管线探沟开挖方案6.10

兰州市轨道交通1号线一期工程

(陈官营~东岗段)

管线探沟施工方案

编制: 审核: 审批:

八冶建设集团有限公司

兰州轨道交通1号线一期TJ Ⅱ-8B 项目部

2014年06月10日

目录

1、工程概况 ······································································································ 1 2、开挖目的 ······································································································ 1 3、施工方案 ······································································································ 1 3.3探沟开挖技术要求 ·················································································· 2 4、组织机构及联系方式 ·················································································· 3 4.1、领导小组组织机构 ··············································································· 3 4.2、主要负责人联系方式 ··········································································· 4 5、安全注意事项 ······························································································ 5 6、附图 ············································································································· 5

八冶建设集团有限公司

管线探沟开挖施工方案

1、工程概况

本车站采用地下两层双柱三跨的结构形式。车站主体长度230.50 米,标准段宽 22.20 米,总高 15.07 米,结构底板埋深约 18.07m ,中心里程处顶板覆土厚约 3.0m 。车站在西津西路南北两侧各设两个出入口(其中1号出入口为远期规划,不纳入本次施工范围),车站两端于南北侧各设臵 1 组风亭。车站采用明挖顺做法施工,因南侧交通疏解需要进行半盖挖施工,根据总体筹划,车站按照盾构过站考虑。

2、开挖目的

本次管线探沟开挖的目的为:明确管线现状位臵(坐标), 高程,规格,材质,完好程度,运行情况、走向等信息,为管线拆改、保护提供必要的数据支持。

3、施工方案

3.1管线现状

根据业主提供的七里河站管线迁改平面图及我单位初步摸排,本车站已知的南侧东西向管线有:D500、D1200、D100给水管线;D325保温热力管网;D300污水管;660*500供电管沟,具体详见附图:(七里河站管线横断面图)。横穿马路的管线自西向东分别为:D300雨水砼管2道,共通电缆沟300*100,D300雨水砼管,D325燃气管道,D300雨水砼管,600*600供电铜缆沟,D300雨水砼管,D100交通铜缆,800*600电信铜/光缆沟,D500铸铁给水管沟,D1000、D800雨污排水管。

3.2探查方法

根据施工现场几天的勘查和各方面提供的资料,为防止实际存在的管线并未在图纸中标识和图纸中标识管线位臵不一致或精确的情况存在,所以我们决定采用在西津东路南侧纯人工方式开挖3道探沟,车站主体南侧围护桩位上挖1道通长探沟,将所有管线找出并定位。探沟开挖位臵 见下图:

1

八冶建设集团有限公司

兰州市轨道交通1号线一期工程土建施工 管线探沟开挖施工方案

图3-1

探沟布臵示意图

3.3探沟开挖技术要求

1、探沟采用放坡开挖,放坡坡度为1:0.33,探沟宽度2m, 基底宽度0.8m ,开挖深度为原地表以下2.5m 。详见下图3-2。开挖出的土方堆放在距探沟边3m 以外位臵,高度不超过1.5m ,沿沟边严禁堆放材料等重物。

图3-2 探沟开挖断面示意图

2

八冶建设集团有限公司

2、因部分场区现状地表为沥青混凝土硬化地面,故先采用带破碎头的小型

挖掘机进行击碎,后安排机械进行清除,然后采用人工开挖。

3、开挖时必须小心,用铁锨轻轻挖掘,不得用镐,以保证不损坏地下管线,待开挖至地面以下约1m 时,如图3-2每隔2m 加入钢管支撑 ,再继续开挖,以防边坡坍塌。

4、在开挖过程中,发现未知地下管线要及时报告现场工程师(必要时报业主及监理),在现场工程师的监视下轻轻扩宽范围,探明管线的种类、规格、根数、走向和深度并作记录。周围设警示标志并用警戒线围挡,专人负责监护重点防护措施。

5、将发现的地下管线全部清理暴露出地面,不留死角,探明管线路径、埋深。现场施工人员需认真检查,不能漏挖、错挖。在挖出的电缆旁立警示牌,并用砖、砂等暂时覆盖保护并及时上报业主相关部门、权属单位进行确认,确定保护方案进行保护,并督促及时迁改。

