龙门架安装.拆除施工方案

目 录

1. 工程概况 . ....................................................................................................... 2 2. 龙门架概况 .................................................................................................... 2 3、施工准备 ..................................................................................................... 3 3.1材料准备 ............................................................................................... 3 3.2劳动准备 ............................................................................................... 3 3.3工具准备 ............................................................................................... 3 3.4作业条件 ............................................................................................... 3 4、工艺流程 ..................................................................................................... 4 5、施工部署和工艺操作 .................................................................................. 4 5.1基础施工 ............................................................................................... 4 5.2架体安装 ............................................................................................... 4 5.3安装附墙架 . ........................................................................................... 5 5.4吊篮安装 ............................................................................................... 6 5.5卷扬机的安装 ........................................................................................ 6 5.6安全防护装置 ........................................................................................ 6 5.7传动系统安装 ........................................................................................ 7 5.8卷扬机安装 . ........................................................................................... 8 5.9吊篮安全装置安装................................................................................. 8 5.10电气设备安装 ......................................................................................... 8

龙门架安装、拆除施工方案

1. 工程概况

1.1该工程为六安广电中心叶集分中心,总建筑面积7703㎡,框架六层,标准层层高3.6m ,主楼底层层高4.2 m,附楼高15m ,建筑高度23.4m 。结构类型为桩基承台基础、框架结构。龙门架操作及安装区域内无高压线。 1.2施工条件:龙门架布置在现场主楼北面,相关二级电箱布置到现场,详见临时用电布置图。

1.3本工程采用一台龙门架,是郑州宏茂机械厂生产的SSE160施工升降机, 起重量: ≤1.5t 。提升机有生产许可证,产品合格证。

2. 龙门架概况

本工程使用的龙门架吊篮尺寸为3.5m ×1.9m ,安装高度30m ,吊盘使用高度为1.9m ,起重量为1t ,螺栓M16,导轨63×40×4.8,节间尺寸1.9m 。主要技术参数见下表

3、施工准备 3.1材料准备

3.1.1 架体材料,吊篮——符合龙门架设计要求

3.1.2 卷扬机、钢丝绳——与龙门架吊篮提升机重量相匹配 3.1.3 电气设备——整套 3.2劳动准备

3.2.1 龙门架安装工人3人——经培训执证上岗

3.2.2 机械安装操作工2人、电工1人——经培训持证上岗 3.3工具准备

3.3.1 专工扳手,尼龙绳φ1.5mm 、60m 3.3.2 安全帽、安全带——操作者每人1套 3.4作业条件

3.4.1 材料、设备工具、劳动准备就绪

3.4.2 井架基础施工完毕,经验收合格,满足安装、使用要求。 4、工艺流程

基础施工→架体安装→滑轮安装→卷扬机安装→电器、限位设备安装→试车→验收

5、施工部署和工艺操作 5.1基础施工

在准备安装龙门架的位置对比井孔尺寸每边大400mm 进行放线挖土,地基打夯、地基承载力≦80kpa ,整个龙门架架基础捣C20砼厚500mm ,基础顶面平整度偏差≧10mm ,在捣制龙门架基础四角架拉处预埋螺栓M20×450。龙门架基础砼要求送实验室进行检测。 5.2架体安装

5.2.1 架体安装顺序:安装底座→标准节安装→顶部天粱安装→滑轮、吊篮安装→标准节提升、加高

5.2.2 待架体基础砼强度达到70%以上以后,才能安装架体。若基础顶不平时,必须用铁板垫平架底,并且要牢固可靠。反复核对架座的水平度,然后锚牢架底座,并核对底座的对角线。

5.2.3底座安装时四角对准基础预埋螺栓,并拧牢,要求底座安装平整,方正、牢固, 水平误差1℅。

5.2.4安装前,清点检查升降机龙门架各标准节,翘曲不平的要校正,各安全装置是否齐全有效。安装时,先把底座放在基础上,上紧锚螺栓。将升降台放在安装好的底架上。安装基础节,左右各一节。安装扒杆,并穿绕钢丝绳。在两个基础节的顶部各安装一个支架。并挂上手拉葫芦。拉动手拉葫芦,

将升降机台提升到基础节上部,并使用卡板将升降台固定在两基础节间。松动手拉葫芦,取下两个支架。转动扒杆,摇动手摇减速机,分两次起吊两个标准节分别加在两个基础节上,并用螺栓紧固,用螺母拧紧。在两个标准节上部安装支架,挂上手拉葫芦,拉动手拉葫芦将升降台升到标准节最上部并固定。取下支架。将吊篮放置两柱架之间的底架上。

