目 录
一、编制依据............................................................................................. 2 二、工程概况............................................................................................. 2 三、塔吊选择............................................................................................. 2 四、塔吊定位............................................................................................. 3 五、塔吊基础施工 .................................................................................... 6 5.1基本准备 ....................................................................................... 6 5.2地基和基础施工 ........................................................................... 7 六、塔机安装程序 .................................................................................. 11 七、塔吊附着设置: .............................................................................. 13 八、塔吊拆除........................................................................................... 14 九、塔吊安拆及使用安全技术措施 ...................................................... 14
一、编制依据
1.1《建筑施工安全检查标准》JGJ59—99 1.2《塔式起重机操作使用规程》ZBJ 80012—89 1.3《安徽省建筑工程施工安全操作规程》
1.4阜阳市颍东区颍新安置区一期工程设计图纸及地质勘察报告 1.5QTZ63/50/40塔吊的说明书
1.6中华人民共和国工程建设标准强制性条文(施工安全部分) 二、工程概况
阜阳市颍东区颍新安置区一期工程位于安徽省阜阳市颍东区,众兴路以东、梨树路以南、富民路以北、富颍路以西。
本工程为住宅小区,并设计配套用房及地下车库,总建筑面积约19.6万平米,其中包括1#2#配套用房、3#4#地下车库,7#-17#高层住宅,部分商业裙楼,建筑层数为15、18、22、28层。基础形式为筏板基础,主体砼结构为剪力墙、框剪、框架、板柱结构。
该工程建设单位为阜阳市颍东区住房发展中心,设计单位为中外建工程设计与顾问有限公司,监理单位为武汉宏宇建设工程咨询公司,总承包单位为中国建筑一局(集团)有限公司 。 三、塔吊选择
选择与配置垂直运输体系时, 需考虑的主要项目有:建筑物的结构形式、模板配制、钢筋总量、混凝土的浇筑量、施工工期、垂直运输的效率和速度。
塔吊的主要参数应满足施工需要,主要参数包括工作幅度、起升
高度、起重量和起重力矩。
为保证每栋建筑在施工中的连续性,满足流水的均衡,以及考虑到现场平面布置,各塔机起重性能如下表
四、塔吊定位
结合现场实际,避免出现塔吊盲区,保证塔吊能够正常安装和拆除,塔吊的现场定位见施工现场塔吊布置示意图,塔吊定位尺寸偏差控制在50mm 之内。
五、塔吊基础施工 5.1基本准备
5.1.1塔机专用电箱:每台塔机必须配备专用电箱,塔机专用电箱必须合理定位,电箱距塔吊定位处最好控制在5米内。
5.1.2电源准备:QTZ63塔机正常工作所需的电容量为43.4 KW ,QTZ50塔机正常工作所需的电容量为26.7KW ,QTZ40和QTZ40A 塔机正常工作所需的电容量为25.7KW 。
5.1.3材料物质准备:根据塔吊基础布筋图,准备相应规格的钢筋、混凝土。
5.1.4场地空间准备:便于塔机部件的摆放和汽车吊的入场选位。 5.1.5现场人员配合:指派专人与塔吊专业公司联系,随时处理塔吊正常安拆需要协作的工作。
5.2地基和基础施工 5.2.1地基
