工程类外语文章

Why is sue important?

John Campbell,P,E, director of the Right of way Division at TxDOT and chair of the American association of state highway and transportation Officials ’(AASHTO) subcommittee on Right-of-way and utilities, initiated the SUE program in Texas. The SUE process, provides valuable engineering information from which to make risk-based decisions …for the delivery of transportation projects, Czmpbell says AtTxDOT, the use of SUE in project planning and design enables us to avoid unnecessary impacts to existing utilities and to save the incalculable costs of adjustments ” that were not required because the SUE process located the utilities beforehand and construction delays never occurred.

An FHW A guidebook, program guide: Utility relocation and Accommodadation on Federal-Aid Highway projecys(FHWA-IF-03-014),states that the proper use of this cost-effective professional engineering service will eliminate many of the utility problems typically encountered on highway projects. According to the guide ,problems reduced or eliminated include project delays caused by (1)waiting for utility relocations to be completed, so highway construction can begin ; and(2) redesign when construction cannot follow the original design due to unexpected utility conflicts Other problems avoided include (3)delays to contractors during highway construction caused by cutting, damaging , or discovering utility lines that were not

known to be present;(4)claims by constractors to project owners for delays resulting from unexpected encounters with utilities; and(5) deaths, injuries, property damage, and releases of product(such sa natural gas or wasterwater) into the envieonment caused by damaging utility lines that were not known to be there .

Jeffery Zaharewicz, FHW A value engineering/utilities program manager ,describes SUE as”one of the best tools available to successfully integrate the activities associated with utility relocation and coordination into the project development process.”

SUE SUCCESS STORIES

A sampling of successful outcomes that resulted from the use of SUE further demonstrates the benefits of this process

When widening I-75,the Georgia Department of Transportation(GDOT) planned to relocate existing water and sewer mains that led from a rest area to a source several miles away. After obtaining and analyzing SUE data, however, GDOT determined that no conflicts were present, and therefore relocating the lines would be unnecessary. This decision conservatively saved GDOT at least $400,000.

In Texas,he use of SUE data enabled consultants working for TxDOT to design around several high-pressure pipelines crossing a major State highway,S-130.To achieve this outcome, the designers shifted the schematic right-of-way approximately 300 feet(91 meters),avoiding

costly pipeline relocations. The right-of-way shift prevented project delays and resulted in accost savings of $3 million.

Hurricane Wilma damaged an estimated 10,000 trees in Coral Springs, FL, that therefore needed to be removed. Wishing to be proactive and prevent costly utility damage, the city hired an SUE provider to locate utilizes ahead of the tree removal crews. During the first week, SUE prevented sevsral major utility hits. Due to the quantity of utility lines found by the provider, the city changed its approach and decided to grind many tree trunks instead of going ahead with complete stump removal. In one area ,where SUE was not used, the tree removal crews hit a major water line on the first day.

The Early Days of SUE

The value of SUE became apparent to highway engineers when an engineering company in Manassas Park, V A, introduced the practice in 1982.The company combined two relatively new technologies- surface geophysics and air/vacuum excavation-to gather data on the exact location of subsurface utilities early in the development of projects.

One year later, the transportation department in nearby Fairfax County,V A,beame the first government agency to use SUE on highway projects. In 1985 the Virginia Department of Transportation(VDOT) became the first State agency to use it.

“We discovered many years ago that the old ways of obtaining

utilities information for design purposes were not working, ” says Greg Wroniewicz, VDOT utility engineer. SUE does work, and we use it on nearly every highway project.

FHW A began promoting SUE in 1991,shortly after its nationwide potential was recognized by Jim Overton, now retired but then-acting branch chief,and Jerry Poston,now deceased but then-branch chief, of FHW ’s former Railroads, Uilities, and Ptograms Branch. Poston was often heard to say that SUE would revolutionize the way utilities are handled on highway projects.

“His prophecy certainly came true, ” says Jon Obenberger, FHW A preconstruction group team leader. Reliable subsurface utility data now can be provided to highway designers, and it is no longer acceptable practice to design highways or construct projects without consideration of those data.

How Has SUE Evolved?

By the 1990s,the new approach had spread from Virginia into nearby States(Delaware, Maryland, North Carolina, and Pennsylvania) and then to more distant States(Arizona and Florida).As the practice of SUE spread, it evolved to include surveying, CADD, affixing of a professional engineer ’s seal to deliverables, and professional liability insurance.

SUE flourished in the 1990s as more States began using it, and more providers began to emerge. Probably the most significant advance in that

decade involved the introduction of the concept of the quality levels, which enabled designers to certify on project plans a certain level of comprehensiveness and accuracy for the utility information.

