4.1、基础部分 ............................................................................................................................ 2 4.2、附墙锚固 ............................................................................................................................ 6 4.3、供电 .................................................................................................................................... 7 4.4、室外电梯架子及防护门: .............................................................................................................. 7 4.5、室外电梯避雷措施: ..................................................................................................................... 11 6.1 电梯安装要求: ................................................................................................................ 13 6.2电梯使用要求:............................................................................................................ 14 6.3电梯拆卸要求:............................................................................................................ 13
一、 编制依据:
1.1 高层建筑施工手册
1.2 北京市建筑工程施工安全操作规程(DBJ01-62-2002) 1.3 建筑机械使用安全技术规程(JGJ33-2001) 1.4xx公司《xx施工图》。 1.5《xx施工组织设计》。
1.6《SCD200/200双笼施工电梯安装使用说明书》 1.7施工现场条件
二、 工程概况:
四、 施工要求:
本工程采用SCD200/200型施工电梯,该机额定最大载重为2000Kg,双笼同时施工,提升速度可达34m/min;能满足不同施工的要求。
4.1、基础部分
基础直接坐在车库地下一层顶板上,场地要清理到位。基础混凝土厚度为250mm,混凝土强度为C25。钢筋配置:直径为12mm的一级圆钢,间距200mm,在基础中布置单层双向钢筋网。混凝土表面平整度小于10mm。经设计核算符合受力要求。
室外电梯基础平面图如下所示:
1-5#楼室外电梯平面布置图如下所示:
上顶4.2
4.3、供电
在施工电梯5m范围内装设一配电箱,容量不小于25Kw。供电电压为380±5%。200A空开一个,100A空开两个。
4.4、室外电梯防护架及防护门: 1-5#楼室外电梯防护架平面图如下图:
室外电梯防护架剖面图如下图:
电梯防护门自制,宽1.4m,高1.3m,用螺纹12的钢筋焊接,采用推拉门方式安装。
4.5、室外电梯避雷措施:
由于室外电梯座在地下一层顶板上,每个住宅楼都有自己的避雷设置区域,室外电梯基座底部位置一端将4*40mm镀锌扁铁用M10螺栓锚固在基座上,扁铁另一端与楼内避雷圈连接,楼内的避雷与底板钢筋为联通的电路并导到地下(相当于避雷接地);
室外电梯中间设置两道与住宅楼预埋幕墙埋件用4*40mm镀锌扁铁连接固定牢固(埋件为住宅楼避雷的一部分);
室外电梯顶端也用4*40mm镀锌扁铁将室外电梯和楼顶端避雷圈连接;
上端与室外电梯顶部避雷针锚固,避雷针采用直径20镀锌钢管,下焊70*70*5镀锌角钢,针尖采用直径16镀锌圆钢磨尖,安装长度高于室外电梯顶部1米。
五、电梯安装、拆除:
5.1.安装前的准备:
5.1.1、施工电梯的项目经理和租赁及安装工长详细了解施工现场的地形。施工现场负责清理、排除施工电梯安装(拆卸)作业周围的障碍物,保证吊车、运输车辆等顺利通行和作业。
5.1.2、施工现场负责做好施工电梯安装(拆卸)作业现场的安全防护区的警戒工作,严禁施工电梯安装(拆卸)时现场其他工种交叉作业和非安装(拆卸)人员穿行和停留。
5.1.3、项目经理或租赁工长、安装工长勘察施工现场后,应与委托单位签定安装(拆卸)合同一式三份,并分别下达安装(拆卸)任务书(填表一)、安全技术交底(填表二)。
5.2.电梯安装:严格按照《施工升降机使用说明书》要求安装拆卸。安装主要步骤如下: 5.2.1、将底座围栏安装就位,用水平仪测平后,将地脚螺栓插入预留孔内,浇注C30混凝土,待强度达到50%时,将螺栓预紧固。
5.2.2、安装3节标准节、下限位及下极限行程开关碰铁。
5.2.3、安装吊笼,注意就位前把拖动电机制动器释放,就位后恢复。调整齿轮和齿条的侧隙,滚轮和立柱的间隙,调整值为0.3-0.5mm。
5.2.4、将操作盒装在吊笼顶部的安全护栏上并接通电源,首先试车检查吊笼的运行方向是否与操作盒上的指示方向相符合。
5.2.5、安装导轨架,在标准节安装至第七或第八节,必须精确校正导轨架的垂直度,垂直度允差为1/1000。每安装六节都要进行一次垂直度校核。用吊杆安装时,注意其载重量为200kg。吊笼运行时,吊杆不得吊挂物品。用塔吊辅助安装时,一次只能拼接6节标准节。每安装一节或一组标准节,都必须按要求安装上限位及上极限行程开关碰铁。
5.2.6、安装导轨附着架,附着架允许的最大水平倾角为±10º-15º。导轨附着架安装的最
5.2.7、当导轨架达到所需高度后,安装天轮与对重钢丝绳。
5.2.8、整体安装完毕后试车3次,保证上限位及上极限碰铁灵敏有效。
5.3 电梯拆卸:
5.3.1、先将操作盒移置吊笼顶部,并校定其功能,然后将电动吊杆安装就位。
5.3.2、与装对重相反的程序,将对重钢丝绳卸下。
5.3.3、吊笼升到最高位置,用吊杆吊住承载天轮,拆下连接螺栓。转动吊臂放置吊笼顶部,运置地面。
5.3.4、将吊笼适当下行一段距离,用专用吊具吊住待卸标准节,确认吊笼上部滚轮总成位于待拆卸标准节连接点下方时,方可卸下连接螺栓。转动吊臂,将标准节置于吊笼顶,运置地面。
5.3.5、拆卸附着架等部件,应随拆随运到地面以防超载运行,也可以用起重机协助拆卸工作。
5.3.6、切断电源,拆除电缆和接地保护线。
5.3.7、拆除部件应码放整齐,妥善保管,以待装运。
六、安全注意事项:
6.1电梯安装要求:
6.1.1、外用电梯的安装、拆卸必须由合格的专业拆装队进行。所有操作人员需持有效证件上岗,工作中必须严格遵守《施工升降机使用说明书》的操作规程,严禁一切违章指挥,一切违章冒险作业。要有明确分工,各负其责,明确一人负责指挥工作,确定指挥联络信号。
6.1.2、外用电梯的安装、拆卸都要有制定安全技术措施,并对所有参加作业的人员进行有关的安全教育。
6.1.3、安装、拆卸前要组织有关技术人员,对各部件、各导轨架、附墙支撑及地基基础进行认真的安全技术检查,确认无误后才能进行安装或拆卸。