各塔机基础承载力均为200KPa ,本工程塔吊基础底标高在-4.800~-7.300之间,根据地质勘察报告,该部位土层为黏土层和黏土夹粉土层,该部位土层建议承载力取值为220、230KPa ,均满足设计要求。通过对塔机基础部位持力层及其持力层周围进行严格的钎探,查明是否有不实结构(防空洞、地下输送管道等),如果存在则必须对地基进行处理,直到达到要求为止。 5.2.2基础施工 5.2.1基础布筋
各塔机均为有固定式基础,按照基础要求铺设钢筋,基础配筋详见附图。 5.2.2基础施工
5.2.2.1塔吊基础土方开挖按照1:0.7坡度放坡进行开挖,并按照原来基坑支护设计图纸对塔基开挖面进行支护,支护采用60厚C20喷射砼内夹钢丝网片做土钉墙,基础配筋经验收后浇筑C35混凝土,当基础块混凝土强度达到75%以上时,方可安装进行塔机安装。基础块水平误差控制在5mm 以内。
5.2.2.2基础应单独做两组接地线,接地电阻不应大于4欧姆,做法如下:用三根ф32长1.5米钢管制作成1.2米等边三角形垂直打到地下,用50X5的镀锌扁钢将三根钢管焊接在一起,然后将扁钢扁钢焊接在塔吊底架上。
5.2.2.3本工程中7#9#15#楼塔吊基础采用“十字”形基础,基础高度为1300mm ,砼强度均为C35;8#11#12#13#14#16#17#楼塔吊基础采用5Mx5mX1.35m 基础,砼强度均采用C35。各个楼塔吊基础顶标高详见下表:
基础配筋及大样图如下:
7#9#15#楼塔吊基础图
8#11#12#13#14#16#17#楼塔吊基础图
8#11#12#13#14#16#17#楼塔吊基础配筋图
A
塔吊基础平面图
注:8#11#12#13#14#16#17#楼塔吊基础
楼塔吊基础
B
塔吊基础厚C15垫层
六、塔机安装程序 6.1安装程序 塔吊安装程序如下:
6.2安装准备
6.2.1起重设备: 25吨汽车吊,性能完好,汽吊司机有操作证。 6.2.2 安装设备:扳手、吊索、大绳、卡环、导向冲子、手锤等。 6.2.3技术准备:安装前精确计算拼臂及安装塔身、塔尖、配重、大臂支车位置,塔件码放要便于安装。 6.2.4安拆器具配置:
6.3安装步骤
6.3.1安装底架:先吊两横梁南北放置,落在基础块上,再吊纵梁东西放置并螺栓连接,再吊四个水平支撑用销子连接。
6.3.2安装基础节:将基础做在纵梁上把螺栓把紧,安装四斜撑。 6.3.3安装过渡节:将过渡节与基础节销轴连接。
6.3.4安装套架总成:安装套架总成,并安好扁担梁、平台及油缸。 6.3.5安装回转支撑:在转支撑上安装平台扶手栏杆和引进梁,然后吊起放在过渡节上,然后提起套架与回转下支座销轴连接。 6.3.6安装塔尖(带有平台扶手拉杆和司机室):将塔尖吊放到上支座上用螺栓和销子进行连接。
6.3.7安装平衡臂:在平衡臂专设的吊点上拴好吊索,安装大臂时要用牵引绳进行地面引导,用小周与塔尖连接,双连杆与塔尖连接。 6.3.8安装起重臂:将牵引小车装在臂架根部,根据所需的长度装配臂节,用两根8米长ф21.3吊索吊起臂架,用一根牵引绳地面引导,将臂根与塔尖连接,之后用张紧装置将拉杆与塔尖销轴连接。 6.3.9安装平衡重:先吊一大块放在根部,其余向尾部排列,安装后用拉杆穿过每块平衡重的孔进行锁固。
6.3.10穿绳及其他:将大钩放在顶升平台处,按说明书穿绕钢丝绳,检查调试各种安全保护装置,保证齐全灵敏有效。 七、塔吊附着设置:
八、塔吊拆除
塔吊先自降塔身标准节,自降到合适高度后,然后用25吨汽车吊拆除配重、起重臂、平衡臂、塔帽、回转装置、顶升套架、过渡节等。
九、塔吊安拆及使用安全技术措施
9.1所有参加作业人员都必须遵守现场施工的各项安全规范及本工种安全操作规程。施工现场所有工作人员必须戴好安全帽,高空作业必须系好安全带,带工具要求做到:搬子、锤子、螺丝刀放在工具箱内。严禁往下仍东西,安装过程中塔机下面禁止有人穿行。
9.2所有现场操作人员必须熟悉同类型塔机的安装和拆除程序和规范。
9.3塔吊司机、塔吊拆装人员以及塔吊指挥都必须持有建设主管部门签发的特殊工种操作证。
9.4塔吊司机每班作业前都必须对设备进行例行检查,塔吊的各项安全限位必须齐全可靠。
9.5塔身标准节之间的连接销及其他任何部件之间的联接销都必须穿开口销。
9.6塔身垂直度偏差不大于4‰。
9.7高空作业严禁抛掷物体,以免物体坠落伤人。
9.8 六级风以上严禁塔吊安装作业,4级风以上严禁塔吊顶升作业。
9.9作业现场必须设置不小于20×20米的安全作业区。
9.10塔司操作要严格按照本塔使用说明书中的规定和本工种安全操作规程执行,严禁超载吊运及斜拉斜吊,并在吊装作业中严格执行“十不吊”。
9.11安全部要定期组织对塔吊进行垂直沉降观测,垂直偏差大于0.2%后必须停止使用。
9.12设立专人指挥,做到指挥准确,动作协调。
9.13 建立故障处理制度。若遇故障,应立即停止作业,并作好相应应急加固措施,待故障排除后,方能继续拆除。 9.14所有参加拆除的人员,要有明确的分工。 9.15 在塔吊附近,禁止其他人员逗留。