By the end of the 1990s,however,some confusion still existed as to just exactly what SUE was. Some companies were claiming that SUE meant subsurface utility exploration or ”pot-holing, ” rather than subsurface utility engineering. The latter provides more accurate and comprehensive information than can be obtained by randomly digging pot-holes. Some DOTs bought into the former concept with poor results that soured them on continuing the use of SUE.

The leading providers were aware that SUE was an engineering practice with quality levels and were promoting it as such .FHWA also recognized the distinction between an engineering practice and pot-holing and began strongly encouraging State DOTs to acquire the service of reputable SUE providers.

The need to quantify the value of SUE on highway projects had become apparent, as well as the need to establish standard guidelines for its use 。FHW A commissioned Purdue University to document and quantify SUE ’S value ,and the American Society of Civil Engineers (ASCE ),working with FHW A and industry ,agreed to establish national guidelines for collecting and depicting existing subsurface utility data 。

Research on the effectiveness of SUE

Purdue university published its report ,cost savings on high way projects utilizing subsurface Utility Engineering ,in 2000 。the Purdue researchers studied 71 projects in North Carolina,Ohio ,Texax ,and Virginia 。The projects involved a mix of interstate ,arterial ,and collector roads in urban ,suburban , and rural settings。

Two broad categories of savings emerged—quantifiable and qualitative savings 。The Purdue study quantified a total of $ 4.62 in avoided costs for every $ 1.00 spent on SUE 。 The greatest savings came from avoiding utility relocations and reducing delay claims。 Although qualitative savings (for example ,avoided impacts on nearby homes and business )were not measurble ,the researchers believed those savings were significant and possibly many times more valuable than the quantifiable savings。

The study conclueded that SUE is a viable technological practice that reduces project costs related to subsurface Utilities and that DOTs should use it in a systematic manner。 In addition ,the Ontario sewer and water main contractors association commissioned the university of Toronto to investigate the practice of using SUE on large infrastructure projects in Ontario 。this study chose nine case studies and determined that the average rate of return for

each dollar spend on SUE, revices on those projects was $3.41。 the study also made a number of qualitative recommendations regarding the use of SUE .

研究报告称地下工程实用是有关减少地下工程项目费用的可实行技术实践。州交通部应该以系统的方式加以使用。

另外,安大略下水道和总水管承包商协会委任多伦多大学调查在安大略大型基础设施项目中对地下工程实用的实际应用。这项研究选择了九个专题,并且确定项目应用地下工程实用后,每投入$3.41平均回报率为一美元。 研究也提出了一定数量的定性建议关于对地下工程实用的用途。

The asce standard

In 2003,ASCE defined SUE as an engineering practice in CI/ASCE 38-02,standard guideline for the collection and depiction of existing subsurface utility data 。The importance of this standard is that it indicated that,in addition to FHWA,a prominent national engineering organization defined SUE as an acceptable engineering practice and provided guidance for applying it on projects。

2003年, 美国土木工程师学会在CI/ASCE 38-02以工程学实践定义了地下工程实用,为汇集和描述现有地下下公用设备的标准指南。这个标准的重要性是它表明了,除联邦公路管理局之外,一个享誉全国的工程学组织也将地下工程实用定义为可接受的工程学实践和施工

指南。

The standard presents the system of classifying the quality level of sub face utility data。The classification enables project owners ,engineers ,and construction companies to develop strategies to reduce risks related to existing subsurface utilities or ,at a minimum ,to allocate the risks in a defined manner。 The standard closely follows concepts already in place in the USE profession 。 Many state Dots therefore are already in compliance with the standard through their use of SUE or through their inclusion of SUE specifications in their engineering contracts。

标准提出分类地下公用设备数据的质量水平系统。分类使业主、工程师和建筑公司在地下工程的开发战略中减少风险,或者用被定义为极小值方法来分配风险。 此标准与实际地下实用工程领域接轨。 因此许多州交通部已经依从标准通过对地下工程实用的应用,或通过在工程合同中对地下工程实用的规格。

The private sector and FHWA roles

The growth of SUE resulted from efforts by FHWA's headquarters and division offices to encourage state DOTs to use it and from state DOTs officials telling their counterparts about it 。but some of credit also must go to SUE professionals who understood the process and worked to sell the concept to

potential clients 。

地下工程实用的广泛应用要归功于联邦公路管理局的总部和分区办公室鼓励各州交通部对其使用以及各州官员对相应各个部门的宣传。但也必须为那些懂得如何使用地下工程实用和以及那些专门挖掘潜在客户的其销售商记功。