6.1.4、安装、拆卸作业要认真执行所制定的安全技术措施,并严格遵守原厂说明书所规定的拆装程序和各项要求。
6.1.5、安装、拆卸时必须要有专业技术人员在场指挥,分工要明确,指挥要统一,每个工作人员都必须遵守有关的安全操作规程,操作人员必须戴安全帽,高作业必须有安全带,作业区内要严禁非工作人员进入。
6.1.6、工作需要升降时,必须由有经验的专职司机操作,其它人员不得操作升降。工作笼每次开动前,司机必须与其它工作人员联系好后才能开动,要鸣警示意。
6.1.7、安装、拆卸时期,除按规定载运少量的安装工作人员及所用物料外,严禁带人、运物。每个吊笼平台作业人员、配备工具及待安装部件总重量不得超过650kg。。
6.1.8、导轨架安装必须垂直牢固,各附墙支撑必须符合规定要求。
6.1.9、外用电梯的安装完毕,要按规定进行调试,对各部位的安全装置要进行可靠性试验,对整机要进行荷载试验。并由主管部门组织检查验收,确认达到安全技术标准,并验收签字后方能投入使用。导轨架最大悬臂高7.5m。
6.1.10、各项装置必须齐全有效(限速器、超高限位装置、超低限位装置、钢丝绳事故限位装置、门限位装置、紧急开关、紧急制动闸)。
6.1.11、对重钢丝绳用四个卡子卡紧,两卡子之间的间距为80-100mm,注意应将绳卡底板扣在钢丝绳工作股上。检查钢丝绳是否符合国标。
6.1.12、整体安装完毕,用经纬仪进行正面和侧面的垂直度检测,标准是当架设高度
小于70m时,其偏差不大于高度的千分之一,架设高度70-100m时,共偏差不大于7cm。
6.1.13、地线采用专用的镀锌扁铁或大于Φ10的圆钢连接,电阻值不得大于4Ω,(安装前安装工长向施工现场要已签认合格的表三和保护接地的测试值报告)。
6.1.14、遇有雨、雪、雾及大风(五级以上)天气不得进行安装拆卸作业。
6.2电梯使用要求:
6.2.1、司机经过专门训练并经考试合格,发给操作证后,方可操作。
6.2.2、司机工作时,工作服要扣紧,带好安全帽。
6.2.3、不准超载工作,荷载严格限制在出厂规定的额定范围内。运送物料不得伸出在护网外面。
6.2.4、禁止非司机操作。
6.2.5、电梯每次起动前都要鸣警示意,操作业时司机必须精神集中,严禁与别人闲谈打闹,看书报等。
6.2.6、电梯升降时所有乘人员必须听从司机指挥,否则司机有权拒绝升降。
6.2.7、上班第一次开车离地一米停车,检查工作笼是否下滑、上爬。并做其它试运转,证明性能正常后,方可正式工作。
6.2.8、运送的物品在工作笼内必须平均分布,防止偏重。
6.2.9、随时注意信号,遇不正常情况立即停车。
6.2.10、在视线差、大雾、雷雨,导轨冰冻等危险条件下禁止开车。
6.2.11、合闸后司机不准离开吊笼,下班后吊笼降至地面,拉开电源开关,锁好操纵箱后才能离开。
6.2.12、制动器、限速器要经常检查调整,确保安全可靠,在其失灵或有故障时,严禁开车。
6.2.13、大风情况下开车要小心,风力超过6级时严禁开车,吊笼停于地面。
6.2.14、下班时要打扫梯笼,整理工作现场。拉开电源开关,检查机械部分有无损坏,做好当班记录,锁好司机室或做好交接班。
6.3电梯拆卸要求:
6.3.1、外用电梯拆卸过程中,要有专人统一指挥,并熟悉图纸、安装、拆卸程序及检查要点。
6.3.2、外用电梯安装、拆卸必须由合格的专业拆装队伍施工,并要制定安全技术措施,对所有人员进行安全交底教育。
6.3.3、拆卸前要组织有关技术人员对各中件、各导轨架、附墙支撑及地基基础进行认真的安全技术检查,确认无误后才能进行拆卸。
6.3.4、在拆除平衡重之前,必须对电梯及附壁杆、制动器的空隙,主转动机构的运行进行检查,确认正常后,方可拆除。
6.3.5、梯笼升至顶部,使平衡铁落地,然后再点动慢慢上升50 cm左右,梯笼不发生下滑,即可开始按顺序拆除。