5.2.5 操作人员必须戴好安全帽,绑好安全带,并且必须穿软底胶鞋进行施工。在搭好第二节架体后,可用滑轮提送工具、零件等。

5.2.6调整架体垂直和架体的稳定性,滑轨安装在水平杆上,垂直度偏差≧导轨架架设高度的1‰,架体垂直度偏差≧导轨架架设高度的3‰,并≧200mm 。井架位置正确,每节接头偏差≧5mm 。导轨接点截面相互错位≧1.5mm, 吊篮导轨与导轨的安装间隙在5-10 mm以内。

5.2.7在架体安装时,每安装4个标准节(≧8m )应采取临时支撑固定,进行初校正,在确定稳定时,方可继续作业。本工程根据实际情况每层设置一组附墙。

5.3安装附墙架

当架体随着建筑物升高而加高的同时,需要对架体进行附着,架体用管及扣件与建筑物连接,每层进行附着设置。 注意:

(l )架体的附墙架与龙门架架体的加高必须同时进行。加管与标准节和建筑物的连接可靠。

(2)附着架必须与建筑墙体内预埋件连接,不得与脚手架钢管连接。

5.4吊篮安装 5.4.1吊篮组

吊篮由底盘、竖杆、斜杆、横梁、角撑、侧围、进料门、出料门、顶棚组成。底盘由大梁搁栅和铺板构成。 5.4.2 吊篮安全装置 a 、吊篮停车安全装置 b 、吊篮钢丝绳断后的安全装置 5.5卷扬机的安装

5.5.1. 卷扬机安装,其基础尺寸为1500 ×1500×600mm ,用C20素砼浇筑,基础顶面必须水平。在浇砼前,先打好迎头桩和牵拉桩,采用Φ48mm 钢管长为2000,埋深不得少于1700mm ,卷扬机必须设有地锚,并且采用不少于两根钢丝 绳与卷扬机联接。 5.5.2. 稳定性验算

基础自重:1.5×1.5×0.6×2.5=3.38t 牵引力:1.5t

卷扬机支座前点力矩:3.38×0.75>1.5×0.6 验算结果:基础牢固、稳定。 5.6安全防护装置

5.6.1龙门架进料口必须设安全门,并要求有联动装置。

5.6.2吊篮顶部要安装防护网,吊篮进出口处设安全门,两侧设栏杆,用钢丝网封闭。

5.6.3卷扬机必须搭防护棚,并且不影响卷扬机操作员的视线。

5.6.4龙门架进料口必须按要求搭设好安全防护棚,按本工程搭设高度26m ,搭设防护棚长度应为4m 。

5.6.5龙门架架体采用2000目的密目网封闭好,操作视线面用大孔网如平网封闭。

5.6.6卸料平台要求单独搭设,不能搁置在外脚手架或龙门架架体上,并要设置拦腰杆及踢脚板、挂网封闭。 5.7传动系统安装

5.7.1龙门架架顶部和底侧部安装传动滑轮,滑轮直径选用≥20d (d 为钢丝绳的直径)。

5.7.2 起重钢丝绳的选用 5.7.3荷载取值

吊篮重0.39T 起重量)1.5T

安全系数n=5 破断拉力为SP=5×(0.39+1.5)=9.45T SP=1/2d² d=2SP(英分、1英分=3.175mm)

d=2SP=(2×9.45)1/2=4.35=5英分=5×3.175=15.88mm 取d=16mm

5.7.3 钢丝绳长度选用

卷扬机吊篮降到最低位置时,钢丝绳在卷筒上至少有3圈以上的钢丝绳。 5.7.4滑轮直径选用

滑轮直径≥20d (d 为钢丝绳的直径)。 20d=20×16=320mm 5.8卷扬机安装

选用额定牵引力1.5t 的中速(绳速平均为33m/min)在安装前做好砼地锚角桩(L75×62根)与卷扬机连接,卷扬机就位、安装后,在卷扬机前又打2根L75×61≥1.7m 的迎头桩。卷扬机离龙门架≥20倍卷筒长度。钢丝绳不允许拖地并设置有过路保护措施。卷扬机安装视野良好,并搭设防护棚。 5.9吊篮安全装置安装

5.9.1吊篮高度限位装置安装在卷扬机的卷筒轴上。 5.9.2. 吊篮停车安全装置 5.9.3. 吊篮钢丝绳断后的安全装置 5.10电气设备安装 5.10.1电器安装:

5.10.1.1. 电器安装必须按三相五线制,一机一箱一闸一漏要求进行安装。 5.10.1.2. 必须按要求配置有超高限位装置。

5.10.1.3. 电器安装完毕后。要认真检查合格后方能合闸,并调整好超高限位开关。

5.10.1.4. 所有电器设备必须有箱有锁,安装漏电保护和接零接地装置。接地电阻>10Ω,卷扬机操作按钮必须接通磁力开关。严禁使用两个闸门开关和倒顺开关代替磁力开关和操作按钮,必须要与限位装置接通。(参考下图)