FHWA encouraged the use of SUE through memos to field offices 。Also ,division administrators and their staff engineers discussed SUE with their state DOT counterparts and encouraged them to give it a try 。FHAW developed flyers,brochures ,and handbooks and distributed them to the divisions and state DOT offices ;wrote numerous papers for conferences and publications,set aside funds for SUE-related research projects ;delivered presentations at conferences and workshops at approximately 20 state DOTs and other venues ;obtained funds to develop and / or distribute instructional videos ;and funded demonstration projects in Oregon ,Puerto Rico ,and Wyoming。

联邦公路管理局通过备忘方式鼓励工程行业部门对其应用。并且,分区官员和他们的人员技师与各州交通部做了商议并且鼓励他们试用地下工程实用。联邦公路管理局制定了传单、小册和手册将其分发给了各个分区办公室; 编写会议文稿,出版物,并且为地下工程实用相关的研究计划留出了资金; 在20多个州交通部和其他地点开展会

和演习班; 获得了制作和分发教育录像的资金; 并且资助了在俄勒冈、波多里哥和怀俄明的示范项目。

State DOTs promoted SUE by word of mouth and continue to do so 。“state DOTs utility engineers get together every year to discuss common issues,”says Chuck Schmidt,chief of design services at the New Hampshire DOT and vice-chair of AASHTO's subcommittee on right of-way and utilities 。 in the 1900s DOT utility engineers would meet at the national highway utility conference ,and for the past decade,we have gotten together at the AASHTO subcommittee conference on right-of-way and utilities 。we have special sessions where we talk about our common problems and possible solutions 。those who use SUE are not bashful about singing its praises and encourage everyone to use it 。in turn ,several states ,included SUE New Hampshire ,have included SUE as a normal course of business on several

各州部门以口传的方法推广和促进地下工程实用,坚持至今。“各州工程师每年聚会谈论共同的问题”,新罕布什尔州交通部设计院院长兼AASHTO 的小组委员会会长说。“ 在20世纪之内各州工程师在国道公共会议会面,并且在过去十年,我们在AASHTO 小组委员会会议聚集讨论关于公路线路和基础建设。我们有临时会议,我们谈论我们共同的问题和对其可能解决的方案。总有人大胆使用地下工程实用甚

至对其大加赞赏,并且鼓励大家使用地下工程实用,有几个州,包括

苏・新罕布什尔州,已经将地下工程实用作为一个正常商务课程。

Of our projects。

While FHWA and state DOTs were promoting the new approach ,

the SUE professionals were on the front lines 。 They visited

state DOTs in all part of country ,wrote papers for conferences

and articles for industry publications ;provided numerous

presentations ,demonstrations ,and exhibits at workshops and

conferences ;developed educational videos and provided them

to FHWA for distribution ;and held numerous workshops for state

DOTs 。

当联邦公路管理局和各州交通部推广这一新方法是,地下工程实用

的专家是站在最前线的,他们拜访了国家所有有关部门,并为会议编

写了文稿以及产业出版物的文章; 大做宣传,示范,展览; 制作教育

录影并将其联邦道路管理局,并且在各州交通部开设演习班。

Nick Zembillas ,senior principal and senior vice president ,

Cardno TBE ,say ,“Highway engineers had been locating

underground utilities with inaccurate as-builds and

backhoes ,often with disastrous results,and it was hard to

convinced them that there was a better way to obtain the

information 。But we did not give up and are still not

giving up on the ones that continue to hold to the old

ways .SUE is here to stay as an industry standard of care .”

尼克Zembillas ,资深校长兼副总裁, “公路工程师利用精度不

高的挖和反铲寻找地下工程,经常惨败收场。说服他们很困难,但是

这里有一个更好的方式来获得相关信息。但我们仍然没有放弃说服那

些仍旧使用老办法的人,地下工程实用已成行业标准”

SUB today

Federal , state ,and local highway agencies are using SUE,

as are design consultants, highway contractors, and utility

companies for public works projects around the country .The

military airports ,transit, hospitals, and ports also use it .

SUE spread from the Untied States into Canada in 2002 where

it is used routinely on highway projects from Toronto in the

east to Calgary in the west . one company alone has carried

out more than 450 projects .to standardize the practice in

Canada,the Canadian standards Association is developing a standard for mapping underground utility

infrastructure that will reference the use of SUE and the

ASCE 38-02 quality levels .

After SUE was introduced into the United Kingdom (UK)in

2008,it slowly gained recognition in London and other major

cities as a sound engineering process. Only a few small

projects have been completed to date , but interest in

developing something similar to the ASCE 38-02 standard seems

to be growing .

