙面防水应粘贴在墙面基层上,不得做在保温层上。

2.厨房地面防渗漏做法 2.1 无防水厨房地面

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

2、闭水试验:

结构闭水试验,水深30~50mm,并比楼板最高处高出20mm以上,试验时间不小于6小时,发现渗漏需进行修补,然后再进行闭水试验,直至不漏为止。

3、饰面层

按设计要求施工面层, 完成面应比相邻厅房完成面低10~20mm。 质量控制点:

1、基层处理 2、闭水试验 3、面层施工

2.2 有防水厨房地面

水泥砂浆找平/找坡,最薄处不小于20mm,并坡向地漏,坡度1%左右。 完成面应坚固、平整、表面压光,不得有酥松、起砂和空鼓。 4、防水附加层

找平层/找坡层干燥后,在管周、管井、地漏、阴角等部位施工防水附加层。 防水附加层材料及做法与防水层相同。

管周、管井、地漏、烟风道防水附加层施工范围参见后续章节说明,墙角处沿墙高和楼板水平方向防水附加层范围各为150 mm。

5、防水层

附加层施工完成后,分多遍涂刷1.5mm II型JS防水涂料,四周上返高度超过地面完成面300mm,过门框向外延伸200mm。

6、闭水试验

防水层完成后将门口与地漏封堵,进行24小时闭水试验,水深30~50mm,并比楼板与道墙相接处高出20mm以上;

做好闭水试验观察记录,确认无渗漏后方可排水。如发现渗漏应分析原因并对渗漏部位进行整改,整改完成后再次进行闭水试验,直至无渗漏现象发生。

7、保护层/饰面层

毛坯房交房时,闭水试验合格后施工20mm厚1:3水泥砂浆保护层,并向地漏找坡; 装修房时,闭水试验合格后按设计要求施工饰面层,饰面层排水坡度和坡向必须正确,不得有倒泛水和积水现象。饰面层完成后最高点应比相邻厅/房完成面低10~20mm。

无论毛坯房的砂浆保护层还是装修房的饰面层,施工时均须做好对防水层的保护,不得损坏防水层。

质量控制点:

1、基层处理

2、结构闭水试验

3、找平/找坡层的坡度及坡向 4、防水层厚度、范围 5、闭水试验

6、面层平整度及坡度、坡向

3.卫生间地面防渗漏做法 3.1 一般卫生间防渗漏做法

做法说明:

卫生间地面完成面应比相邻/厅房完成面低20mm。根据卫生间与相邻厅/房的装饰面厚度确定卫生间结构板面降低高度。

卫生间周边后砌墙根部浇筑C20同墙厚素混凝土导墙,高度不小于200mm。 土建与水电安装专业应合理安排工序,必须先装好设备及管道,严禁在施工完成防水的地面、墙面上打眼凿洞。

地面防水施工前,应先完成设备管道、地漏、烟风道等的安装及根部封堵,并经闭水试验验收合格。

工艺流程:

基层处理——结构闭水试验——找平层/找坡层——防水附加层——防水层——闭水试

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

不得有倒泛水和积水现象。饰面层完成后最高点应比相邻厅/房完成面低20mm。

无论毛坯房的砂浆保护层还是装修房的饰面层,施工时均须做好对防水层的保护,不得损坏防水层。

质量控制点:

1、基层处理

2、结构闭水试验

3、找平/找坡层的坡度及坡向 4、防水层厚度、范围 5、闭水试验

6、面层平整度及坡度、坡向

3.2 沉箱式卫生间防渗漏做法

水泥砂浆找平/找坡,最薄处不小于20mm,并坡向侧排口,坡度1%左右。 完成面应坚固、平整、表面压光,不得有酥松、起砂和空鼓。 4、防水附加层

找平层/找坡层干燥后,在管周、管井、地漏、阴角等部位施工防水附加层。 防水附加层材料及做法与地面防水层相同。

管周、管井、地漏、烟风道防水附加层施工范围参见后续章节说明,墙角处沿墙高和楼板水平方向防水附加层范围各为250 mm。

5、防水层

附加层施工完成后,地面分多遍涂刷1.5mm JS防水涂料或1.5mm厚聚氨酯防水涂膜,四周上返高度超过地面完成面300mm,过门框向外延伸200mm。

浴缸、淋浴间墙面分多遍涂刷1.2mm 厚II型JS防水涂料,下部从墙根开始,高度到地面完成面1800mm处。

6、闭水试验

防水层完成后将门口与地漏、侧排口封堵,进行24小时闭水试验,水深30~50mm,并比楼板与导墙相接处高出20mm以上;