5.10.2 防雷、接地安装

在龙门架顶部安装有1个端磨尖,Φ16 L=1m镀锌铁与井架顶部焊牢,钢筋作为接闪器,并在井架底打一根L50×5 L ≥2m 角钢桩,并与井架底部焊牢作为接地装置,防雷接地电阻≧30Ω。 6. 质量要求与验收

6.1新制作的龙门架架体安装的垂直偏差最大不得超过架体高度的1.5‰,多次使用过的偏差不得超过3‰,并且不得超过200mm 。本工程使用的龙门架在多个工程使用过,最近一次使用在柳州市公安局强制戒毒所易地重建食堂工程,因此,本架体的垂直度偏差≧3‰(84mm )。

6.2龙门架截面内,两对角线长度公差不得超过最大边长尺寸的3‰。 6.3导轨接点截面错位不大于1.5mm 。

6.4吊篮导轨与导轨的安装间隙应在5~10mm 以内。

6.5基础表面平整,水平误差≧10mm ,基础有排水设施,型钢底座用地脚螺

栓与基础连接。

6.6楼层卸料通道两侧应按临边防护规定设置防护栏杆及挡脚板。卸料平台应独立搭设,不得与脚手架连接。架体三面挂密目式(2000目)安全网。底层进料口设防护棚,防护棚两侧挂落地密目安全网,楼层标志醒目,层间有安全警示牌。

6.7附墙杆宜每层设置,且在建筑物顶层必须设置1组,架体顶部自由高度不得大于6m 。刚性件连接,不得连接在脚手架上。严禁使用铅丝绑扎。 6.8吊篮导轮与导轨安装间隙控制在5-10mm ,吊篮必须有进出料安全门,安全门要与停靠装置联动。运行时安全门封闭吊篮的进料口。严禁吊篮、吊笼使用单根钢丝绳提升。吊篮两侧应设置高度不小于1m 的安全挡板或挡网。 6.9卷扬机卷筒中心与导向轮的距离≥卷筒直径20倍。地锚角钢桩≦L75×6 L ≥2m ,滑轮直径与钢丝绳的比值≦25倍。吊篮处于最低位置,卷扬机卷筒内钢丝绳≦3圈。并不. 得接长使用,卷筒与钢丝绳直径之比不小于30。滑轮应选用滚动轴承支承。

6.10卷扬机卷筒两端的凸缘至最外层钢丝绳的距离不小于钢丝绳直径的2倍,卷筒边缘必须设防止钢丝绳脱出的防护装置。 6.11滑轮组滑轮直径和钢丝绳直径比值不小于25。

6.12滑轮组与架体(或吊篮)的连接要采用刚性连接,严禁用钢丝绳、铅丝等柔性连接和使用开口拉板式滑轮。 6.13钢丝绳要有合格证,且符合使用要求。

6.14钢丝绳端部的固定,绳卡与绳径要匹配,其数量不少于3个,间距不少于钢丝绳直径的6倍。绳卡滑鞍放在受力绳的一侧,不得正反设置绳卡。最后一个绳卡与绳头的距离不得小于150mm ,并设置安全弯。

6.15. 总电源短路、漏电保护装置,金属结构和电气线路要设有保护接头和重复接地装置。接地电阻不应大于10Ω。提升机架体的防雷装置的冲击电阻不得大于30Ω。禁止使用倒顺开关作为卷扬机的控制开关。

6.16安全停靠装置能可靠承受吊篮自重、额定荷载及运料和装卸物料的工作荷载。当吊篮悬挂或运行中发生断绳时,应能可靠地将吊篮停住并固定在架体上。滑落行程,在吊篮满载时,不得超过1m 。

6.17上极限限位装置应使吊篮的越程不小于3m 。当采用高速度提升机时,还应设置下极限限位器,缓冲器、超载限制器和通讯装置。

6.18低架提升机操作人员应能清晰观察吊篮运行。

6.19提升机要有可靠的安全停靠装置、断绳保护装置、楼层口停靠栏杆。防护栏杆由上下两道横杆及栏杆柱组成,上杆离平台高度为1~1.2m ,下杆离平台高度为0.5~0.6m 。