联邦,州和地方高速公路机构处都在使用地下工程实用,同时设计

顾问公司、高速公路承包商和公用工程公司在公共建设项目中对地下

工程实用正在广泛应用。军事机场、运输、医院和口岸也在应用。

2002年,地下工程实用从美国传入加拿大,被应用在在高速公路

从东部多伦多在到西部卡尔加里的高速公路项目中。一家公司单独执

行了450多个项目。加拿大规范工程实践,加拿大标准协会 开发一个标准以反映地下公共基础设施 ,将参考地下工程实用和

ASCE 38-02质量水平。

2008年,在地下工程实用被介绍进入英国之后,它在伦敦得到和

其他主要城市作为一个酣然的工程学过程慢慢得到了重视。迄今最然

只有几个小项目完成了,但是在开发与ASCE 38-02的标准兴趣似乎

增长。

In addition ,standards Australia is working with ASCE to

develop an engineering standard similar to ASCE 38-02 in

anticipation of the growth of SUE .The practice was introduced

only recently in Belgium ,China, New Zealand ,and the United

Arab Emirates.

SUE is an integral part of the National /Utility

/Issues(FHWA-NHI-134006).The course currently is being

updated to include conflict analysis ,which is the newest

engineering practice to evolve from SUE .SUE continues to be the subject of many presentations and workshops at conferences such as the annual conference of the AASHTO Right-of-Way and Utilities subcommittee, the transportation research board annual meeting ,and others。

另外,澳洲标准协会与美国土木工程学会一起使用开发工程学标准相似于ASCE 38-02预期成长为地下工程实用。而最近此项科学实践又被介绍到了比利时、中国、新西兰和阿拉伯联合酋长等国家。 地下工程实用是 国家/基础工程 /问题 (FHWA-NHI-134006)的整体部分。当前正在更新,包括冲突分析,是从地下工程实用中演变出的最新工程学惯例。地下工程实用仍然是许多会议的热门话题,比如AASHTO 基础建设小组委员会年会,运输研究委员会年会和其他一些会议。

Today ,utilities should no longer be unnecessarily relocated or unexpectedly encountered on highway projects 。 The application of SUE by transportation agencies and qualified providers who understand the practice makes it possible to avoid utility related problems that have plagued highway engineers for decades and thereby accelerate project delivery 。

C. Paul Scott ,P.E., has been Cardno TBE's national utilities liaison since 2003,joining it after retiring from FHWA ,where he worked for 34 years 。He received the university

of Tennessee and is a registered professional engineer in Kentucky and Virginia。

今天,在高速公路项目应该不会有多余地调迁或意想不到地下工程问题。 地下工程实用的实用者是交运机构和具有资格的并懂得如何避免已困扰了公路工程师数十年的公共问题从而加速项目交付的那些供应商家。

Why is sue important?

John Campbell,P,E, director of the Right of way Division at TxDOT and chair of the American association of state highway and transportation Officials ’(AASHTO) subcommittee on Right-of-way and utilities, initiated the SUE program in Texas. The SUE process, provides valuable engineering information from which to make risk-based decisions …for the delivery of transportation projects, Czmpbell says AtTxDOT, the use of SUE in project planning and design enables us to avoid unnecessary impacts to existing utilities and to save the incalculable costs of adjustments ” that were not required because the SUE process located the utilities beforehand and construction delays never occurred.

An FHW A guidebook, program guide: Utility relocation and Accommodadation on Federal-Aid Highway projecys(FHWA-IF-03-014),states that the proper use of this cost-effective professional engineering service will eliminate many of the utility problems typically encountered on highway projects. According to the guide ,problems reduced or eliminated include project delays caused by (1)waiting for utility relocations to be completed, so highway construction can begin ; and(2) redesign when construction cannot follow the original design due to unexpected utility conflicts Other problems avoided include (3)delays to contractors during highway construction caused by cutting, damaging , or discovering utility lines that were not

known to be present;(4)claims by constractors to project owners for delays resulting from unexpected encounters with utilities; and(5) deaths, injuries, property damage, and releases of product(such sa natural gas or wasterwater) into the envieonment caused by damaging utility lines that were not known to be there .

Jeffery Zaharewicz, FHW A value engineering/utilities program manager ,describes SUE as”one of the best tools available to successfully integrate the activities associated with utility relocation and coordination into the project development process.”

SUE SUCCESS STORIES

A sampling of successful outcomes that resulted from the use of SUE further demonstrates the benefits of this process

When widening I-75,the Georgia Department of Transportation(GDOT) planned to relocate existing water and sewer mains that led from a rest area to a source several miles away. After obtaining and analyzing SUE data, however, GDOT determined that no conflicts were present, and therefore relocating the lines would be unnecessary. This decision conservatively saved GDOT at least $400,000.