做好闭水试验观察记录,确认无渗漏后方可排水。如发现渗漏应分析原因并对渗漏部位进行整改,整改完成后再次进行闭水试验,直至无渗漏现象发生。

7、防水保护层

闭水试验合格后施工20mm厚1:3水泥砂浆保护层。保护层达到强度后方可安装管道。8、沉箱内管道安装

保护层达到强度后,按设计要求安装管道。 9、侧排口疏水层

侧排口200mm范围设置卵石疏水层并用无纺布包裹,以防水泥浆等堵塞侧排口。 10、地漏及立管周围包封

沉箱内有地漏或立管时,在地漏或立管四周浇100宽,200高C20细石混凝土。 11、轻质填层

铺设轻质填层,具体厚度以沉箱深度及饰面做法确定。 12、细石混凝土层

在填层上做40mm厚C20细石混凝土层,内配φ6@200单层双向钢筋。细石混凝土层应一次向地漏找坡压光,坡度不小于1%,并在四周根部阴角处抹半径不小于10mm圆角。

13、防水层

细石混凝土层干燥后,分遍涂刷1.5mm厚JS防水涂料或聚氨酯涂膜,四周上返高度超过地面完成面300mm,过门框向外延伸200mm。

浴缸、淋浴间墙面分多遍涂刷1.2mm 厚II型JS防水涂料,下部从墙根开始,高度到地面完成面1800mm处。

14、闭水试验

第三次24小时闭水试验,水面最浅处不小于30-50mm,并观察、记录,确认无渗漏后方可排水。

15、防水保护层/饰面层

毛坯房交房时,闭水试验合格后施工20mm厚1:3水泥砂浆保护层,并向地漏找坡; 装修房时,闭水试验合格后按设计要求施工饰面层,饰面层排水坡度和坡向必须正确,不得有倒泛水和积水现象。饰面层完成后最高点应比相邻厅/房完成面低20mm。

无论毛坯房的砂浆保护层还是装修房的饰面层,施工时均须做好对防水层的保护,不得

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

损坏防水层。

质量控制点:

1、基层处理

2、侧排口、管周封堵及结构闭水试验

3、第一道防水附加层、防水层厚度、范围和闭水试验 4、侧排口疏水层

5、地漏、管周细石混凝土包封 6、细石钢筋混凝土找平压光 7、第二道防水层 8、闭水试验

4.穿楼板管道防渗漏做法 4.1 无套管穿楼板管道

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

不得有倒泛水和积水现象。饰面层完成后最高点应比相邻厅/房完成面低20mm。

无论毛坯房的砂浆保护层还是装修房的饰面层,施工时均须做好对防水层的保护,不得损坏防水层。 质量控制点:

1、孔洞清理凿毛 2、混凝土密实度 3、嵌填密封膏 4、防水层 5、闭水试验

4.2 有套管穿楼板管道

构造做法:

1、放线定位

模板支好后在模板上测量放线,准确确定管道、套管位置。 2、套管固定

把套管牢固地固定在模板上并用胶布等密封两端。 3、浇筑楼板

浇筑楼板混凝土时一定注意套管周边密实。 4、套管清理

在安装管道前,先清除套管内的杂物,钢套管应清除铁锈,并在管壁刷防锈漆,等防锈漆干透之后安装管道。

5、安装管道

安装管道穿过套管,管道接口不得设在套管内,注意管道与套管间缝隙要一致并固定好管道。

6、填塞套管与管道间缝隙

用沥青油麻丝分两遍填充套管与管道间缝隙,挤密压实并在上下口各留20mm深凹槽。

7、打密封膏

在上下口凹槽内嵌填建筑密封膏。 8、结构闭水试验

临时堵住门口与地漏口,与楼地面同时进行24小时闭水试验,在套管周围设置围堰使水淹没套管,确认无渗漏后方可排水。如发现渗漏应分析原因并对渗漏部位进行整改处理,完成后再次进行闭水试验,直至无渗漏现象发生。

后续的找平层/找坡层、防水附加层、防水层、闭水试验、防水保护层/饰面层做法与楼地面做法相同,其中施工防水保护层时,应在套管周边找出较大坡度,面层施工保持此坡度,避免套管根部积水。 质量控制点:

1、套管定位及固定 2、套管清理

3、套管与管道间沥青麻丝密实度 4、打密封膏 5、闭水试验

6、防水附加层及防水层 7、面层坡度

4.3 穿楼板管道止水节做法

做法说明:

本做法用于卫生间、厨房、阳台等现浇楼板的管道穿板安装。

目前穿楼板的各种无套管管道,均是在结构施工时通过预留孔洞进行安装,管道安装完毕后分次堵塞细石混凝土的做法,但是,由于混凝土堵塞不密实以及收缩变形等原因,此处往往发生渗漏。

止水节既不需要套管,也不在楼板上留孔洞,又能有效解决传统施工方法所导致卫生间的渗漏问题。

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

7、管道安装

直接将管道插入止水节中,用粘结剂粘结管道与止水节。

楼地面的闭水试验、找平找坡及防水等参照楼地面做法执行。 质量控制点:

1、弹线定位 2、止水节固定 3、止水节保护 4、管道安装

5.地漏节点防渗漏做法

做法说明:

本做法适用于厨房、卫生间、阳台等处地漏节点的防渗漏处理。

楼地面向地漏处找坡不小于1%,且地漏口应比楼地面完成面低2~5mm。

为便于孔洞封堵,地漏孔洞在结构施工时须采用定型模板预留,做成上大下小状,上部直径大于下部40mm为宜。

地漏应距墙根一定距离,以便于施工和防渗漏;预留地漏孔洞位置应在模板上放线定位,并牢固固定孔洞定型模板。

工艺流程:

安装地漏——支模——浇注混凝土——结构闭水试验——打密封膏——找平找坡层——防水附加层——防水层——闭水试验——防水保护层/饰面层 节点图:

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

无论毛坯房的砂浆保护层还是装修房的饰面层,施工时均须做好对防水层的保护,不得损坏防水层。

质量控制点:

1、孔洞清理、凿毛、湿润 2、细石混凝土密实度 3、结构闭水试验 4、嵌填密封膏 5、防水层施工 6、面层坡度

6.穿楼板烟风道防渗漏做法 6.1 厨房、卫生间烟风道做法(1)

厨房、卫生间烟风道节点做法(1)

构造做法:

1、检查洞口

检查预留洞口尺寸及位置,不符合要求的要剔凿处理。 2、基层处理

清理干净洞口周边,理顺预留钢筋,根部凿毛并浇水湿润。 3、安装烟风道 安装烟风道时,须先在下部烟风道壁上口坐浆,然后从上部插入本节烟风道并与下节对齐,同时矫正烟风道垂直度、方正度,要求垂直度偏差±5mm、阴阳角偏差±5mm。

4、浇筑烟风道周边及反坎混凝土 混凝土下部支模必须牢固且不漏浆,楼板预留洞口与反坎一次浇成。反坎混凝土强度不得低于C20。

5、楼地面施工

烟风道安装、混凝土浇筑完成后,按照找平层/找坡层、防水附加层、防水层、闭水试验、饰面层等楼地面的做法施工完成楼地面。

其中防水附加层和防水层上反高度需高出楼地面完成面300mm以上,平面出反坎周边不小于200mm。

6、甩浆抹灰

在烟风道表面甩浆养护并抹灰。 质量控制点:

1、洞口检查、清理、凿毛及湿润 2、反坎混凝土密实度及高度 3、烟风道进场验收及安装

4、防水附加层和防水层以及施工范围 5、闭水试验

6、烟风道壁甩浆抹灰

6.2 厨房、卫生间烟风道做法(2)

做法说明:

结构施工时上下吊线,采用定型模板准确预留出烟风道孔洞位置和大小,并在楼板上后浇混凝土反坎,烟风道下部安装在反坎上,上部顶住结构楼板,上部与下部缝隙用水泥砂浆堵塞密实。

混凝土反坎宽不小于50mm,高出楼地面完成面不小于100mm,混凝土标号为C20。 烟风道制作高度=楼层净高-反坎高度-30mm,30mm为塞缝及调节高度。

烟风道安装前要对其尺寸及外观进行验收,表面不允许有裂缝,截面尺寸偏差在±5mm以内。

当烟风道周边墙体为砌体时,应先完成砌筑及抹灰施工,之后安装烟风道;最下层的烟风道应最后安装,以避免烟风道内垃圾无法清除。

此种安装方式有以下优点:

1、混凝土反坎起到较好的挡水作用,有效解决了烟风道根部的渗漏问题。

2、在烟风道表面甩浆养护及抹灰,饰面完成后烟风道与反坎外侧平齐,不出现凸台,

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

开裂,应在抹灰层中压入网格布。 质量控制点:

1、洞口检查、清理、凿毛及湿润 2、反坎混凝土密实度及高度 3、烟风道进场验收及安装 4、塞缝密实度

5、防水附加层和防水层以及施工范围 6、闭水试验

7、烟风道壁甩浆抹灰

6.3 沉箱式卫生间烟风道做法(1)

沉箱式卫生间烟风道节点做法(1)

构造做法:

1、检查洞口

检查复核预留洞口,尺寸及位置不符合要求的要剔凿处理。 2、基层处理

清理干净洞口周边,凿毛并浇水湿润。 3、安装烟风道 安装烟风道时,须先在下部烟风道壁上口坐浆,然后从上部插入本节烟风道并与下节对齐,同时矫正烟风道垂直度、方正度,要求垂直度偏差±5mm、阴阳角偏差±5mm。

4、浇筑烟风道周边及反坎混凝土 混凝土下部支模必须牢固且不漏浆,楼板预留洞口与反坎一次浇成。反坎混凝土强度不得低于C20。

5、管道安装及楼地面施工

烟风道安装完毕后,按照沉箱式卫生间做法安装沉箱内管道并施工完成楼地面。 其中上下两层防水附加层和防水层上反高度均需高出楼地面完成面300mm以上,平面出反坎周边不小于200mm。