6.3.6、先把平衡铁拆下来放平,拆下钢丝绳及无轮组,把梯笼升至接近柱顶处,拆除立柱标准节。此时梯笼处于无平衡重运行,梯笼内可以载两名工人和必要工具运行使用,必须用钢丝绳做保险,把梯笼顶部与钢丝绳牢固连接在立柱上,向下运行时,应靠梯笼自重分段逐节下滑,每下滑一个标准节,停车一次,以免超速刹车发热。
6.3.7、每拆除两个标准节,随之把附壁支撑同时拆下,拆下的附件装入梯笼时,其吊重不能超载,因无配重载重量应折减。
6.3.8、拆除附壁杆以及各层通道架板时,梯笼应随之停置在作业层的高度,不能在拆除过程中,梯笼同时上下运行。
6.3.9、所有施工人员必须严格按照操作规程作业,戴好安全帽,挂好安全带,作业区内要严禁非作业人员进入,整个拆装过程要有专业机械,安全人员在场监护。
6.3.10、大风情况下不得进行拆除作业,风力超过5级时严禁开车作业,梯笼应停于地面。
6.3.11、下班时要将现场整理干净,切断电源开关,锁好梯笼。
因违章作业造成的损失、事故一律由施工单位全部负责,甲方(中铁)还将依据有关规定给予处罚。
七、环保措施:
7.1进出现场不得大声喧闹,不得吸烟。
7.2不得随便乱扔纸屑、油料和废弃物、塑料袋等。
7.3严禁随地大小便。
7.4安装、拆卸的部件要集中放置,防止漏油污染。擦拭油物等使用的棉纱不得随地乱丢,放在专用塑料桶内,统一送运至项目指定的垃圾点处理。
7.5现场安装和拆卸时,不准大声喧哗。设专人专管,定期检查,保证施工电梯正常运转,杜绝因不正常运转而产生噪音。
八、质量标准:
8.2.1节架垂直度必须符合要求,偏差不得超过2‰ 。
8.2.2所有紧固件,开中销螺栓等必须紧固到位,一应俱全。
8.2.3所有安全限位必须齐全,灵活,有效。
8.2.4电气零部件绝缘可靠,不漏铜丝,接地电阻≤4欧姆。
8.2.5要轻吊轻放,吊点位置选择准确,保证结构件不变形。
8.2.6整机达到市建委颁布的验收标准,并出具书面资质,以供备查。
4.1、基础部分 ............................................................................................................................ 2 4.2、附墙锚固 ............................................................................................................................ 6 4.3、供电 .................................................................................................................................... 7 4.4、室外电梯架子及防护门: .............................................................................................................. 7 4.5、室外电梯避雷措施: ..................................................................................................................... 11 6.1 电梯安装要求: ................................................................................................................ 13 6.2电梯使用要求:............................................................................................................ 14 6.3电梯拆卸要求:............................................................................................................ 13