In Texas,he use of SUE data enabled consultants working for TxDOT to design around several high-pressure pipelines crossing a major State highway,S-130.To achieve this outcome, the designers shifted the schematic right-of-way approximately 300 feet(91 meters),avoiding

costly pipeline relocations. The right-of-way shift prevented project delays and resulted in accost savings of $3 million.

Hurricane Wilma damaged an estimated 10,000 trees in Coral Springs, FL, that therefore needed to be removed. Wishing to be proactive and prevent costly utility damage, the city hired an SUE provider to locate utilizes ahead of the tree removal crews. During the first week, SUE prevented sevsral major utility hits. Due to the quantity of utility lines found by the provider, the city changed its approach and decided to grind many tree trunks instead of going ahead with complete stump removal. In one area ,where SUE was not used, the tree removal crews hit a major water line on the first day.

The Early Days of SUE

The value of SUE became apparent to highway engineers when an engineering company in Manassas Park, V A, introduced the practice in 1982.The company combined two relatively new technologies- surface geophysics and air/vacuum excavation-to gather data on the exact location of subsurface utilities early in the development of projects.

One year later, the transportation department in nearby Fairfax County,V A,beame the first government agency to use SUE on highway projects. In 1985 the Virginia Department of Transportation(VDOT) became the first State agency to use it.

“We discovered many years ago that the old ways of obtaining

utilities information for design purposes were not working, ” says Greg Wroniewicz, VDOT utility engineer. SUE does work, and we use it on nearly every highway project.

FHW A began promoting SUE in 1991,shortly after its nationwide potential was recognized by Jim Overton, now retired but then-acting branch chief,and Jerry Poston,now deceased but then-branch chief, of FHW ’s former Railroads, Uilities, and Ptograms Branch. Poston was often heard to say that SUE would revolutionize the way utilities are handled on highway projects.

“His prophecy certainly came true, ” says Jon Obenberger, FHW A preconstruction group team leader. Reliable subsurface utility data now can be provided to highway designers, and it is no longer acceptable practice to design highways or construct projects without consideration of those data.

How Has SUE Evolved?

By the 1990s,the new approach had spread from Virginia into nearby States(Delaware, Maryland, North Carolina, and Pennsylvania) and then to more distant States(Arizona and Florida).As the practice of SUE spread, it evolved to include surveying, CADD, affixing of a professional engineer ’s seal to deliverables, and professional liability insurance.

SUE flourished in the 1990s as more States began using it, and more providers began to emerge. Probably the most significant advance in that

decade involved the introduction of the concept of the quality levels, which enabled designers to certify on project plans a certain level of comprehensiveness and accuracy for the utility information.

By the end of the 1990s,however,some confusion still existed as to just exactly what SUE was. Some companies were claiming that SUE meant subsurface utility exploration or ”pot-holing, ” rather than subsurface utility engineering. The latter provides more accurate and comprehensive information than can be obtained by randomly digging pot-holes. Some DOTs bought into the former concept with poor results that soured them on continuing the use of SUE.

The leading providers were aware that SUE was an engineering practice with quality levels and were promoting it as such .FHWA also recognized the distinction between an engineering practice and pot-holing and began strongly encouraging State DOTs to acquire the service of reputable SUE providers.

The need to quantify the value of SUE on highway projects had become apparent, as well as the need to establish standard guidelines for its use 。FHW A commissioned Purdue University to document and quantify SUE ’S value ,and the American Society of Civil Engineers (ASCE ),working with FHW A and industry ,agreed to establish national guidelines for collecting and depicting existing subsurface utility data 。

Research on the effectiveness of SUE

Purdue university published its report ,cost savings on high way projects utilizing subsurface Utility Engineering ,in 2000 。the Purdue researchers studied 71 projects in North Carolina,Ohio ,Texax ,and Virginia 。The projects involved a mix of interstate ,arterial ,and collector roads in urban ,suburban , and rural settings。

Two broad categories of savings emerged—quantifiable and qualitative savings 。The Purdue study quantified a total of $ 4.62 in avoided costs for every $ 1.00 spent on SUE 。 The greatest savings came from avoiding utility relocations and reducing delay claims。 Although qualitative savings (for example ,avoided impacts on nearby homes and business )were not measurble ,the researchers believed those savings were significant and possibly many times more valuable than the quantifiable savings。

The study conclueded that SUE is a viable technological practice that reduces project costs related to subsurface Utilities and that DOTs should use it in a systematic manner。 In addition ,the Ontario sewer and water main contractors association commissioned the university of Toronto to investigate the practice of using SUE on large infrastructure projects in Ontario 。this study chose nine case studies and determined that the average rate of return for

each dollar spend on SUE, revices on those projects was $3.41。 the study also made a number of qualitative recommendations regarding the use of SUE .