6、现场施工员负责记录当天的工作部位、工作内容、缆线状况,下班前对当天的探沟开挖及探测的实际情况及时进行汇报。

7、探沟开挖完毕后将所挖探出的管线的种类、规格、走向及深度等绘出管线埋设分布图,上报业主和监理,并及时请相关部门进行确认验收,制定迁改方案。

8、在探挖过程中要特别注意数据的记录工作,高程数据应注意管外顶、内顶、内底、外底的区别。

4、组织机构及联系方式

4.1、领导小组组织机构

3

八冶建设集团有限公司

1、组长王海岩负责对施工全过程监督,是探沟开挖的总负责人。 2、项目总工程师薛守文负责对本方案的检查、监督及评价。 3、技术负责人孙闯负责方案的编制、实施和检查。

4、专职安全员杨小峰:对施工全过程的安全施行控制,并做好记载;定期安全检查,及时处观工现场安全隐患。

5、施工员李鹤龄:组织探沟开挖施工,对投入到本工作的人、机、材、设备等作统一安排和部署,对本工作负主责。

6、材料员魏林:负责物资供应及后勤支持。 7、各组员负责配合各部门落实各项安全措施。 4.2、主要负责人联系方式

八冶建设集团有限公司

4

1、所有管理人员认真学习管线迁改平面图,掌握各地下管线的类型、分布、走向、管线的交叉情况等。

2、现场进行开挖作业必须有项目部管理人员旁站监督,遇特殊情况及时上报。

3、本着随挖随埋的原则,测量技术人员密切配合,对开挖裸露出的各种管线及时测量坐标、标高、管径等有效信息,统计明确后及时将裸露管线埋填,以保证探明的管线不在长时间处于悬空状态,保护管线的完好程度。

4、在开挖探沟时,应根据工作面大小合理安排施工人数,人与人之间应保持安全距离,防止镐头、铁锨等伤人事故的发生。

5、按照要求放坡,采用分层开挖逐层加深的办法,防止坍塌。

6、坑沟施工应注意对现况管线的保护,开挖前参考附图预计大致埋深。(注意如电力管线、小盖板,上水、燃气等管线的表示带埋设情况)

7、挖探沟过程中,探沟四周应做保护措施,使用临时护栏,并设警示标识。

6、附图

5

八冶建设集团有限公司

兰州市轨道交通1号线一期工程土建施工 八冶建设集团有限公司

管线探沟开挖施工方案

1

兰州市轨道交通1号线一期工程

(陈官营~东岗段)

管线探沟施工方案

编制: 审核: 审批:

八冶建设集团有限公司

兰州轨道交通1号线一期TJ Ⅱ-8B 项目部

2014年06月10日

目录

1、工程概况 ······································································································ 1 2、开挖目的 ······································································································ 1 3、施工方案 ······································································································ 1 3.3探沟开挖技术要求 ·················································································· 2 4、组织机构及联系方式 ·················································································· 3 4.1、领导小组组织机构 ··············································································· 3 4.2、主要负责人联系方式 ··········································································· 4 5、安全注意事项 ······························································································ 5 6、附图 ············································································································· 5

八冶建设集团有限公司

管线探沟开挖施工方案

1、工程概况

本车站采用地下两层双柱三跨的结构形式。车站主体长度230.50 米,标准段宽 22.20 米,总高 15.07 米,结构底板埋深约 18.07m ,中心里程处顶板覆土厚约 3.0m 。车站在西津西路南北两侧各设两个出入口(其中1号出入口为远期规划,不纳入本次施工范围),车站两端于南北侧各设臵 1 组风亭。车站采用明挖顺做法施工,因南侧交通疏解需要进行半盖挖施工,根据总体筹划,车站按照盾构过站考虑。