一、 编制依据:
1.1 高层建筑施工手册
1.2 北京市建筑工程施工安全操作规程(DBJ01-62-2002) 1.3 建筑机械使用安全技术规程(JGJ33-2001) 1.4xx公司《xx施工图》。 1.5《xx施工组织设计》。
1.6《SCD200/200双笼施工电梯安装使用说明书》 1.7施工现场条件
二、 工程概况:
四、 施工要求:
本工程采用SCD200/200型施工电梯,该机额定最大载重为2000Kg,双笼同时施工,提升速度可达34m/min;能满足不同施工的要求。
4.1、基础部分
基础直接坐在车库地下一层顶板上,场地要清理到位。基础混凝土厚度为250mm,混凝土强度为C25。钢筋配置:直径为12mm的一级圆钢,间距200mm,在基础中布置单层双向钢筋网。混凝土表面平整度小于10mm。经设计核算符合受力要求。
室外电梯基础平面图如下所示:
1-5#楼室外电梯平面布置图如下所示:
上顶4.2
4.3、供电
在施工电梯5m范围内装设一配电箱,容量不小于25Kw。供电电压为380±5%。200A空开一个,100A空开两个。
4.4、室外电梯防护架及防护门: 1-5#楼室外电梯防护架平面图如下图:
室外电梯防护架剖面图如下图:
电梯防护门自制,宽1.4m,高1.3m,用螺纹12的钢筋焊接,采用推拉门方式安装。
4.5、室外电梯避雷措施:
由于室外电梯座在地下一层顶板上,每个住宅楼都有自己的避雷设置区域,室外电梯基座底部位置一端将4*40mm镀锌扁铁用M10螺栓锚固在基座上,扁铁另一端与楼内避雷圈连接,楼内的避雷与底板钢筋为联通的电路并导到地下(相当于避雷接地);
室外电梯中间设置两道与住宅楼预埋幕墙埋件用4*40mm镀锌扁铁连接固定牢固(埋件为住宅楼避雷的一部分);
室外电梯顶端也用4*40mm镀锌扁铁将室外电梯和楼顶端避雷圈连接;
上端与室外电梯顶部避雷针锚固,避雷针采用直径20镀锌钢管,下焊70*70*5镀锌角钢,针尖采用直径16镀锌圆钢磨尖,安装长度高于室外电梯顶部1米。
五、电梯安装、拆除:
5.1.安装前的准备:
5.1.1、施工电梯的项目经理和租赁及安装工长详细了解施工现场的地形。施工现场负责清理、排除施工电梯安装(拆卸)作业周围的障碍物,保证吊车、运输车辆等顺利通行和作业。
5.1.2、施工现场负责做好施工电梯安装(拆卸)作业现场的安全防护区的警戒工作,严禁施工电梯安装(拆卸)时现场其他工种交叉作业和非安装(拆卸)人员穿行和停留。
5.1.3、项目经理或租赁工长、安装工长勘察施工现场后,应与委托单位签定安装(拆卸)合同一式三份,并分别下达安装(拆卸)任务书(填表一)、安全技术交底(填表二)。
5.2.电梯安装:严格按照《施工升降机使用说明书》要求安装拆卸。安装主要步骤如下: 5.2.1、将底座围栏安装就位,用水平仪测平后,将地脚螺栓插入预留孔内,浇注C30混凝土,待强度达到50%时,将螺栓预紧固。
5.2.2、安装3节标准节、下限位及下极限行程开关碰铁。
5.2.3、安装吊笼,注意就位前把拖动电机制动器释放,就位后恢复。调整齿轮和齿条的侧隙,滚轮和立柱的间隙,调整值为0.3-0.5mm。
5.2.4、将操作盒装在吊笼顶部的安全护栏上并接通电源,首先试车检查吊笼的运行方向是否与操作盒上的指示方向相符合。
