目 录
马驹桥西区康桥溪镇住宅小区临水消防安全工程施工方案
目录···························································1 一、编制依据··················································2 二、工程概况··················································2 三、施工安排··················································2 四、施工准备··················································3 五、给、排水、消防平面布置···································3 六、质量要求··················································9 七、临时用水系统的维护与管理·································9 八、现场临水、消防应急小组组织机构···························10 九、消防安全保障体系网络图····································10 十、附图:临水系统图··········································11 十一、附图:临水平面布置图·····································12 十二、附图:临建平面布置图·····································13
施工方案
1、编制依据
1.1、康桥溪镇住宅小区区建筑施工现场总平面布置图及施工工人生活区总平面布置图。
1.2、施工现场状况及给定施工现场给水位置,管径、现场市政排水井位置,标高。
1.3、《北京市建筑工程施工现场保卫消防标准》及其它相关法规和规定。 1.4、康桥溪镇住宅小区建筑工程施工组织设计。
2、工程概况
2.1、马驹桥西区康桥溪镇住宅小区工程由北京嘉禾远东置业有限公司投资建设,北京正华建筑设计事务所设计,北京城建北方建设有限责任公司总承包施工。工程位于北京通州区马驹桥镇,北临兴华中街,西临西滨河路,南侧与六环高速公路北辅路相隔,西临西凤减河。
2.2、本工程规划建设用地面积250346.72m2,总建筑面积为148269.86 m2,由81栋多层住宅组成。结构形式为短肢剪力墙结构,工程开工日期为2007年3月,竣工日期为2007年11 月。
3、施工安排
根据施工组织设计及建筑平面布置图,结合生活、生产安全需要,对规划区内用水设施,排水区域、消防面积进行实地勘察测量。掌握给、排、消防管道走向、坡度、标高,了解规划区内地下市政管网、电信等公共设施,对规划区给水、消防用水量进行准确计算,确定给水管径,使其保证生活、生产、消防安全要求,制定规划区临时给水、排水、消防管道施工措施及施工计划,为施工提供切实可行的施工依据,作好技术准备。
4、施工准备
4.1、施工人员配备 焊 工 三名
水暖工 五名 勤杂工 八名 质检员 一名 4.2、机具设备准备
套丝机 一套 电焊机 三套 砂轮切割机 一套 氧焊割设备 一套
以及管钳、压力泵、手锤、钢卷尺(检测合格)等相应的手工工具。 4.3技术准备
对施工人员进行书面交底,并配合图纸对现场进行实地详细解释,使施工人员了解设计意图精心施工,保证质量,符合设计及规范要求。
4.4、材料准备:
按设计图纸,对其工程量:管线、阀门及其管件认真计算,进场材料要有有效检验报告及产品合格证等证明文件。
5、给、排水、消防平面布置
5.1、由于施工用水及消防用水采用同一管线供水,因此根据消防用水的有关管理规定,供水水管管径确定为100mm。为保证消防用水使用,本方案确定施工用水管网与市政自来水管网连通。在施工用水管道与市政管网连通处加装止回阀及蝶阀,此连通处蝶阀只在发生火灾时开启。正常情况下绝
对关闭,并安排专人每天定期巡查。(见临水平面及系统图)
5.2、所有消防施工用水的管路均采用焊接钢管,生活用水采用镀锌钢管。
5.3、临时用水水源:
5.3.1施工水源:本工程施工现场水源由南区西北角的水泵房供给(为地下水),管径为DN100,其具体计算如下:
5.3.2、施工用水量计算 Q1N1 k2
q1=k∑———·————
T1t 8×3600
=k1∑Q1N1k2/(T1t×8×3600)
=1.05×200×12000×1.5/(8×3600)(300×1.5) =0.29L/S
q1:施工用水量(L/S)
k:未预计的施工用水系数(1.05-1.15) Q1:年(季)度实物使用量(立方米) N1:施工用水定额(升/立方米) T1:年(季)度有效作业天数(天) t:每天工作班数
k2:用水不均衡系数
5.3.2 机械用水较少,忽略不计:
q2=0