研究报告称地下工程实用是有关减少地下工程项目费用的可实行技术实践。州交通部应该以系统的方式加以使用。

另外,安大略下水道和总水管承包商协会委任多伦多大学调查在安大略大型基础设施项目中对地下工程实用的实际应用。这项研究选择了九个专题,并且确定项目应用地下工程实用后,每投入$3.41平均回报率为一美元。 研究也提出了一定数量的定性建议关于对地下工程实用的用途。

The asce standard

In 2003,ASCE defined SUE as an engineering practice in CI/ASCE 38-02,standard guideline for the collection and depiction of existing subsurface utility data 。The importance of this standard is that it indicated that,in addition to FHWA,a prominent national engineering organization defined SUE as an acceptable engineering practice and provided guidance for applying it on projects。

2003年, 美国土木工程师学会在CI/ASCE 38-02以工程学实践定义了地下工程实用,为汇集和描述现有地下下公用设备的标准指南。这个标准的重要性是它表明了,除联邦公路管理局之外,一个享誉全国的工程学组织也将地下工程实用定义为可接受的工程学实践和施工

指南。

The standard presents the system of classifying the quality level of sub face utility data。The classification enables project owners ,engineers ,and construction companies to develop strategies to reduce risks related to existing subsurface utilities or ,at a minimum ,to allocate the risks in a defined manner。 The standard closely follows concepts already in place in the USE profession 。 Many state Dots therefore are already in compliance with the standard through their use of SUE or through their inclusion of SUE specifications in their engineering contracts。

标准提出分类地下公用设备数据的质量水平系统。分类使业主、工程师和建筑公司在地下工程的开发战略中减少风险,或者用被定义为极小值方法来分配风险。 此标准与实际地下实用工程领域接轨。 因此许多州交通部已经依从标准通过对地下工程实用的应用,或通过在工程合同中对地下工程实用的规格。

The private sector and FHWA roles

The growth of SUE resulted from efforts by FHWA's headquarters and division offices to encourage state DOTs to use it and from state DOTs officials telling their counterparts about it 。but some of credit also must go to SUE professionals who understood the process and worked to sell the concept to

potential clients 。

地下工程实用的广泛应用要归功于联邦公路管理局的总部和分区办公室鼓励各州交通部对其使用以及各州官员对相应各个部门的宣传。但也必须为那些懂得如何使用地下工程实用和以及那些专门挖掘潜在客户的其销售商记功。

FHWA encouraged the use of SUE through memos to field offices 。Also ,division administrators and their staff engineers discussed SUE with their state DOT counterparts and encouraged them to give it a try 。FHAW developed flyers,brochures ,and handbooks and distributed them to the divisions and state DOT offices ;wrote numerous papers for conferences and publications,set aside funds for SUE-related research projects ;delivered presentations at conferences and workshops at approximately 20 state DOTs and other venues ;obtained funds to develop and / or distribute instructional videos ;and funded demonstration projects in Oregon ,Puerto Rico ,and Wyoming。

联邦公路管理局通过备忘方式鼓励工程行业部门对其应用。并且,分区官员和他们的人员技师与各州交通部做了商议并且鼓励他们试用地下工程实用。联邦公路管理局制定了传单、小册和手册将其分发给了各个分区办公室; 编写会议文稿,出版物,并且为地下工程实用相关的研究计划留出了资金; 在20多个州交通部和其他地点开展会

和演习班; 获得了制作和分发教育录像的资金; 并且资助了在俄勒冈、波多里哥和怀俄明的示范项目。

State DOTs promoted SUE by word of mouth and continue to do so 。“state DOTs utility engineers get together every year to discuss common issues,”says Chuck Schmidt,chief of design services at the New Hampshire DOT and vice-chair of AASHTO's subcommittee on right of-way and utilities 。 in the 1900s DOT utility engineers would meet at the national highway utility conference ,and for the past decade,we have gotten together at the AASHTO subcommittee conference on right-of-way and utilities 。we have special sessions where we talk about our common problems and possible solutions 。those who use SUE are not bashful about singing its praises and encourage everyone to use it 。in turn ,several states ,included SUE New Hampshire ,have included SUE as a normal course of business on several

各州部门以口传的方法推广和促进地下工程实用,坚持至今。“各州工程师每年聚会谈论共同的问题”,新罕布什尔州交通部设计院院长兼AASHTO 的小组委员会会长说。“ 在20世纪之内各州工程师在国道公共会议会面,并且在过去十年,我们在AASHTO 小组委员会会议聚集讨论关于公路线路和基础建设。我们有临时会议,我们谈论我们共同的问题和对其可能解决的方案。总有人大胆使用地下工程实用甚