2、开挖目的

本次管线探沟开挖的目的为:明确管线现状位臵(坐标), 高程,规格,材质,完好程度,运行情况、走向等信息,为管线拆改、保护提供必要的数据支持。

3、施工方案

3.1管线现状

根据业主提供的七里河站管线迁改平面图及我单位初步摸排,本车站已知的南侧东西向管线有:D500、D1200、D100给水管线;D325保温热力管网;D300污水管;660*500供电管沟,具体详见附图:(七里河站管线横断面图)。横穿马路的管线自西向东分别为:D300雨水砼管2道,共通电缆沟300*100,D300雨水砼管,D325燃气管道,D300雨水砼管,600*600供电铜缆沟,D300雨水砼管,D100交通铜缆,800*600电信铜/光缆沟,D500铸铁给水管沟,D1000、D800雨污排水管。

3.2探查方法

根据施工现场几天的勘查和各方面提供的资料,为防止实际存在的管线并未在图纸中标识和图纸中标识管线位臵不一致或精确的情况存在,所以我们决定采用在西津东路南侧纯人工方式开挖3道探沟,车站主体南侧围护桩位上挖1道通长探沟,将所有管线找出并定位。探沟开挖位臵 见下图:

1

八冶建设集团有限公司

兰州市轨道交通1号线一期工程土建施工 管线探沟开挖施工方案

图3-1

探沟布臵示意图

3.3探沟开挖技术要求

1、探沟采用放坡开挖,放坡坡度为1:0.33,探沟宽度2m, 基底宽度0.8m ,开挖深度为原地表以下2.5m 。详见下图3-2。开挖出的土方堆放在距探沟边3m 以外位臵,高度不超过1.5m ,沿沟边严禁堆放材料等重物。

图3-2 探沟开挖断面示意图

2

八冶建设集团有限公司

2、因部分场区现状地表为沥青混凝土硬化地面,故先采用带破碎头的小型

挖掘机进行击碎,后安排机械进行清除,然后采用人工开挖。

3、开挖时必须小心,用铁锨轻轻挖掘,不得用镐,以保证不损坏地下管线,待开挖至地面以下约1m 时,如图3-2每隔2m 加入钢管支撑 ,再继续开挖,以防边坡坍塌。

4、在开挖过程中,发现未知地下管线要及时报告现场工程师(必要时报业主及监理),在现场工程师的监视下轻轻扩宽范围,探明管线的种类、规格、根数、走向和深度并作记录。周围设警示标志并用警戒线围挡,专人负责监护重点防护措施。

5、将发现的地下管线全部清理暴露出地面,不留死角,探明管线路径、埋深。现场施工人员需认真检查,不能漏挖、错挖。在挖出的电缆旁立警示牌,并用砖、砂等暂时覆盖保护并及时上报业主相关部门、权属单位进行确认,确定保护方案进行保护,并督促及时迁改。

6、现场施工员负责记录当天的工作部位、工作内容、缆线状况,下班前对当天的探沟开挖及探测的实际情况及时进行汇报。

7、探沟开挖完毕后将所挖探出的管线的种类、规格、走向及深度等绘出管线埋设分布图,上报业主和监理,并及时请相关部门进行确认验收,制定迁改方案。

8、在探挖过程中要特别注意数据的记录工作,高程数据应注意管外顶、内顶、内底、外底的区别。

4、组织机构及联系方式

4.1、领导小组组织机构

3

八冶建设集团有限公司

1、组长王海岩负责对施工全过程监督,是探沟开挖的总负责人。 2、项目总工程师薛守文负责对本方案的检查、监督及评价。 3、技术负责人孙闯负责方案的编制、实施和检查。

4、专职安全员杨小峰:对施工全过程的安全施行控制,并做好记载;定期安全检查,及时处观工现场安全隐患。

5、施工员李鹤龄:组织探沟开挖施工,对投入到本工作的人、机、材、设备等作统一安排和部署,对本工作负主责。

6、材料员魏林:负责物资供应及后勤支持。 7、各组员负责配合各部门落实各项安全措施。 4.2、主要负责人联系方式

八冶建设集团有限公司

4

1、所有管理人员认真学习管线迁改平面图,掌握各地下管线的类型、分布、走向、管线的交叉情况等。

2、现场进行开挖作业必须有项目部管理人员旁站监督,遇特殊情况及时上报。

3、本着随挖随埋的原则,测量技术人员密切配合,对开挖裸露出的各种管线及时测量坐标、标高、管径等有效信息,统计明确后及时将裸露管线埋填,以保证探明的管线不在长时间处于悬空状态,保护管线的完好程度。