5.3.3 生活用水量计算: P1N3K4 q3= ————— t×8×3600
=2600×20×1.5/(1.5×8×3600)
=1.81 L/S
q3:生活区生活用水量(L/S) p1:生活区居住人数
N3:生活区生活用水定额(20升/人.班) t:每天工作班数(班)
k4:用水不均衡系数(2.00-2.50) 5.3.4消防用水: q4=10~15L/S
5.3.5总用水量:当q1+q2+q3
=0.29L/S+1.81L/S =2.1L/S
5.3.6管径计算:
·Q ×15
————————————
π·v·1000 3.14×1.5×1000
≈0.100m
根据计算:给水管选用DN100 焊接钢管,生活区干管选用DN65热度锌钢管,能够满足生活,生产消防要求。
5.4生活区给水系统干管为DN65,镀锌钢管焊接,埋地深度为0.80m以下,设DN65主控阀门及井一个,其配水点如下(具体位置,管径详见附图)。
配水点如下: 具体位置,管径见总平面布置图。 5.5生活区排水系统:
本方案设计污/废水合流排放。排水干管的布置根据现场市政排水管网确定,现场生活区排水主要考虑临时食堂、宿舍、厕所及其它临时建筑等。食堂的污水经隔油池后排入污水管网;厕所排污出户后经化粪池、沉淀池处理后再排入市政污水管网。排水系统室内采用排水U-PVC排水管,室外采用水泥管d=200mm埋地。
考虑现场设公共厕所,其化粪池按2600人考虑,根据化粪池容积计算公式得出:
W=W1+W2
=Nnqt/24×1000+1.2[aNnT(1-b)k/(1-C) ×1000](m3)
=1300×10%×30×30×24 +1.2×[0.4×1300×0.1×30×(1-25%)×0.8] 24×1000×6 (1-90%)×100 =11+8 =19(m3)
其中: W1:化粪池污水部分容积(m3) W2:化粪池污泥部分容积(m3)
N:使用卫生器具总人数
q:最高日生活用水量定额(取30L/人日) t:污水在化粪池内停留时间(时) n: 卫生设备同时使用百分数(取10%) a=0.4L/人日 b:污泥含水率b=25% c:浓缩后污泥含水率c=90% k:腐化期间污泥缩减系数k=0.80 T:清掏周期(天)
3
故化粪池选用2个4A号砖砌化粪池有效容积是20m(做法见91SB-排158
页),清掏周期1个月,可以满足使用要求。
5.6生活区消防系统:
生活区域横跨35m,纵长150m、生活区内设DN65消防栓三处,配置消防
箱及25m长水龙带,按具体位置计算、消防半径为25m,覆盖整个生活区,消防栓安装高度为1.10m消防箱就近设置,配全其它警示标志。
消防设备: 5.7施工区给水系统:
每栋楼施工用水支管采用DN25焊接钢管与埋地主管道焊接,支管立管在引出地面1米处安装截至阀一个供此楼施工用水。楼层施工用水采用橡胶软管接至施工用水点。
5.8施工区消防系统:
5.8.1施工区域共设置80处地上式单口消火栓,消防栓覆盖直径为60m(水龙带25m),整个施工区域将被全部覆盖、消防覆盖面积等于100%,局部重复覆盖,满足现场消防安全要求。
5.8.2施工区消防管为DN100焊接钢管,沿现场环形消防道路埋地,埋地深度为0.80m以下,地下主、支干管接成环状。
5.12.3消火栓分地上式,口径DN65,就近设置消防箱、栓、水龙带等相关配套警示标志,消火栓周围5m内不堆放任何材料、工具等。木料堆放加工区,易燃品库区设重复专用消火栓,消防道路保证畅通无阻。
消防设备:
具体位置,管径详见平面布置图
6、质量要求
6.1、规划区域内所有埋地管道均为焊接,刷防锈漆一道,沥清漆一道,隐
蔽前作水压试验,试验压力为0.9MPa,合格后即行隐蔽,埋地深度为0.8m以下。
6.2、埋地管道作防锈刷漆处理,地下管道埋地深0.80m以下。 6.3、材料:
所有工程材料入场前认真检查,不合格材料严禁使用,阀门管件,管材及其它设备均应有产品检验报告产品出厂合格证。
6.4所有给水,消防管道试压合格后进行冲洗,排水进入市政管道必须沉淀过滤处理后,才能排放。
6.5施工过程中,严格执行各项技术规程及施工规范,积累搜集各项技术资料,保证各项资料齐全,确保工程质量。
7、临时用水系统的维护与管理
7.1、施工时应注意保证消防管路畅通,消火栓箱内设施完备且箱前道路
畅通,无阻塞或堆放杂物。
7.2、现场消防及生产用水干管的埋深应在本地区冻土层以下。 7.3、现场平面应及时清扫,保证干净、无积水。
八、现场临水、消防应急小组组织机构
组 长:申欲斌
副组长:姜金鹏 刘同希 组 员:共8人,待开工后确定。
九、消防安全保障体系网络图
项目部所有管理人员在项目经理领导下,参与施工生活区,施工现场消防安全工作,日常消防安全监督、检查工作由安全员负责,施工过程中出现的安全隐患,安全员及现场管理人员有权责令其整改、停工、处罚,各专业工长密切配合,严格执行各项消防,安全条例,法规及规定。
十、附图:临水系统图