6、甩浆抹灰

在烟风道表面甩浆养护并抹灰。 质量控制点:

1、洞口检查、清理、凿毛及湿润 2、反坎混凝土密实度及高度 3、烟风道进场验收及安装

4、上下两层防水附加层和防水层以及上反高度 5、闭水试验

6、烟风道壁甩浆抹灰

6.4 沉箱式卫生间烟风道做法(2)

做法说明:

沉箱式卫生间烟风道洞口周边须设置一道C20素混凝土反坎,并与楼面混凝土一起浇筑。楼地面完成面以下反坎宽度不小于200mm、以上不小于50mm;反坎高度须高出楼地面完成面不小于100mm。

结构施工时上下吊线,采用定型模板准确预留出烟风道孔洞位置和大小,烟风道下部安装在反坎上,上部顶住结构楼板,上部与下部缝隙用水泥砂浆堵塞密实。

烟风道制作高度=楼层净高-反坎高度-30mm,30mm为塞缝及调节高度。

烟风道安装前要对其尺寸及外观进行验收,表面不允许有裂缝,截面尺寸偏差在±5mm以内。

当烟风道周边墙体为砌体时,应先完成砌筑及抹灰施工,之后安装烟风道;最下层的烟风道应最后安装,以避免烟风道内垃圾无法清除。

工艺流程:

检查洞口——基层处理——浇筑反坎——安装烟风道——管道安装及楼地面施工——甩浆抹灰

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

2、反坎混凝土密实度及高度 3、烟风道进场验收及安装 4、塞缝密实度

5、上下两层防水附加层和防水层以及上反高度 6、闭水试验

7、烟风道壁甩浆抹灰

7.管道井防渗漏做法

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

楼地面防渗漏节点做法

集团工程采购与成本管理部 二○○九年十一月十八日

楼地面防渗漏节点做法

目录

1.一般要求........................................................1

1.1 楼板压槽...........................................................................................................................1 1.2 防水材料...........................................................................................................................1 1.3 内保温防水.......................................................................................................................1

2.厨房地面防渗漏做法..............................................1

2.1 无防水厨房地面...............................................................................................................1 2.2 有防水厨房地面...............................................................................................................2

3.卫生间地面防渗漏做法............................................3

3.1 一般卫生间防渗漏做法...................................................................................................3 3.2 沉箱式卫生间防渗漏做法...............................................................................................5

4.穿楼板管道防渗漏做法............................................8

4.1 无套管穿楼板管道...........................................................................................................8 4.2 有套管穿楼板管道.........................................................................................................10 4.3 穿楼板管道止水节做法.................................................................................................11

5.地漏节点防渗漏做法.............................................13 6.穿楼板烟风道防渗漏做法.........................................15

6.1 厨房、卫生间烟风道做法(1)...................................................................................15 6.2 厨房、卫生间烟风道做法(2)...................................................................................16 6.3 沉箱式卫生间烟风道做法(1)...................................................................................18 6.4 沉箱式卫生间烟风道做法(2)...................................................................................19

7.管道井防渗漏做法...............................................21

楼地面防渗漏节点做法

1.一般要求

1.1 楼板压槽

室内管道不宜采用在结构楼板上压槽埋设的做法,以免对结构楼板造成破坏。

当不得不在结构楼板上采用压槽的方法埋设管道时,压槽深度不得超过钢筋保护层厚度且必须经过结构安全确认,埋管后必须用水泥砂浆填实。 1.2 防水材料

当厨房、卫生间采用地热采暖时,防水层不可采用聚氨酯等可挥发性防水材料。

墙面防水材料应选用与砂浆粘结较好的JS等防水材料,不得使用与砂浆粘结不好的防水材料,以免出现空鼓。 1.3 内保温防水

采用内保温做法时,墙面防水应粘贴在墙面基层上,不得做在保温层上。

2.厨房地面防渗漏做法 2.1 无防水厨房地面

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

2、闭水试验:

结构闭水试验,水深30~50mm,并比楼板最高处高出20mm以上,试验时间不小于6小时,发现渗漏需进行修补,然后再进行闭水试验,直至不漏为止。

3、饰面层

按设计要求施工面层, 完成面应比相邻厅房完成面低10~20mm。 质量控制点:

1、基层处理 2、闭水试验 3、面层施工

2.2 有防水厨房地面

水泥砂浆找平/找坡,最薄处不小于20mm,并坡向地漏,坡度1%左右。 完成面应坚固、平整、表面压光,不得有酥松、起砂和空鼓。 4、防水附加层

找平层/找坡层干燥后,在管周、管井、地漏、阴角等部位施工防水附加层。 防水附加层材料及做法与防水层相同。

管周、管井、地漏、烟风道防水附加层施工范围参见后续章节说明,墙角处沿墙高和楼板水平方向防水附加层范围各为150 mm。

5、防水层

附加层施工完成后,分多遍涂刷1.5mm II型JS防水涂料,四周上返高度超过地面完成面300mm,过门框向外延伸200mm。

6、闭水试验

防水层完成后将门口与地漏封堵,进行24小时闭水试验,水深30~50mm,并比楼板与道墙相接处高出20mm以上;