目 录
一、编制依据............................................................................................. 2 二、工程概况............................................................................................. 2 三、塔吊选择............................................................................................. 2 四、塔吊定位............................................................................................. 3 五、塔吊基础施工 .................................................................................... 6 5.1基本准备 ....................................................................................... 6 5.2地基和基础施工 ........................................................................... 7 六、塔机安装程序 .................................................................................. 11 七、塔吊附着设置: .............................................................................. 13 八、塔吊拆除........................................................................................... 14 九、塔吊安拆及使用安全技术措施 ...................................................... 14
一、编制依据
1.1《建筑施工安全检查标准》JGJ59—99 1.2《塔式起重机操作使用规程》ZBJ 80012—89 1.3《安徽省建筑工程施工安全操作规程》
1.4阜阳市颍东区颍新安置区一期工程设计图纸及地质勘察报告 1.5QTZ63/50/40塔吊的说明书
1.6中华人民共和国工程建设标准强制性条文(施工安全部分) 二、工程概况
阜阳市颍东区颍新安置区一期工程位于安徽省阜阳市颍东区,众兴路以东、梨树路以南、富民路以北、富颍路以西。
本工程为住宅小区,并设计配套用房及地下车库,总建筑面积约19.6万平米,其中包括1#2#配套用房、3#4#地下车库,7#-17#高层住宅,部分商业裙楼,建筑层数为15、18、22、28层。基础形式为筏板基础,主体砼结构为剪力墙、框剪、框架、板柱结构。
该工程建设单位为阜阳市颍东区住房发展中心,设计单位为中外建工程设计与顾问有限公司,监理单位为武汉宏宇建设工程咨询公司,总承包单位为中国建筑一局(集团)有限公司 。 三、塔吊选择
选择与配置垂直运输体系时, 需考虑的主要项目有:建筑物的结构形式、模板配制、钢筋总量、混凝土的浇筑量、施工工期、垂直运输的效率和速度。
塔吊的主要参数应满足施工需要,主要参数包括工作幅度、起升
高度、起重量和起重力矩。
为保证每栋建筑在施工中的连续性,满足流水的均衡,以及考虑到现场平面布置,各塔机起重性能如下表
四、塔吊定位
结合现场实际,避免出现塔吊盲区,保证塔吊能够正常安装和拆除,塔吊的现场定位见施工现场塔吊布置示意图,塔吊定位尺寸偏差控制在50mm 之内。
五、塔吊基础施工 5.1基本准备
5.1.1塔机专用电箱:每台塔机必须配备专用电箱,塔机专用电箱必须合理定位,电箱距塔吊定位处最好控制在5米内。
5.1.2电源准备:QTZ63塔机正常工作所需的电容量为43.4 KW ,QTZ50塔机正常工作所需的电容量为26.7KW ,QTZ40和QTZ40A 塔机正常工作所需的电容量为25.7KW 。
5.1.3材料物质准备:根据塔吊基础布筋图,准备相应规格的钢筋、混凝土。
5.1.4场地空间准备:便于塔机部件的摆放和汽车吊的入场选位。 5.1.5现场人员配合:指派专人与塔吊专业公司联系,随时处理塔吊正常安拆需要协作的工作。
5.2地基和基础施工 5.2.1地基