6.20吊篮要采用联锁装置开启的吊篮安全门。

6.21地面进出口防护棚,其宽度大于2m ,长度大于3m 。棚顶铺设50mm 厚木板或两层竹脚手板,上下两层脚手板间距不小于600mm 。

6.22提升机设置信号装置,能使各楼层使用提升机装卸物料的人员清晰听到。本工程采用哨笛信号,在作业人员的交底中必须明确信号类别。

6.23电缆绝缘电阻要大于0.5M Ω,接地电阻值不大于10Ω。

6.24提升机的照明开关要与提升机主电源开关相互独立。

6.25架体各节点的螺栓必须坚固,螺栓要符合孔径的要求,严禁扩孔和开孔,更不得漏装或以铅丝代替。

6.26提升钢丝绳要架起,使之不拖地面和被水浸泡,并作护绳沟槽,沟宽600mm ,高度350mm ,上面用48mm 厚木板盖实。护绳沟不能兼做排水沟。

6.27开关箱与卷扬机的距离不得超过3m ,保护零线要接好。开关箱要有门、有锁及防雨设施,开关箱宜设置在卷扬机防护棚内的后侧面。

7. 使用完毕,按规定程序和要求进行拆除工作。

7.1龙门架的拆卸方法,遵循“先装后拆,后装先拆”的原则进行拆卸。

7.2把钢丝绳全部排卷进卷扬机的卷筒上,并加润滑油保养。

7.3把电源切断,并拆除电器部分。

7.4拆卸吊篮。

7.5架体拆卸:升降机的拆卸顺序按照架设时的逆顺序进行,即后安装的先拆,先安装的后拆。拆卸时,标准节的落下依然靠吊篮来运输,每次两节。

7.6龙门架拆卸完后,要进行全面检修、保养,以便下次再用。

8. 安全保障和维护措施

8.1 设备应装设在可靠的基础和导轨上。基础应具有足够的承载力和稳定性,并设有良好的排水措施。

8.2 设备在使用以前必须进行全面的检查和维护保养,确保设备完好。未经检修保养的设备不能使用。

8.3 严格遵照设备的安装程序和规定进行设备的安装(搭设)和接高工作。

8.4 确保架设过程中的安全,注意事项为:

1)安装过程中,龙门架内要铺设跳板,供登高安装人员落脚,操作人员持证上岗,并系安全带,戴安全帽,穿防滑鞋。

2)按规定及时设置临时支撑、附墙拉结装置;

3)在统一指挥下作业;

4) 在安装区域内停止进行有碍确保架设安全的其他作业。

8.5 设备安装完毕后,应全面检查安装的质量是否符合要求,并及时解决存

在的问题。随后进行空载和负载试运行,判断是运行情况是否正常,吊索、吊具、吊篮、安全保险以及刹车装置等是否可靠。都无问题时才能报公司职能部门验收,验收合格后交付使用。

8.6 进出料口之间的的安全设施:垂直运输设施的出料口与建筑结构的进料口之间,根据其距离的大小设置铺板或栈桥通道,通道两侧设护栏。建筑物入料口设栏杆门。

8.7 设备应由专门的人员操纵和管理。严禁违章作业和超载使用。设备出现故障或运转不正常时应立即停止使用,并及时予以解决。

8.8 位于及外的卷扬机应设置安全作业棚。操作人员的视线不得受到遮挡。当作业层较高,观测和对话困难时,应采取可靠的解决办法,如增加卷扬定位装置、对讲设备或多级联络办法等。

目 录

1. 工程概况 . ....................................................................................................... 2 2. 龙门架概况 .................................................................................................... 2 3、施工准备 ..................................................................................................... 3 3.1材料准备 ............................................................................................... 3 3.2劳动准备 ............................................................................................... 3 3.3工具准备 ............................................................................................... 3 3.4作业条件 ............................................................................................... 3 4、工艺流程 ..................................................................................................... 4 5、施工部署和工艺操作 .................................................................................. 4 5.1基础施工 ............................................................................................... 4 5.2架体安装 ............................................................................................... 4 5.3安装附墙架 . ........................................................................................... 5 5.4吊篮安装 ............................................................................................... 6 5.5卷扬机的安装 ........................................................................................ 6 5.6安全防护装置 ........................................................................................ 6 5.7传动系统安装 ........................................................................................ 7 5.8卷扬机安装 . ........................................................................................... 8 5.9吊篮安全装置安装................................................................................. 8 5.10电气设备安装 ......................................................................................... 8

龙门架安装、拆除施工方案

1. 工程概况

1.1该工程为六安广电中心叶集分中心,总建筑面积7703㎡,框架六层,标准层层高3.6m ,主楼底层层高4.2 m,附楼高15m ,建筑高度23.4m 。结构类型为桩基承台基础、框架结构。龙门架操作及安装区域内无高压线。 1.2施工条件:龙门架布置在现场主楼北面,相关二级电箱布置到现场,详见临时用电布置图。

1.3本工程采用一台龙门架,是郑州宏茂机械厂生产的SSE160施工升降机, 起重量: ≤1.5t 。提升机有生产许可证,产品合格证。

2. 龙门架概况

本工程使用的龙门架吊篮尺寸为3.5m ×1.9m ,安装高度30m ,吊盘使用高度为1.9m ,起重量为1t ,螺栓M16,导轨63×40×4.8,节间尺寸1.9m 。主要技术参数见下表