目 录
马驹桥西区康桥溪镇住宅小区临水消防安全工程施工方案
目录···························································1 一、编制依据··················································2 二、工程概况··················································2 三、施工安排··················································2 四、施工准备··················································3 五、给、排水、消防平面布置···································3 六、质量要求··················································9 七、临时用水系统的维护与管理·································9 八、现场临水、消防应急小组组织机构···························10 九、消防安全保障体系网络图····································10 十、附图:临水系统图··········································11 十一、附图:临水平面布置图·····································12 十二、附图:临建平面布置图·····································13
施工方案
1、编制依据
1.1、康桥溪镇住宅小区区建筑施工现场总平面布置图及施工工人生活区总平面布置图。
1.2、施工现场状况及给定施工现场给水位置,管径、现场市政排水井位置,标高。
1.3、《北京市建筑工程施工现场保卫消防标准》及其它相关法规和规定。 1.4、康桥溪镇住宅小区建筑工程施工组织设计。
2、工程概况
2.1、马驹桥西区康桥溪镇住宅小区工程由北京嘉禾远东置业有限公司投资建设,北京正华建筑设计事务所设计,北京城建北方建设有限责任公司总承包施工。工程位于北京通州区马驹桥镇,北临兴华中街,西临西滨河路,南侧与六环高速公路北辅路相隔,西临西凤减河。
2.2、本工程规划建设用地面积250346.72m2,总建筑面积为148269.86 m2,由81栋多层住宅组成。结构形式为短肢剪力墙结构,工程开工日期为2007年3月,竣工日期为2007年11 月。
3、施工安排
根据施工组织设计及建筑平面布置图,结合生活、生产安全需要,对规划区内用水设施,排水区域、消防面积进行实地勘察测量。掌握给、排、消防管道走向、坡度、标高,了解规划区内地下市政管网、电信等公共设施,对规划区给水、消防用水量进行准确计算,确定给水管径,使其保证生活、生产、消防安全要求,制定规划区临时给水、排水、消防管道施工措施及施工计划,为施工提供切实可行的施工依据,作好技术准备。
4、施工准备
4.1、施工人员配备 焊 工 三名
水暖工 五名 勤杂工 八名 质检员 一名 4.2、机具设备准备
套丝机 一套 电焊机 三套 砂轮切割机 一套 氧焊割设备 一套
以及管钳、压力泵、手锤、钢卷尺(检测合格)等相应的手工工具。 4.3技术准备
对施工人员进行书面交底,并配合图纸对现场进行实地详细解释,使施工人员了解设计意图精心施工,保证质量,符合设计及规范要求。
4.4、材料准备:
按设计图纸,对其工程量:管线、阀门及其管件认真计算,进场材料要有有效检验报告及产品合格证等证明文件。
5、给、排水、消防平面布置
5.1、由于施工用水及消防用水采用同一管线供水,因此根据消防用水的有关管理规定,供水水管管径确定为100mm。为保证消防用水使用,本方案确定施工用水管网与市政自来水管网连通。在施工用水管道与市政管网连通处加装止回阀及蝶阀,此连通处蝶阀只在发生火灾时开启。正常情况下绝
对关闭,并安排专人每天定期巡查。(见临水平面及系统图)
5.2、所有消防施工用水的管路均采用焊接钢管,生活用水采用镀锌钢管。
5.3、临时用水水源:
5.3.1施工水源:本工程施工现场水源由南区西北角的水泵房供给(为地下水),管径为DN100,其具体计算如下:
5.3.2、施工用水量计算 Q1N1 k2
q1=k∑———·————
T1t 8×3600
=k1∑Q1N1k2/(T1t×8×3600)
=1.05×200×12000×1.5/(8×3600)(300×1.5) =0.29L/S
q1:施工用水量(L/S)
k:未预计的施工用水系数(1.05-1.15) Q1:年(季)度实物使用量(立方米) N1:施工用水定额(升/立方米) T1:年(季)度有效作业天数(天) t:每天工作班数
k2:用水不均衡系数
5.3.2 机械用水较少,忽略不计:
q2=0