各塔机基础承载力均为200KPa ,本工程塔吊基础底标高在-4.800~-7.300之间,根据地质勘察报告,该部位土层为黏土层和黏土夹粉土层,该部位土层建议承载力取值为220、230KPa ,均满足设计要求。通过对塔机基础部位持力层及其持力层周围进行严格的钎探,查明是否有不实结构(防空洞、地下输送管道等),如果存在则必须对地基进行处理,直到达到要求为止。 5.2.2基础施工 5.2.1基础布筋
各塔机均为有固定式基础,按照基础要求铺设钢筋,基础配筋详见附图。 5.2.2基础施工
5.2.2.1塔吊基础土方开挖按照1:0.7坡度放坡进行开挖,并按照原来基坑支护设计图纸对塔基开挖面进行支护,支护采用60厚C20喷射砼内夹钢丝网片做土钉墙,基础配筋经验收后浇筑C35混凝土,当基础块混凝土强度达到75%以上时,方可安装进行塔机安装。基础块水平误差控制在5mm 以内。
5.2.2.2基础应单独做两组接地线,接地电阻不应大于4欧姆,做法如下:用三根ф32长1.5米钢管制作成1.2米等边三角形垂直打到地下,用50X5的镀锌扁钢将三根钢管焊接在一起,然后将扁钢扁钢焊接在塔吊底架上。
5.2.2.3本工程中7#9#15#楼塔吊基础采用“十字”形基础,基础高度为1300mm ,砼强度均为C35;8#11#12#13#14#16#17#楼塔吊基础采用5Mx5mX1.35m 基础,砼强度均采用C35。各个楼塔吊基础顶标高详见下表:
基础配筋及大样图如下:
7#9#15#楼塔吊基础图
8#11#12#13#14#16#17#楼塔吊基础图
8#11#12#13#14#16#17#楼塔吊基础配筋图
A
塔吊基础平面图
注:8#11#12#13#14#16#17#楼塔吊基础
楼塔吊基础
B
塔吊基础厚C15垫层
六、塔机安装程序 6.1安装程序 塔吊安装程序如下:
6.2安装准备
6.2.1起重设备: 25吨汽车吊,性能完好,汽吊司机有操作证。 6.2.2 安装设备:扳手、吊索、大绳、卡环、导向冲子、手锤等。 6.2.3技术准备:安装前精确计算拼臂及安装塔身、塔尖、配重、大臂支车位置,塔件码放要便于安装。 6.2.4安拆器具配置:
6.3安装步骤
6.3.1安装底架:先吊两横梁南北放置,落在基础块上,再吊纵梁东西放置并螺栓连接,再吊四个水平支撑用销子连接。
6.3.2安装基础节:将基础做在纵梁上把螺栓把紧,安装四斜撑。 6.3.3安装过渡节:将过渡节与基础节销轴连接。
6.3.4安装套架总成:安装套架总成,并安好扁担梁、平台及油缸。 6.3.5安装回转支撑:在转支撑上安装平台扶手栏杆和引进梁,然后吊起放在过渡节上,然后提起套架与回转下支座销轴连接。 6.3.6安装塔尖(带有平台扶手拉杆和司机室):将塔尖吊放到上支座上用螺栓和销子进行连接。
6.3.7安装平衡臂:在平衡臂专设的吊点上拴好吊索,安装大臂时要用牵引绳进行地面引导,用小周与塔尖连接,双连杆与塔尖连接。 6.3.8安装起重臂:将牵引小车装在臂架根部,根据所需的长度装配臂节,用两根8米长ф21.3吊索吊起臂架,用一根牵引绳地面引导,将臂根与塔尖连接,之后用张紧装置将拉杆与塔尖销轴连接。 6.3.9安装平衡重:先吊一大块放在根部,其余向尾部排列,安装后用拉杆穿过每块平衡重的孔进行锁固。
6.3.10穿绳及其他:将大钩放在顶升平台处,按说明书穿绕钢丝绳,检查调试各种安全保护装置,保证齐全灵敏有效。 七、塔吊附着设置:
八、塔吊拆除
塔吊先自降塔身标准节,自降到合适高度后,然后用25吨汽车吊拆除配重、起重臂、平衡臂、塔帽、回转装置、顶升套架、过渡节等。
九、塔吊安拆及使用安全技术措施
9.1所有参加作业人员都必须遵守现场施工的各项安全规范及本工种安全操作规程。施工现场所有工作人员必须戴好安全帽,高空作业必须系好安全带,带工具要求做到:搬子、锤子、螺丝刀放在工具箱内。严禁往下仍东西,安装过程中塔机下面禁止有人穿行。
9.2所有现场操作人员必须熟悉同类型塔机的安装和拆除程序和规范。
9.3塔吊司机、塔吊拆装人员以及塔吊指挥都必须持有建设主管部门签发的特殊工种操作证。
9.4塔吊司机每班作业前都必须对设备进行例行检查,塔吊的各项安全限位必须齐全可靠。
9.5塔身标准节之间的连接销及其他任何部件之间的联接销都必须穿开口销。
9.6塔身垂直度偏差不大于4‰。
9.7高空作业严禁抛掷物体,以免物体坠落伤人。
9.8 六级风以上严禁塔吊安装作业,4级风以上严禁塔吊顶升作业。
9.9作业现场必须设置不小于20×20米的安全作业区。
9.10塔司操作要严格按照本塔使用说明书中的规定和本工种安全操作规程执行,严禁超载吊运及斜拉斜吊,并在吊装作业中严格执行“十不吊”。
9.11安全部要定期组织对塔吊进行垂直沉降观测,垂直偏差大于0.2%后必须停止使用。
9.12设立专人指挥,做到指挥准确,动作协调。
9.13 建立故障处理制度。若遇故障,应立即停止作业,并作好相应应急加固措施,待故障排除后,方能继续拆除。 9.14所有参加拆除的人员,要有明确的分工。 9.15 在塔吊附近,禁止其他人员逗留。