3、施工准备 3.1材料准备

3.1.1 架体材料,吊篮——符合龙门架设计要求

3.1.2 卷扬机、钢丝绳——与龙门架吊篮提升机重量相匹配 3.1.3 电气设备——整套 3.2劳动准备

3.2.1 龙门架安装工人3人——经培训执证上岗

3.2.2 机械安装操作工2人、电工1人——经培训持证上岗 3.3工具准备

3.3.1 专工扳手,尼龙绳φ1.5mm 、60m 3.3.2 安全帽、安全带——操作者每人1套 3.4作业条件

3.4.1 材料、设备工具、劳动准备就绪

3.4.2 井架基础施工完毕,经验收合格,满足安装、使用要求。 4、工艺流程

基础施工→架体安装→滑轮安装→卷扬机安装→电器、限位设备安装→试车→验收

5、施工部署和工艺操作 5.1基础施工

在准备安装龙门架的位置对比井孔尺寸每边大400mm 进行放线挖土,地基打夯、地基承载力≦80kpa ,整个龙门架架基础捣C20砼厚500mm ,基础顶面平整度偏差≧10mm ,在捣制龙门架基础四角架拉处预埋螺栓M20×450。龙门架基础砼要求送实验室进行检测。 5.2架体安装

5.2.1 架体安装顺序:安装底座→标准节安装→顶部天粱安装→滑轮、吊篮安装→标准节提升、加高

5.2.2 待架体基础砼强度达到70%以上以后,才能安装架体。若基础顶不平时,必须用铁板垫平架底,并且要牢固可靠。反复核对架座的水平度,然后锚牢架底座,并核对底座的对角线。

5.2.3底座安装时四角对准基础预埋螺栓,并拧牢,要求底座安装平整,方正、牢固, 水平误差1℅。

5.2.4安装前,清点检查升降机龙门架各标准节,翘曲不平的要校正,各安全装置是否齐全有效。安装时,先把底座放在基础上,上紧锚螺栓。将升降台放在安装好的底架上。安装基础节,左右各一节。安装扒杆,并穿绕钢丝绳。在两个基础节的顶部各安装一个支架。并挂上手拉葫芦。拉动手拉葫芦,

将升降机台提升到基础节上部,并使用卡板将升降台固定在两基础节间。松动手拉葫芦,取下两个支架。转动扒杆,摇动手摇减速机,分两次起吊两个标准节分别加在两个基础节上,并用螺栓紧固,用螺母拧紧。在两个标准节上部安装支架,挂上手拉葫芦,拉动手拉葫芦将升降台升到标准节最上部并固定。取下支架。将吊篮放置两柱架之间的底架上。

5.2.5 操作人员必须戴好安全帽,绑好安全带,并且必须穿软底胶鞋进行施工。在搭好第二节架体后,可用滑轮提送工具、零件等。

5.2.6调整架体垂直和架体的稳定性,滑轨安装在水平杆上,垂直度偏差≧导轨架架设高度的1‰,架体垂直度偏差≧导轨架架设高度的3‰,并≧200mm 。井架位置正确,每节接头偏差≧5mm 。导轨接点截面相互错位≧1.5mm, 吊篮导轨与导轨的安装间隙在5-10 mm以内。

5.2.7在架体安装时,每安装4个标准节(≧8m )应采取临时支撑固定,进行初校正,在确定稳定时,方可继续作业。本工程根据实际情况每层设置一组附墙。

5.3安装附墙架

当架体随着建筑物升高而加高的同时,需要对架体进行附着,架体用管及扣件与建筑物连接,每层进行附着设置。 注意:

(l )架体的附墙架与龙门架架体的加高必须同时进行。加管与标准节和建筑物的连接可靠。

(2)附着架必须与建筑墙体内预埋件连接,不得与脚手架钢管连接。

5.4吊篮安装 5.4.1吊篮组

吊篮由底盘、竖杆、斜杆、横梁、角撑、侧围、进料门、出料门、顶棚组成。底盘由大梁搁栅和铺板构成。 5.4.2 吊篮安全装置 a 、吊篮停车安全装置 b 、吊篮钢丝绳断后的安全装置 5.5卷扬机的安装

5.5.1. 卷扬机安装,其基础尺寸为1500 ×1500×600mm ,用C20素砼浇筑,基础顶面必须水平。在浇砼前,先打好迎头桩和牵拉桩,采用Φ48mm 钢管长为2000,埋深不得少于1700mm ,卷扬机必须设有地锚,并且采用不少于两根钢丝 绳与卷扬机联接。 5.5.2. 稳定性验算