5.2.5、安装导轨架,在标准节安装至第七或第八节,必须精确校正导轨架的垂直度,垂直度允差为1/1000。每安装六节都要进行一次垂直度校核。用吊杆安装时,注意其载重量为200kg。吊笼运行时,吊杆不得吊挂物品。用塔吊辅助安装时,一次只能拼接6节标准节。每安装一节或一组标准节,都必须按要求安装上限位及上极限行程开关碰铁。
5.2.6、安装导轨附着架,附着架允许的最大水平倾角为±10º-15º。导轨附着架安装的最
5.2.7、当导轨架达到所需高度后,安装天轮与对重钢丝绳。
5.2.8、整体安装完毕后试车3次,保证上限位及上极限碰铁灵敏有效。
5.3 电梯拆卸:
5.3.1、先将操作盒移置吊笼顶部,并校定其功能,然后将电动吊杆安装就位。
5.3.2、与装对重相反的程序,将对重钢丝绳卸下。
5.3.3、吊笼升到最高位置,用吊杆吊住承载天轮,拆下连接螺栓。转动吊臂放置吊笼顶部,运置地面。
5.3.4、将吊笼适当下行一段距离,用专用吊具吊住待卸标准节,确认吊笼上部滚轮总成位于待拆卸标准节连接点下方时,方可卸下连接螺栓。转动吊臂,将标准节置于吊笼顶,运置地面。
5.3.5、拆卸附着架等部件,应随拆随运到地面以防超载运行,也可以用起重机协助拆卸工作。
5.3.6、切断电源,拆除电缆和接地保护线。
5.3.7、拆除部件应码放整齐,妥善保管,以待装运。
六、安全注意事项:
6.1电梯安装要求:
6.1.1、外用电梯的安装、拆卸必须由合格的专业拆装队进行。所有操作人员需持有效证件上岗,工作中必须严格遵守《施工升降机使用说明书》的操作规程,严禁一切违章指挥,一切违章冒险作业。要有明确分工,各负其责,明确一人负责指挥工作,确定指挥联络信号。
6.1.2、外用电梯的安装、拆卸都要有制定安全技术措施,并对所有参加作业的人员进行有关的安全教育。
6.1.3、安装、拆卸前要组织有关技术人员,对各部件、各导轨架、附墙支撑及地基基础进行认真的安全技术检查,确认无误后才能进行安装或拆卸。
6.1.4、安装、拆卸作业要认真执行所制定的安全技术措施,并严格遵守原厂说明书所规定的拆装程序和各项要求。
6.1.5、安装、拆卸时必须要有专业技术人员在场指挥,分工要明确,指挥要统一,每个工作人员都必须遵守有关的安全操作规程,操作人员必须戴安全帽,高作业必须有安全带,作业区内要严禁非工作人员进入。
6.1.6、工作需要升降时,必须由有经验的专职司机操作,其它人员不得操作升降。工作笼每次开动前,司机必须与其它工作人员联系好后才能开动,要鸣警示意。
6.1.7、安装、拆卸时期,除按规定载运少量的安装工作人员及所用物料外,严禁带人、运物。每个吊笼平台作业人员、配备工具及待安装部件总重量不得超过650kg。。
6.1.8、导轨架安装必须垂直牢固,各附墙支撑必须符合规定要求。
6.1.9、外用电梯的安装完毕,要按规定进行调试,对各部位的安全装置要进行可靠性试验,对整机要进行荷载试验。并由主管部门组织检查验收,确认达到安全技术标准,并验收签字后方能投入使用。导轨架最大悬臂高7.5m。
6.1.10、各项装置必须齐全有效(限速器、超高限位装置、超低限位装置、钢丝绳事故限位装置、门限位装置、紧急开关、紧急制动闸)。
6.1.11、对重钢丝绳用四个卡子卡紧,两卡子之间的间距为80-100mm,注意应将绳卡底板扣在钢丝绳工作股上。检查钢丝绳是否符合国标。
6.1.12、整体安装完毕,用经纬仪进行正面和侧面的垂直度检测,标准是当架设高度
小于70m时,其偏差不大于高度的千分之一,架设高度70-100m时,共偏差不大于7cm。
6.1.13、地线采用专用的镀锌扁铁或大于Φ10的圆钢连接,电阻值不得大于4Ω,(安装前安装工长向施工现场要已签认合格的表三和保护接地的测试值报告)。
6.1.14、遇有雨、雪、雾及大风(五级以上)天气不得进行安装拆卸作业。
6.2电梯使用要求:
6.2.1、司机经过专门训练并经考试合格,发给操作证后,方可操作。