做好闭水试验观察记录,确认无渗漏后方可排水。如发现渗漏应分析原因并对渗漏部位进行整改,整改完成后再次进行闭水试验,直至无渗漏现象发生。

7、保护层/饰面层

毛坯房交房时,闭水试验合格后施工20mm厚1:3水泥砂浆保护层,并向地漏找坡; 装修房时,闭水试验合格后按设计要求施工饰面层,饰面层排水坡度和坡向必须正确,不得有倒泛水和积水现象。饰面层完成后最高点应比相邻厅/房完成面低10~20mm。

无论毛坯房的砂浆保护层还是装修房的饰面层,施工时均须做好对防水层的保护,不得损坏防水层。

质量控制点:

1、基层处理

2、结构闭水试验

3、找平/找坡层的坡度及坡向 4、防水层厚度、范围 5、闭水试验

6、面层平整度及坡度、坡向

3.卫生间地面防渗漏做法 3.1 一般卫生间防渗漏做法

做法说明:

卫生间地面完成面应比相邻/厅房完成面低20mm。根据卫生间与相邻厅/房的装饰面厚度确定卫生间结构板面降低高度。

卫生间周边后砌墙根部浇筑C20同墙厚素混凝土导墙,高度不小于200mm。 土建与水电安装专业应合理安排工序,必须先装好设备及管道,严禁在施工完成防水的地面、墙面上打眼凿洞。

地面防水施工前,应先完成设备管道、地漏、烟风道等的安装及根部封堵,并经闭水试验验收合格。

工艺流程:

基层处理——结构闭水试验——找平层/找坡层——防水附加层——防水层——闭水试

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

不得有倒泛水和积水现象。饰面层完成后最高点应比相邻厅/房完成面低20mm。

无论毛坯房的砂浆保护层还是装修房的饰面层,施工时均须做好对防水层的保护,不得损坏防水层。

质量控制点:

1、基层处理

2、结构闭水试验

3、找平/找坡层的坡度及坡向 4、防水层厚度、范围 5、闭水试验

6、面层平整度及坡度、坡向

3.2 沉箱式卫生间防渗漏做法

水泥砂浆找平/找坡,最薄处不小于20mm,并坡向侧排口,坡度1%左右。 完成面应坚固、平整、表面压光,不得有酥松、起砂和空鼓。 4、防水附加层

找平层/找坡层干燥后,在管周、管井、地漏、阴角等部位施工防水附加层。 防水附加层材料及做法与地面防水层相同。

管周、管井、地漏、烟风道防水附加层施工范围参见后续章节说明,墙角处沿墙高和楼板水平方向防水附加层范围各为250 mm。

5、防水层

附加层施工完成后,地面分多遍涂刷1.5mm JS防水涂料或1.5mm厚聚氨酯防水涂膜,四周上返高度超过地面完成面300mm,过门框向外延伸200mm。

浴缸、淋浴间墙面分多遍涂刷1.2mm 厚II型JS防水涂料,下部从墙根开始,高度到地面完成面1800mm处。

6、闭水试验

防水层完成后将门口与地漏、侧排口封堵,进行24小时闭水试验,水深30~50mm,并比楼板与导墙相接处高出20mm以上;

做好闭水试验观察记录,确认无渗漏后方可排水。如发现渗漏应分析原因并对渗漏部位进行整改,整改完成后再次进行闭水试验,直至无渗漏现象发生。

7、防水保护层

闭水试验合格后施工20mm厚1:3水泥砂浆保护层。保护层达到强度后方可安装管道。8、沉箱内管道安装

保护层达到强度后,按设计要求安装管道。 9、侧排口疏水层

侧排口200mm范围设置卵石疏水层并用无纺布包裹,以防水泥浆等堵塞侧排口。 10、地漏及立管周围包封

沉箱内有地漏或立管时,在地漏或立管四周浇100宽,200高C20细石混凝土。 11、轻质填层

铺设轻质填层,具体厚度以沉箱深度及饰面做法确定。 12、细石混凝土层

在填层上做40mm厚C20细石混凝土层,内配φ6@200单层双向钢筋。细石混凝土层应一次向地漏找坡压光,坡度不小于1%,并在四周根部阴角处抹半径不小于10mm圆角。