基础自重:1.5×1.5×0.6×2.5=3.38t 牵引力:1.5t

卷扬机支座前点力矩:3.38×0.75>1.5×0.6 验算结果:基础牢固、稳定。 5.6安全防护装置

5.6.1龙门架进料口必须设安全门,并要求有联动装置。

5.6.2吊篮顶部要安装防护网,吊篮进出口处设安全门,两侧设栏杆,用钢丝网封闭。

5.6.3卷扬机必须搭防护棚,并且不影响卷扬机操作员的视线。

5.6.4龙门架进料口必须按要求搭设好安全防护棚,按本工程搭设高度26m ,搭设防护棚长度应为4m 。

5.6.5龙门架架体采用2000目的密目网封闭好,操作视线面用大孔网如平网封闭。

5.6.6卸料平台要求单独搭设,不能搁置在外脚手架或龙门架架体上,并要设置拦腰杆及踢脚板、挂网封闭。 5.7传动系统安装

5.7.1龙门架架顶部和底侧部安装传动滑轮,滑轮直径选用≥20d (d 为钢丝绳的直径)。

5.7.2 起重钢丝绳的选用 5.7.3荷载取值

吊篮重0.39T 起重量)1.5T

安全系数n=5 破断拉力为SP=5×(0.39+1.5)=9.45T SP=1/2d² d=2SP(英分、1英分=3.175mm)

d=2SP=(2×9.45)1/2=4.35=5英分=5×3.175=15.88mm 取d=16mm

5.7.3 钢丝绳长度选用

卷扬机吊篮降到最低位置时,钢丝绳在卷筒上至少有3圈以上的钢丝绳。 5.7.4滑轮直径选用

滑轮直径≥20d (d 为钢丝绳的直径)。 20d=20×16=320mm 5.8卷扬机安装

选用额定牵引力1.5t 的中速(绳速平均为33m/min)在安装前做好砼地锚角桩(L75×62根)与卷扬机连接,卷扬机就位、安装后,在卷扬机前又打2根L75×61≥1.7m 的迎头桩。卷扬机离龙门架≥20倍卷筒长度。钢丝绳不允许拖地并设置有过路保护措施。卷扬机安装视野良好,并搭设防护棚。 5.9吊篮安全装置安装

5.9.1吊篮高度限位装置安装在卷扬机的卷筒轴上。 5.9.2. 吊篮停车安全装置 5.9.3. 吊篮钢丝绳断后的安全装置 5.10电气设备安装 5.10.1电器安装:

5.10.1.1. 电器安装必须按三相五线制,一机一箱一闸一漏要求进行安装。 5.10.1.2. 必须按要求配置有超高限位装置。

5.10.1.3. 电器安装完毕后。要认真检查合格后方能合闸,并调整好超高限位开关。

5.10.1.4. 所有电器设备必须有箱有锁,安装漏电保护和接零接地装置。接地电阻>10Ω,卷扬机操作按钮必须接通磁力开关。严禁使用两个闸门开关和倒顺开关代替磁力开关和操作按钮,必须要与限位装置接通。(参考下图)

5.10.2 防雷、接地安装

在龙门架顶部安装有1个端磨尖,Φ16 L=1m镀锌铁与井架顶部焊牢,钢筋作为接闪器,并在井架底打一根L50×5 L ≥2m 角钢桩,并与井架底部焊牢作为接地装置,防雷接地电阻≧30Ω。 6. 质量要求与验收

6.1新制作的龙门架架体安装的垂直偏差最大不得超过架体高度的1.5‰,多次使用过的偏差不得超过3‰,并且不得超过200mm 。本工程使用的龙门架在多个工程使用过,最近一次使用在柳州市公安局强制戒毒所易地重建食堂工程,因此,本架体的垂直度偏差≧3‰(84mm )。

6.2龙门架截面内,两对角线长度公差不得超过最大边长尺寸的3‰。 6.3导轨接点截面错位不大于1.5mm 。

6.4吊篮导轨与导轨的安装间隙应在5~10mm 以内。

6.5基础表面平整,水平误差≧10mm ,基础有排水设施,型钢底座用地脚螺

栓与基础连接。

6.6楼层卸料通道两侧应按临边防护规定设置防护栏杆及挡脚板。卸料平台应独立搭设,不得与脚手架连接。架体三面挂密目式(2000目)安全网。底层进料口设防护棚,防护棚两侧挂落地密目安全网,楼层标志醒目,层间有安全警示牌。

6.7附墙杆宜每层设置,且在建筑物顶层必须设置1组,架体顶部自由高度不得大于6m 。刚性件连接,不得连接在脚手架上。严禁使用铅丝绑扎。 6.8吊篮导轮与导轨安装间隙控制在5-10mm ,吊篮必须有进出料安全门,安全门要与停靠装置联动。运行时安全门封闭吊篮的进料口。严禁吊篮、吊笼使用单根钢丝绳提升。吊篮两侧应设置高度不小于1m 的安全挡板或挡网。 6.9卷扬机卷筒中心与导向轮的距离≥卷筒直径20倍。地锚角钢桩≦L75×6 L ≥2m ,滑轮直径与钢丝绳的比值≦25倍。吊篮处于最低位置,卷扬机卷筒内钢丝绳≦3圈。并不. 得接长使用,卷筒与钢丝绳直径之比不小于30。滑轮应选用滚动轴承支承。