4、在开挖探沟时,应根据工作面大小合理安排施工人数,人与人之间应保持安全距离,防止镐头、铁锨等伤人事故的发生。

5、按照要求放坡,采用分层开挖逐层加深的办法,防止坍塌。

6、坑沟施工应注意对现况管线的保护,开挖前参考附图预计大致埋深。(注意如电力管线、小盖板,上水、燃气等管线的表示带埋设情况)

7、挖探沟过程中,探沟四周应做保护措施,使用临时护栏,并设警示标识。

6、附图

5

八冶建设集团有限公司

兰州市轨道交通1号线一期工程土建施工 八冶建设集团有限公司

管线探沟开挖施工方案

1


相关内容

  • 基坑施工方案--桥梁工程
  • ---------------------有限公司 ----------------景观桥工程 基坑施工方案 工程名称: 编制单位: 编 制: 审 核: 报送日期: 目 录 1. 编制依据 ....................................................... ...

  • 内蒙古某地下管道施工方案_secret
  • 目 录 1. 编制说明 ..................................................... 2 2. 编制依据 ..................................................... 2 3. 工程概况 .......... ...

  • 对某市供水二期工程地基注浆施工技术探讨
  • 对某市供水二期工程地基注浆施工技术探讨 摘要:本文结合工程实例,分析了基坑工程的特点.重点.难点,并对建筑工程中基坑防护方法和注浆施工技术进行了论述,供同行参考. 关键词:基坑施工: 分析 : 注浆处理 1.工程概况 某市供水二期工程,项目建设规模为5万吨/日,施工内容包括新建建(构)筑物共计9个子 ...

  • 土方开挖专项施工方案
  • 目 录 一.编制依据 ............................................. 2 二.工程概况 ............................................. 2 三.工程气象.地质.水文情况 ..................... ...

  • 2012版建设部十项新技术
  • 建筑业十项新技术(2012版) 1 地基基础和地下空间工程技术 1.1灌注桩后注浆技术 1.2长螺旋钻孔压灌桩技术 1.3水泥粉煤灰碎石桩(CFG 桩)复合地基技术 1.4真空预压法加固软土地基技术 1.5土工合成材料应用技术 1.6复合土钉墙支护技术 1.7型钢水泥土复合搅拌桩支护结构技术 1.8 ...

  • 第六章 地铁车站施工设计
  • 第6章 地铁车站施工设计 6.1 工程概况分析 中山西路站是南昌地铁1号线的中间站,该车站位于中山西路和西河滩路的交汇处,前身是滨江大道站,商业比较繁荣,人流量较大,有许多建筑物在附近,多为浅基础多层建筑.场地较为平坦,地面标高一般为20-24m 左右,场地较为平整.道路地下管线较多,经线路图分析及 ...

  • 施工方案编制导则(修改)
  • 1 目的 建筑工程施工方案是工程施工重要的指导性文件,本导则旨在加 强对施工方案的管理,统一危险性较大的施工方案的编制要求.标准和内容,理顺方案编制的程序,明确施工方案的编制.审核.审批程序.以保证其满足本组织QEOHSMS管理体系规定的要求. 2 范围 适用于本组织工程项目施工过程中危险性较大的分 ...

  • 基坑支护设计文件
  • 武汉市硚口区人民政府 硚口区行政中心 (修改稿) 武汉地质工程勘察院 2006年10月17日 武汉市硚口区人民政府 硚口区新行政中心基坑支护设计 任务号:2006-11 图别:基坑支护施工设计 总工程师: (签章) 审 核: (签章) 设 计: (签章) 武汉地质工程勘察院 2006年10月17日 ...

  • 基坑土钉喷锚支护管井降水施工方案
  • 基 坑 土 钉 墙 喷 锚 支 护 开 挖 降 水 施 工 方 案目 录 第一章 第二章 第三章 工程概况 编制依据 围护结构设计概况第一节围护结构选定类型.具体参数 第二节局部深坑(坑中坑)挖土支护措施 第三节降排水措施 第四章 施工部署 第一节管理体系 第二节施工进度计划安排 第三节施工准备 第 ...