至对其大加赞赏,并且鼓励大家使用地下工程实用,有几个州,包括

苏・新罕布什尔州,已经将地下工程实用作为一个正常商务课程。

Of our projects。

While FHWA and state DOTs were promoting the new approach ,

the SUE professionals were on the front lines 。 They visited

state DOTs in all part of country ,wrote papers for conferences

and articles for industry publications ;provided numerous

presentations ,demonstrations ,and exhibits at workshops and

conferences ;developed educational videos and provided them

to FHWA for distribution ;and held numerous workshops for state

DOTs 。

当联邦公路管理局和各州交通部推广这一新方法是,地下工程实用

的专家是站在最前线的,他们拜访了国家所有有关部门,并为会议编

写了文稿以及产业出版物的文章; 大做宣传,示范,展览; 制作教育

录影并将其联邦道路管理局,并且在各州交通部开设演习班。

Nick Zembillas ,senior principal and senior vice president ,

Cardno TBE ,say ,“Highway engineers had been locating

underground utilities with inaccurate as-builds and

backhoes ,often with disastrous results,and it was hard to

convinced them that there was a better way to obtain the

information 。But we did not give up and are still not

giving up on the ones that continue to hold to the old

ways .SUE is here to stay as an industry standard of care .”

尼克Zembillas ,资深校长兼副总裁, “公路工程师利用精度不

高的挖和反铲寻找地下工程,经常惨败收场。说服他们很困难,但是

这里有一个更好的方式来获得相关信息。但我们仍然没有放弃说服那

些仍旧使用老办法的人,地下工程实用已成行业标准”

SUB today

Federal , state ,and local highway agencies are using SUE,

as are design consultants, highway contractors, and utility

companies for public works projects around the country .The

military airports ,transit, hospitals, and ports also use it .

SUE spread from the Untied States into Canada in 2002 where

it is used routinely on highway projects from Toronto in the

east to Calgary in the west . one company alone has carried

out more than 450 projects .to standardize the practice in

Canada,the Canadian standards Association is developing a standard for mapping underground utility

infrastructure that will reference the use of SUE and the

ASCE 38-02 quality levels .

After SUE was introduced into the United Kingdom (UK)in

2008,it slowly gained recognition in London and other major

cities as a sound engineering process. Only a few small

projects have been completed to date , but interest in

developing something similar to the ASCE 38-02 standard seems

to be growing .

联邦,州和地方高速公路机构处都在使用地下工程实用,同时设计

顾问公司、高速公路承包商和公用工程公司在公共建设项目中对地下

工程实用正在广泛应用。军事机场、运输、医院和口岸也在应用。

2002年,地下工程实用从美国传入加拿大,被应用在在高速公路

从东部多伦多在到西部卡尔加里的高速公路项目中。一家公司单独执

行了450多个项目。加拿大规范工程实践,加拿大标准协会 开发一个标准以反映地下公共基础设施 ,将参考地下工程实用和

ASCE 38-02质量水平。

2008年,在地下工程实用被介绍进入英国之后,它在伦敦得到和

其他主要城市作为一个酣然的工程学过程慢慢得到了重视。迄今最然

只有几个小项目完成了,但是在开发与ASCE 38-02的标准兴趣似乎

增长。

In addition ,standards Australia is working with ASCE to

develop an engineering standard similar to ASCE 38-02 in

anticipation of the growth of SUE .The practice was introduced

only recently in Belgium ,China, New Zealand ,and the United

Arab Emirates.

SUE is an integral part of the National /Utility

/Issues(FHWA-NHI-134006).The course currently is being

updated to include conflict analysis ,which is the newest

engineering practice to evolve from SUE .SUE continues to be the subject of many presentations and workshops at conferences such as the annual conference of the AASHTO Right-of-Way and Utilities subcommittee, the transportation research board annual meeting ,and others。

另外,澳洲标准协会与美国土木工程学会一起使用开发工程学标准相似于ASCE 38-02预期成长为地下工程实用。而最近此项科学实践又被介绍到了比利时、中国、新西兰和阿拉伯联合酋长等国家。 地下工程实用是 国家/基础工程 /问题 (FHWA-NHI-134006)的整体部分。当前正在更新,包括冲突分析,是从地下工程实用中演变出的最新工程学惯例。地下工程实用仍然是许多会议的热门话题,比如AASHTO 基础建设小组委员会年会,运输研究委员会年会和其他一些会议。

Today ,utilities should no longer be unnecessarily relocated or unexpectedly encountered on highway projects 。 The application of SUE by transportation agencies and qualified providers who understand the practice makes it possible to avoid utility related problems that have plagued highway engineers for decades and thereby accelerate project delivery 。