5.3.3 生活用水量计算: P1N3K4 q3= ————— t×8×3600
=2600×20×1.5/(1.5×8×3600)
=1.81 L/S
q3:生活区生活用水量(L/S) p1:生活区居住人数
N3:生活区生活用水定额(20升/人.班) t:每天工作班数(班)
k4:用水不均衡系数(2.00-2.50) 5.3.4消防用水: q4=10~15L/S
5.3.5总用水量:当q1+q2+q3
=0.29L/S+1.81L/S =2.1L/S
5.3.6管径计算:
·Q ×15
————————————
π·v·1000 3.14×1.5×1000
≈0.100m
根据计算:给水管选用DN100 焊接钢管,生活区干管选用DN65热度锌钢管,能够满足生活,生产消防要求。
5.4生活区给水系统干管为DN65,镀锌钢管焊接,埋地深度为0.80m以下,设DN65主控阀门及井一个,其配水点如下(具体位置,管径详见附图)。
配水点如下: 具体位置,管径见总平面布置图。 5.5生活区排水系统:
本方案设计污/废水合流排放。排水干管的布置根据现场市政排水管网确定,现场生活区排水主要考虑临时食堂、宿舍、厕所及其它临时建筑等。食堂的污水经隔油池后排入污水管网;厕所排污出户后经化粪池、沉淀池处理后再排入市政污水管网。排水系统室内采用排水U-PVC排水管,室外采用水泥管d=200mm埋地。
考虑现场设公共厕所,其化粪池按2600人考虑,根据化粪池容积计算公式得出:
W=W1+W2
=Nnqt/24×1000+1.2[aNnT(1-b)k/(1-C) ×1000](m3)
=1300×10%×30×30×24 +1.2×[0.4×1300×0.1×30×(1-25%)×0.8] 24×1000×6 (1-90%)×100 =11+8 =19(m3)
其中: W1:化粪池污水部分容积(m3) W2:化粪池污泥部分容积(m3)
N:使用卫生器具总人数
q:最高日生活用水量定额(取30L/人日) t:污水在化粪池内停留时间(时) n: 卫生设备同时使用百分数(取10%) a=0.4L/人日 b:污泥含水率b=25% c:浓缩后污泥含水率c=90% k:腐化期间污泥缩减系数k=0.80 T:清掏周期(天)
3
故化粪池选用2个4A号砖砌化粪池有效容积是20m(做法见91SB-排158
页),清掏周期1个月,可以满足使用要求。
5.6生活区消防系统:
生活区域横跨35m,纵长150m、生活区内设DN65消防栓三处,配置消防
箱及25m长水龙带,按具体位置计算、消防半径为25m,覆盖整个生活区,消防栓安装高度为1.10m消防箱就近设置,配全其它警示标志。
消防设备: 5.7施工区给水系统:
每栋楼施工用水支管采用DN25焊接钢管与埋地主管道焊接,支管立管在引出地面1米处安装截至阀一个供此楼施工用水。楼层施工用水采用橡胶软管接至施工用水点。
5.8施工区消防系统:
5.8.1施工区域共设置80处地上式单口消火栓,消防栓覆盖直径为60m(水龙带25m),整个施工区域将被全部覆盖、消防覆盖面积等于100%,局部重复覆盖,满足现场消防安全要求。
5.8.2施工区消防管为DN100焊接钢管,沿现场环形消防道路埋地,埋地深度为0.80m以下,地下主、支干管接成环状。
5.12.3消火栓分地上式,口径DN65,就近设置消防箱、栓、水龙带等相关配套警示标志,消火栓周围5m内不堆放任何材料、工具等。木料堆放加工区,易燃品库区设重复专用消火栓,消防道路保证畅通无阻。
消防设备:
具体位置,管径详见平面布置图
6、质量要求
6.1、规划区域内所有埋地管道均为焊接,刷防锈漆一道,沥清漆一道,隐
蔽前作水压试验,试验压力为0.9MPa,合格后即行隐蔽,埋地深度为0.8m以下。
6.2、埋地管道作防锈刷漆处理,地下管道埋地深0.80m以下。 6.3、材料:
所有工程材料入场前认真检查,不合格材料严禁使用,阀门管件,管材及其它设备均应有产品检验报告产品出厂合格证。
6.4所有给水,消防管道试压合格后进行冲洗,排水进入市政管道必须沉淀过滤处理后,才能排放。
6.5施工过程中,严格执行各项技术规程及施工规范,积累搜集各项技术资料,保证各项资料齐全,确保工程质量。
7、临时用水系统的维护与管理
7.1、施工时应注意保证消防管路畅通,消火栓箱内设施完备且箱前道路
畅通,无阻塞或堆放杂物。
7.2、现场消防及生产用水干管的埋深应在本地区冻土层以下。 7.3、现场平面应及时清扫,保证干净、无积水。
八、现场临水、消防应急小组组织机构
组 长:申欲斌
副组长:姜金鹏 刘同希 组 员:共8人,待开工后确定。
九、消防安全保障体系网络图
项目部所有管理人员在项目经理领导下,参与施工生活区,施工现场消防安全工作,日常消防安全监督、检查工作由安全员负责,施工过程中出现的安全隐患,安全员及现场管理人员有权责令其整改、停工、处罚,各专业工长密切配合,严格执行各项消防,安全条例,法规及规定。
十、附图:临水系统图