13、防水层

细石混凝土层干燥后,分遍涂刷1.5mm厚JS防水涂料或聚氨酯涂膜,四周上返高度超过地面完成面300mm,过门框向外延伸200mm。

浴缸、淋浴间墙面分多遍涂刷1.2mm 厚II型JS防水涂料,下部从墙根开始,高度到地面完成面1800mm处。

14、闭水试验

第三次24小时闭水试验,水面最浅处不小于30-50mm,并观察、记录,确认无渗漏后方可排水。

15、防水保护层/饰面层

毛坯房交房时,闭水试验合格后施工20mm厚1:3水泥砂浆保护层,并向地漏找坡; 装修房时,闭水试验合格后按设计要求施工饰面层,饰面层排水坡度和坡向必须正确,不得有倒泛水和积水现象。饰面层完成后最高点应比相邻厅/房完成面低20mm。

无论毛坯房的砂浆保护层还是装修房的饰面层,施工时均须做好对防水层的保护,不得

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

损坏防水层。

质量控制点:

1、基层处理

2、侧排口、管周封堵及结构闭水试验

3、第一道防水附加层、防水层厚度、范围和闭水试验 4、侧排口疏水层

5、地漏、管周细石混凝土包封 6、细石钢筋混凝土找平压光 7、第二道防水层 8、闭水试验

4.穿楼板管道防渗漏做法 4.1 无套管穿楼板管道

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

不得有倒泛水和积水现象。饰面层完成后最高点应比相邻厅/房完成面低20mm。

无论毛坯房的砂浆保护层还是装修房的饰面层,施工时均须做好对防水层的保护,不得损坏防水层。 质量控制点:

1、孔洞清理凿毛 2、混凝土密实度 3、嵌填密封膏 4、防水层 5、闭水试验

4.2 有套管穿楼板管道

构造做法:

1、放线定位

模板支好后在模板上测量放线,准确确定管道、套管位置。 2、套管固定

把套管牢固地固定在模板上并用胶布等密封两端。 3、浇筑楼板

浇筑楼板混凝土时一定注意套管周边密实。 4、套管清理

在安装管道前,先清除套管内的杂物,钢套管应清除铁锈,并在管壁刷防锈漆,等防锈漆干透之后安装管道。

5、安装管道

安装管道穿过套管,管道接口不得设在套管内,注意管道与套管间缝隙要一致并固定好管道。

6、填塞套管与管道间缝隙

用沥青油麻丝分两遍填充套管与管道间缝隙,挤密压实并在上下口各留20mm深凹槽。

7、打密封膏

在上下口凹槽内嵌填建筑密封膏。 8、结构闭水试验

临时堵住门口与地漏口,与楼地面同时进行24小时闭水试验,在套管周围设置围堰使水淹没套管,确认无渗漏后方可排水。如发现渗漏应分析原因并对渗漏部位进行整改处理,完成后再次进行闭水试验,直至无渗漏现象发生。

后续的找平层/找坡层、防水附加层、防水层、闭水试验、防水保护层/饰面层做法与楼地面做法相同,其中施工防水保护层时,应在套管周边找出较大坡度,面层施工保持此坡度,避免套管根部积水。 质量控制点:

1、套管定位及固定 2、套管清理

3、套管与管道间沥青麻丝密实度 4、打密封膏 5、闭水试验

6、防水附加层及防水层 7、面层坡度

4.3 穿楼板管道止水节做法

做法说明:

本做法用于卫生间、厨房、阳台等现浇楼板的管道穿板安装。

目前穿楼板的各种无套管管道,均是在结构施工时通过预留孔洞进行安装,管道安装完毕后分次堵塞细石混凝土的做法,但是,由于混凝土堵塞不密实以及收缩变形等原因,此处往往发生渗漏。

止水节既不需要套管,也不在楼板上留孔洞,又能有效解决传统施工方法所导致卫生间的渗漏问题。

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

7、管道安装

直接将管道插入止水节中,用粘结剂粘结管道与止水节。

楼地面的闭水试验、找平找坡及防水等参照楼地面做法执行。 质量控制点:

1、弹线定位 2、止水节固定 3、止水节保护 4、管道安装

5.地漏节点防渗漏做法

做法说明:

本做法适用于厨房、卫生间、阳台等处地漏节点的防渗漏处理。

楼地面向地漏处找坡不小于1%,且地漏口应比楼地面完成面低2~5mm。

为便于孔洞封堵,地漏孔洞在结构施工时须采用定型模板预留,做成上大下小状,上部直径大于下部40mm为宜。

地漏应距墙根一定距离,以便于施工和防渗漏;预留地漏孔洞位置应在模板上放线定位,并牢固固定孔洞定型模板。

工艺流程:

安装地漏——支模——浇注混凝土——结构闭水试验——打密封膏——找平找坡层——防水附加层——防水层——闭水试验——防水保护层/饰面层 节点图:

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

无论毛坯房的砂浆保护层还是装修房的饰面层,施工时均须做好对防水层的保护,不得损坏防水层。

质量控制点:

1、孔洞清理、凿毛、湿润 2、细石混凝土密实度 3、结构闭水试验 4、嵌填密封膏 5、防水层施工 6、面层坡度

6.穿楼板烟风道防渗漏做法 6.1 厨房、卫生间烟风道做法(1)

厨房、卫生间烟风道节点做法(1)

构造做法:

1、检查洞口

检查预留洞口尺寸及位置,不符合要求的要剔凿处理。 2、基层处理

清理干净洞口周边,理顺预留钢筋,根部凿毛并浇水湿润。 3、安装烟风道 安装烟风道时,须先在下部烟风道壁上口坐浆,然后从上部插入本节烟风道并与下节对齐,同时矫正烟风道垂直度、方正度,要求垂直度偏差±5mm、阴阳角偏差±5mm。

4、浇筑烟风道周边及反坎混凝土 混凝土下部支模必须牢固且不漏浆,楼板预留洞口与反坎一次浇成。反坎混凝土强度不得低于C20。

5、楼地面施工

烟风道安装、混凝土浇筑完成后,按照找平层/找坡层、防水附加层、防水层、闭水试验、饰面层等楼地面的做法施工完成楼地面。

其中防水附加层和防水层上反高度需高出楼地面完成面300mm以上,平面出反坎周边不小于200mm。

6、甩浆抹灰

在烟风道表面甩浆养护并抹灰。 质量控制点:

1、洞口检查、清理、凿毛及湿润 2、反坎混凝土密实度及高度 3、烟风道进场验收及安装

4、防水附加层和防水层以及施工范围 5、闭水试验

6、烟风道壁甩浆抹灰

6.2 厨房、卫生间烟风道做法(2)

做法说明:

结构施工时上下吊线,采用定型模板准确预留出烟风道孔洞位置和大小,并在楼板上后浇混凝土反坎,烟风道下部安装在反坎上,上部顶住结构楼板,上部与下部缝隙用水泥砂浆堵塞密实。

混凝土反坎宽不小于50mm,高出楼地面完成面不小于100mm,混凝土标号为C20。 烟风道制作高度=楼层净高-反坎高度-30mm,30mm为塞缝及调节高度。

烟风道安装前要对其尺寸及外观进行验收,表面不允许有裂缝,截面尺寸偏差在±5mm以内。

当烟风道周边墙体为砌体时,应先完成砌筑及抹灰施工,之后安装烟风道;最下层的烟风道应最后安装,以避免烟风道内垃圾无法清除。

此种安装方式有以下优点:

1、混凝土反坎起到较好的挡水作用,有效解决了烟风道根部的渗漏问题。

2、在烟风道表面甩浆养护及抹灰,饰面完成后烟风道与反坎外侧平齐,不出现凸台,

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

开裂,应在抹灰层中压入网格布。 质量控制点:

1、洞口检查、清理、凿毛及湿润 2、反坎混凝土密实度及高度 3、烟风道进场验收及安装 4、塞缝密实度

5、防水附加层和防水层以及施工范围 6、闭水试验

7、烟风道壁甩浆抹灰

6.3 沉箱式卫生间烟风道做法(1)

沉箱式卫生间烟风道节点做法(1)

构造做法:

1、检查洞口

检查复核预留洞口,尺寸及位置不符合要求的要剔凿处理。 2、基层处理

清理干净洞口周边,凿毛并浇水湿润。 3、安装烟风道 安装烟风道时,须先在下部烟风道壁上口坐浆,然后从上部插入本节烟风道并与下节对齐,同时矫正烟风道垂直度、方正度,要求垂直度偏差±5mm、阴阳角偏差±5mm。

4、浇筑烟风道周边及反坎混凝土 混凝土下部支模必须牢固且不漏浆,楼板预留洞口与反坎一次浇成。反坎混凝土强度不得低于C20。

5、管道安装及楼地面施工

烟风道安装完毕后,按照沉箱式卫生间做法安装沉箱内管道并施工完成楼地面。 其中上下两层防水附加层和防水层上反高度均需高出楼地面完成面300mm以上,平面出反坎周边不小于200mm。

6、甩浆抹灰

在烟风道表面甩浆养护并抹灰。 质量控制点:

1、洞口检查、清理、凿毛及湿润 2、反坎混凝土密实度及高度 3、烟风道进场验收及安装

4、上下两层防水附加层和防水层以及上反高度 5、闭水试验

6、烟风道壁甩浆抹灰

6.4 沉箱式卫生间烟风道做法(2)

做法说明:

沉箱式卫生间烟风道洞口周边须设置一道C20素混凝土反坎,并与楼面混凝土一起浇筑。楼地面完成面以下反坎宽度不小于200mm、以上不小于50mm;反坎高度须高出楼地面完成面不小于100mm。