C. Paul Scott ,P.E., has been Cardno TBE's national utilities liaison since 2003,joining it after retiring from FHWA ,where he worked for 34 years 。He received the university

of Tennessee and is a registered professional engineer in Kentucky and Virginia。

今天,在高速公路项目应该不会有多余地调迁或意想不到地下工程问题。 地下工程实用的实用者是交运机构和具有资格的并懂得如何避免已困扰了公路工程师数十年的公共问题从而加速项目交付的那些供应商家。


相关内容

  • 2015年职称英语考试证书领取
  • 2015年职称英语考试证书领取 2014年职称英语考试真题.模拟题尽收其中,千名业界权威名师精心解析,精细化试题分析.完美解析 成绩查询及证书发放时间 (一)一般在考试后三个月,考生可于本网站进行成绩查询.考试成绩单不另行发放,考生如有需要,请于考试成绩公布之日起 30天内自行下载打印. (二)领证 ...

  • 2015全国职称英语考试报考级别
  • 2015职称英语考试报考级别 2014年职称英语考试真题.模拟题尽收其中,千名业界权威名师精心解析,精细化试题分析.完美解 析一网 尽!在线做题就选针题库:http://www.dwz.cn/oXVZF 英语考试按职称的系列.级别分为A.B.C三个等级,专业人员按规定的级别任选一个语种参加考试.其中 ...

  • 关于学术英语教学的几点思考_王守仁
  • 编者按:"立足改革"是<中国外语>的办刊宗旨之一.作为<中国外语>的特色栏目,<改革论坛>贯彻百花齐放.百家争鸣的思想,长期以来一直关注我国的外语教学改革,力求全面展示我国外语教学改革和理论研究的成果,发表了百余篇探讨教学改革的稿件,推动了我国 ...

  • 中小学外语教学研究的统计分析方法使用调研
  • 第28卷第1期北京教育学院学报 Vol.28No.1中小学外语教学研究的统计分析方法使用调研* 李宗强** (阜阳师范学院信息工程学院外语系,安徽阜阳 236041) 摘要:通过调查2001年-2010年国内两种主要的中小学阶段外语教学研究核心期刊发表的 中小学英语教学论文中统计分析方法的使用特点, ...

  • 业绩证明材料
  • 业绩证明材料 业绩证明材料 职称评审工作是一项认真细致的工作,涉及单位与个人两个方面.为了帮助单位及广大专业技术人员准备好高级职称评审材料,使申报材料更加规范.整齐,我们根据评审工作的需要及以往评审时遇到的常见问题,把有关注意事项归纳整理,介绍给大家,供参考. 一.职称评审的程序 按照个人自愿提出申 ...

  • 工程师评职称流程
  • 一.申报级别:助理工程师.中级工程师.高级工程师 二.申报所需材料: 1.助理工程师:身份证复印件,毕业证原件(本科毕业1年或1年以上,专科毕业2年或2年以上),本专业工作经验两年. 2.工程师:身份证复印件.毕业证原件(本科毕业要求4年或4年以上,专科毕业要求5年或5年以上),助理工程师原件(助理 ...

  • 英文合同翻译之我见
  • 2004年第20卷第1期(总第75期) 华北工学院学报(社科版) JOURNAL OF NCUST (Soc i al Sc iences ) . 20 N o . 1 2004V o l (Sum . 75) 文章编号:100924520(2004) 0120026202 英文合同翻译之我见 Ξ ...

  • 翻译能力与外语能力相关性的实证研究及对翻译教学的启示
  • 第20卷 第4期 浙江万里学院学报 Vol.20 No.4 翻译能力与外语能力相关性的实证研究 及对翻译教学的启示 范 勇 (南京信息工程大学,江苏 南京 210044) 摘 要:运用数理统计软件,对124名学生2003年专业八级统考中汉译英.英译汉成绩与其他"纯"英语技能(听力 ...

  • 从通用英语到学术英语_回归大学英语教学本位_蔡基刚
  • =5>:C5:8A5>7B;8: (复旦大学外文学院,上海200433) 要:我国大学英语教学面临的危机.英语在我国已成为世界通用语性质.经济全球化的挑战.高等教育国际 摘 化需求等情况决定了我国大学英语教学必须重新定位,从通用英语向学术英语转型,从应试到应用,回归大学英语教学本位.学术 ...

  • 江苏省石油化工专业研究员级高级工程师资格条件
  • 江苏省石油化工专业研究员级高级工程师资格条件(2004 年度)(一)学历.资历要求 学历. 大学本科以上学历(学位) ,取得高级工程师资格后,从事本专业技术工作 5 年以上. (二)计算机和年度考核要求 职称计算机要求按"苏人通[2004]24 号"文件有关规定执行. 任现职期间 ...