6.2.2、司机工作时,工作服要扣紧,带好安全帽。
6.2.3、不准超载工作,荷载严格限制在出厂规定的额定范围内。运送物料不得伸出在护网外面。
6.2.4、禁止非司机操作。
6.2.5、电梯每次起动前都要鸣警示意,操作业时司机必须精神集中,严禁与别人闲谈打闹,看书报等。
6.2.6、电梯升降时所有乘人员必须听从司机指挥,否则司机有权拒绝升降。
6.2.7、上班第一次开车离地一米停车,检查工作笼是否下滑、上爬。并做其它试运转,证明性能正常后,方可正式工作。
6.2.8、运送的物品在工作笼内必须平均分布,防止偏重。
6.2.9、随时注意信号,遇不正常情况立即停车。
6.2.10、在视线差、大雾、雷雨,导轨冰冻等危险条件下禁止开车。
6.2.11、合闸后司机不准离开吊笼,下班后吊笼降至地面,拉开电源开关,锁好操纵箱后才能离开。
6.2.12、制动器、限速器要经常检查调整,确保安全可靠,在其失灵或有故障时,严禁开车。
6.2.13、大风情况下开车要小心,风力超过6级时严禁开车,吊笼停于地面。
6.2.14、下班时要打扫梯笼,整理工作现场。拉开电源开关,检查机械部分有无损坏,做好当班记录,锁好司机室或做好交接班。
6.3电梯拆卸要求:
6.3.1、外用电梯拆卸过程中,要有专人统一指挥,并熟悉图纸、安装、拆卸程序及检查要点。
6.3.2、外用电梯安装、拆卸必须由合格的专业拆装队伍施工,并要制定安全技术措施,对所有人员进行安全交底教育。
6.3.3、拆卸前要组织有关技术人员对各中件、各导轨架、附墙支撑及地基基础进行认真的安全技术检查,确认无误后才能进行拆卸。
6.3.4、在拆除平衡重之前,必须对电梯及附壁杆、制动器的空隙,主转动机构的运行进行检查,确认正常后,方可拆除。
6.3.5、梯笼升至顶部,使平衡铁落地,然后再点动慢慢上升50 cm左右,梯笼不发生下滑,即可开始按顺序拆除。
6.3.6、先把平衡铁拆下来放平,拆下钢丝绳及无轮组,把梯笼升至接近柱顶处,拆除立柱标准节。此时梯笼处于无平衡重运行,梯笼内可以载两名工人和必要工具运行使用,必须用钢丝绳做保险,把梯笼顶部与钢丝绳牢固连接在立柱上,向下运行时,应靠梯笼自重分段逐节下滑,每下滑一个标准节,停车一次,以免超速刹车发热。
6.3.7、每拆除两个标准节,随之把附壁支撑同时拆下,拆下的附件装入梯笼时,其吊重不能超载,因无配重载重量应折减。
6.3.8、拆除附壁杆以及各层通道架板时,梯笼应随之停置在作业层的高度,不能在拆除过程中,梯笼同时上下运行。
6.3.9、所有施工人员必须严格按照操作规程作业,戴好安全帽,挂好安全带,作业区内要严禁非作业人员进入,整个拆装过程要有专业机械,安全人员在场监护。
6.3.10、大风情况下不得进行拆除作业,风力超过5级时严禁开车作业,梯笼应停于地面。
6.3.11、下班时要将现场整理干净,切断电源开关,锁好梯笼。
因违章作业造成的损失、事故一律由施工单位全部负责,甲方(中铁)还将依据有关规定给予处罚。
七、环保措施:
7.1进出现场不得大声喧闹,不得吸烟。
7.2不得随便乱扔纸屑、油料和废弃物、塑料袋等。
7.3严禁随地大小便。
7.4安装、拆卸的部件要集中放置,防止漏油污染。擦拭油物等使用的棉纱不得随地乱丢,放在专用塑料桶内,统一送运至项目指定的垃圾点处理。
7.5现场安装和拆卸时,不准大声喧哗。设专人专管,定期检查,保证施工电梯正常运转,杜绝因不正常运转而产生噪音。
八、质量标准:
8.2.1节架垂直度必须符合要求,偏差不得超过2‰ 。
8.2.2所有紧固件,开中销螺栓等必须紧固到位,一应俱全。
8.2.3所有安全限位必须齐全,灵活,有效。
8.2.4电气零部件绝缘可靠,不漏铜丝,接地电阻≤4欧姆。
8.2.5要轻吊轻放,吊点位置选择准确,保证结构件不变形。
8.2.6整机达到市建委颁布的验收标准,并出具书面资质,以供备查。