结构施工时上下吊线,采用定型模板准确预留出烟风道孔洞位置和大小,烟风道下部安装在反坎上,上部顶住结构楼板,上部与下部缝隙用水泥砂浆堵塞密实。

烟风道制作高度=楼层净高-反坎高度-30mm,30mm为塞缝及调节高度。

烟风道安装前要对其尺寸及外观进行验收,表面不允许有裂缝,截面尺寸偏差在±5mm以内。

当烟风道周边墙体为砌体时,应先完成砌筑及抹灰施工,之后安装烟风道;最下层的烟风道应最后安装,以避免烟风道内垃圾无法清除。

工艺流程:

检查洞口——基层处理——浇筑反坎——安装烟风道——管道安装及楼地面施工——甩浆抹灰

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日

2、反坎混凝土密实度及高度 3、烟风道进场验收及安装 4、塞缝密实度

5、上下两层防水附加层和防水层以及上反高度 6、闭水试验

7、烟风道壁甩浆抹灰

7.管道井防渗漏做法

审定

赵汉昌

编制 刘国权、杨满宏、赵飞宇、段计先、张登先

批准

周卫军

生效期 2009年11月18 日


相关内容

  • 建筑工程质量标准化管理
  • 关于实行建筑工程质量标准化管理 关于实行建筑工程质量标准化管理各区.市建设行政主管部门,各开发建设.施工.监理单位,各有关单位: 各区.市建设行政主管部门,各开发建设.施工.监理单位,各有关单位:为进一步提高建筑工程质量管理水平,促进全市建筑工程质量管理的科学化.规范化和标准化, 为进一步提高建筑工 ...

  • 工程质量常见问题防治操作手册土建篇
  • 目 录 一.防治地下室渗漏.回填土下沉质量问题技术措施 (一) 防治地下室剪力墙渗漏技术措施 „„„„„„„„„„„1 (二) 防治地下室施工缝渗漏技术措施„„„„„„„„„„„1 (三) 防治地下室室外地面渗漏技术措施„„„„„„„„„„2 (四) 地下室防水层成品保措施„„„„„„„„„„„„2 ...

  • 防渗漏防水方案
  • 马泘沱村城中村改造项目DK-2工程 防渗漏专项施工方案 编 写: 审 核: 批 准: 长枫建设集团有限公司 二〇一七年八月二十二日 一.编制依据 1.<地下工程防水技术规范>(GB50108-2008) 2.<地下防水工程质量验收规范>(GB50208-2002) 3.< ...

  • 加强正负零以下工程质量的通知书1
  • 关于<加强±0以下工程质量管理>的通知 各万科标段项目部: 结合近期万科标段项目的质量检查,±0以下渗漏.墙面返潮等质量问题较普遍,为了有效避免此类问题的发生,公司对检查过程中发现的普遍性质量问题进行了总结,并根据原因分析制定了相应的管理改进措施,望项目部有针对性的进行管理改进,提高±0 ...

  • 卫生间防水施工方案(2)
  • 卫生间防水 施 工 方 案 目 录 一.编制依据 ........................................................2 二.卫生间防水工程概况 ..............................................2 三.卫生间防水 ...

  • 高层防水万科统一技术标准
  • 高层项目统一构造做法 1. 适用范围 本技术要求适用于万科深圳区域所有高层项目构造做法的招投标及现场安装指导.(本文划线部分应先根据项目填充) 2. 2.1 依 据 除另有注明外, 本工程须符合设计.图纸和相关国家.地方及行业标准,主要包括但不限于: <工程建设标准强制性条文>2002年 ...

  • 地下室渗漏原因及防治措施
  • 1.地下室底板渗水 1.1.后浇带的节点做法:后浇带中垃圾.积水处理不到位,会导致混凝土夹渣,强度降低等影响后浇带混凝土质量,增加渗漏风险,可以从后浇带的节点设计上来预防此类通病: 1.1.1.多数图纸设计中仍采用图1所示的节点,此节点不能有效解决以上问题.建议采用图2节点,后浇带的底板加厚100m ...

  • 钢结构预埋螺栓安装技术
  • 本工程钢结构数量较大,而钢结构是通过钢柱底部的螺栓连接座与钢砼基座连接的.为确保基座预埋底脚螺栓的准确就位并且在砼浇筑过程中不产生偏移,将采取以下技术措施: ①采用二次定位.二次校核的办法确保定位的精度: 首先用全钻仪和高精度水准仪定出基础的准确位置并弹出预埋螺栓支架控制线:然后在安装螺栓时,再用经 ...

  • 地下室自粘防水卷材施工方案
  • 地下室外侧墙.防水施工方案 2.工程概况 本工程地下室外侧墙防水工程采用: 一层1.0mm水泥基渗透结晶防水涂料 + 一层1.5mmSAM921自粘防水卷材. 侧墙防水施工做法如下图: 5.砌砖保护防水层 4.挤塑板隔离隔气层 3.1.5mmSAM921防水卷材 2.1mmPCC501水泥基渗透结晶 ...