6.10卷扬机卷筒两端的凸缘至最外层钢丝绳的距离不小于钢丝绳直径的2倍,卷筒边缘必须设防止钢丝绳脱出的防护装置。 6.11滑轮组滑轮直径和钢丝绳直径比值不小于25。

6.12滑轮组与架体(或吊篮)的连接要采用刚性连接,严禁用钢丝绳、铅丝等柔性连接和使用开口拉板式滑轮。 6.13钢丝绳要有合格证,且符合使用要求。

6.14钢丝绳端部的固定,绳卡与绳径要匹配,其数量不少于3个,间距不少于钢丝绳直径的6倍。绳卡滑鞍放在受力绳的一侧,不得正反设置绳卡。最后一个绳卡与绳头的距离不得小于150mm ,并设置安全弯。

6.15. 总电源短路、漏电保护装置,金属结构和电气线路要设有保护接头和重复接地装置。接地电阻不应大于10Ω。提升机架体的防雷装置的冲击电阻不得大于30Ω。禁止使用倒顺开关作为卷扬机的控制开关。

6.16安全停靠装置能可靠承受吊篮自重、额定荷载及运料和装卸物料的工作荷载。当吊篮悬挂或运行中发生断绳时,应能可靠地将吊篮停住并固定在架体上。滑落行程,在吊篮满载时,不得超过1m 。

6.17上极限限位装置应使吊篮的越程不小于3m 。当采用高速度提升机时,还应设置下极限限位器,缓冲器、超载限制器和通讯装置。

6.18低架提升机操作人员应能清晰观察吊篮运行。

6.19提升机要有可靠的安全停靠装置、断绳保护装置、楼层口停靠栏杆。防护栏杆由上下两道横杆及栏杆柱组成,上杆离平台高度为1~1.2m ,下杆离平台高度为0.5~0.6m 。

6.20吊篮要采用联锁装置开启的吊篮安全门。

6.21地面进出口防护棚,其宽度大于2m ,长度大于3m 。棚顶铺设50mm 厚木板或两层竹脚手板,上下两层脚手板间距不小于600mm 。

6.22提升机设置信号装置,能使各楼层使用提升机装卸物料的人员清晰听到。本工程采用哨笛信号,在作业人员的交底中必须明确信号类别。

6.23电缆绝缘电阻要大于0.5M Ω,接地电阻值不大于10Ω。

6.24提升机的照明开关要与提升机主电源开关相互独立。

6.25架体各节点的螺栓必须坚固,螺栓要符合孔径的要求,严禁扩孔和开孔,更不得漏装或以铅丝代替。

6.26提升钢丝绳要架起,使之不拖地面和被水浸泡,并作护绳沟槽,沟宽600mm ,高度350mm ,上面用48mm 厚木板盖实。护绳沟不能兼做排水沟。

6.27开关箱与卷扬机的距离不得超过3m ,保护零线要接好。开关箱要有门、有锁及防雨设施,开关箱宜设置在卷扬机防护棚内的后侧面。

7. 使用完毕,按规定程序和要求进行拆除工作。

7.1龙门架的拆卸方法,遵循“先装后拆,后装先拆”的原则进行拆卸。

7.2把钢丝绳全部排卷进卷扬机的卷筒上,并加润滑油保养。

7.3把电源切断,并拆除电器部分。

7.4拆卸吊篮。

7.5架体拆卸:升降机的拆卸顺序按照架设时的逆顺序进行,即后安装的先拆,先安装的后拆。拆卸时,标准节的落下依然靠吊篮来运输,每次两节。

7.6龙门架拆卸完后,要进行全面检修、保养,以便下次再用。

8. 安全保障和维护措施

8.1 设备应装设在可靠的基础和导轨上。基础应具有足够的承载力和稳定性,并设有良好的排水措施。

8.2 设备在使用以前必须进行全面的检查和维护保养,确保设备完好。未经检修保养的设备不能使用。

8.3 严格遵照设备的安装程序和规定进行设备的安装(搭设)和接高工作。

8.4 确保架设过程中的安全,注意事项为:

1)安装过程中,龙门架内要铺设跳板,供登高安装人员落脚,操作人员持证上岗,并系安全带,戴安全帽,穿防滑鞋。

2)按规定及时设置临时支撑、附墙拉结装置;

3)在统一指挥下作业;

4) 在安装区域内停止进行有碍确保架设安全的其他作业。

8.5 设备安装完毕后,应全面检查安装的质量是否符合要求,并及时解决存

在的问题。随后进行空载和负载试运行,判断是运行情况是否正常,吊索、吊具、吊篮、安全保险以及刹车装置等是否可靠。都无问题时才能报公司职能部门验收,验收合格后交付使用。

8.6 进出料口之间的的安全设施:垂直运输设施的出料口与建筑结构的进料口之间,根据其距离的大小设置铺板或栈桥通道,通道两侧设护栏。建筑物入料口设栏杆门。

8.7 设备应由专门的人员操纵和管理。严禁违章作业和超载使用。设备出现故障或运转不正常时应立即停止使用,并及时予以解决。

8.8 位于及外的卷扬机应设置安全作业棚。操作人员的视线不得受到遮挡。当作业层较高,观测和对话困难时,应采取可靠的解决办法,如增加卷扬定位装置、对讲设备或多级联络办法等。


相关内容

  • 龙门架物料提升机按拆方案
  • 安徽农业大学科技大楼工程 自升式龙门架 安装与拆除方案 安徽建工集团有限公司 安徽农业大学科技大楼项目部 2010年12月10日 会 签 栏 编制: 审核: 审批: 日期: LMZ1A型自升式龙门架安装与拆除方案 一.工程概况 本工程总建筑面积30426.3㎡,框架结构,主体六层,平屋面结构,建筑檐 ...

  • 龙门吊安装拆除安全施工专项方案
  • 龙门吊安装及拆除安全专项方案 编制人:沈剑 一.编制依据 1.1.编制目的 为保证广宁高速公路路基工程03合同段预制梁场制梁和龙门吊安装.使用及拆除施工安全,切实履行企业安全生产的主体责任,根据<建设工程安全生产管理条例>和<危险性较大工程安全专项施工方案编制及专家论证审查办法&g ...

  • 龙门吊方案
  • 物料提升机安装(拆卸)方案 工程名称: 使用单位: 方案编制: 方案审批: 单位: 龙门架提升机安装技术及安装 安全操作指导书 工程名称: 使用单位: 龙门架提升机安装工作内容及安装程序 物料提升机基础检验表 检验时间: 年 月 日 龙门架安拆施工方案 工程名称: 施工单位: 建设单位: 监理单位: ...

  • 龙门架施工方案
  • 龙门架安拆施工方案 一.工程概况 本工程为XXX 工程,为群体工程.位于XXX .其结构为框架剪力墙,建筑面积为24119m 2,建筑高度为32.15m .为了使本工程施工能顺利地进行,确保如期按质地完成,根据具体情况特选用4台高架龙门架提升机.龙门架在整个施工过程中不准载人上下. 二.安装前准备工 ...

  • 龙门架 吊装方案1
  • 组合龙门架安装方案 一.工程概况; 移动安装龙门架, 由钢制立柱及横梁等附件组成承载框架, 通过框架底座平台安装有实验室水池底部预埋的螺栓定位固定.龙门架主梁上可布置冲击载荷试验装置.龙门架便于拆解移动, 试验时可移动至其他试验场地.其外形尺寸为18.04米*6.2米*12.68米(长*宽*高). ...

  • 沙筒式临时支座专项施工方案_secret
  • 临时支座专项施工方案 第一章.工程概况 本合同段设计有大桥1786.46m/6座,分离式立交桥579.31m/5座, 梁板共1108片.梁板安装时除伸缩缝处安装永久支座外其余墩顶均需设置临时支座,待每一联完成简支到连续的体系转换后,方可将临时支座拆除完成一联桥梁的安装工程. 支座的设计,既要保证梁体 ...

  • 某地铁车站土石方工程施工方案
  • 地铁车站土石方工程施工方案 一.土石方工程施工简述 1 车站主体工程土石施工: 车站主体土石采取分两段由中间向两边开挖,每一段配三台0.5m 3的小型挖土机进行开挖, 在钢支撑设置后,小型挖土机横向开挖,纵向推进,A 至B 轴间盖挖部分的土方由挖土机横向转运至明挖部分(B 至C 轴).在地面每段架设 ...

  • 龙门吊安装拆卸事故应急救援预案
  • 龙门吊安装拆卸事故应急救援预案 一.概述 本工程主桥为跨越蓟运河故道的大型桥梁,该桥是连接生态城03片区与04片区两个子片区的重要纽带:同时,经六路又与中新大道.中生大道.中央大道等主干道相接,可沟通塘沽.开发区.汉沽等区域,是03片区与生态城外部交通衔接的重要通道. 主桥采用35m+4×50m+3 ...

  • 龙门架简介
  • 龙门架简介 目录 1.龙门架操作(拼装)完成后,应进行负荷试吊:试吊分静载和动载,检查各个系统运行能力.承载能力.稳定可靠程度等. 2.龙门架运行时,要做到平行稳定,不使其产生扭曲. 3.严禁超负荷使用. 4.作业时应有专人统一指挥,其他人员要有明确分工:确定好统一的联络信号. 5.作业中遇有停电或 ...