工程测量工作程序

程序会签

修改审批

文件变更记录表

目 录

1.目的 .......................................................................................................................................... 5 2.适用范围 .................................................................................................................................. 5 3.引用文件 .................................................................................................................................. 5 4.定义及缩略语 .......................................................................................................................... 5 5.职责 .......................................................................................................................................... 5 5.1工程技术部 .............................................................................................................................. 5 5.2测量班组 .................................................................................................................................. 6 5.3 测量负责人 ............................................................................................................................. 6 5.4其他各部门和施工班组 .......................................................................................................... 7 6.测量施工 .................................................................................................................................. 7 6.1施工准备 .................................................................................................................................. 7 6.2控制测量 .................................................................................................................................. 8 6.3 施工放样 ................................................................................................................................. 9 6.4质量保证措施 ........................................................................................................................ 11 6.5资料管理 ................................................................................................................................ 11 6.7安全保证措施 ........................................................................................................................ 12 7 .测量工作流程图 ...................................................................................................................... 12 8 .附件 .......................................................................................................................................... 13

1.目的

本程序旨在明确规范连云港田湾核电厂5、6号机组BOP标段00等子项建安工程工程现场测量工作的管理,在施工现场通过测量技术规范指导施工,同时对施工质量进行控制,以确保工程符合技术、质量安全和进度要求。

2.适用范围

适用于田湾5、6号机组BOP标段00等子项建安工程工程。 3.引用文件

中国核电工程有限公司提供的施工图纸、技术规格书、有关技术文件等 《核电厂工程测量技术规范》(GB50633-2010) 《工程测量规范》(GB50026-2007)

《5、6号机组测量接口管理程序》(CNPE-0603-PSB-288) 《建筑变形测量规范》(JGJ8-2007)

《建筑地基基础工程施工质量验收规范》(GB50202-2002) 《国家三四等水准测量规范》(GBT12898-2009) 4.定义及缩略语

初级网:在工程项目建设勘察阶段在厂区范围及周边布设的测量控制网。 次级网:在电厂主要厂房周围布设的、用于主要厂房施工测量控制的测量控制网。 施工测量:为田湾核电站 5、6号机组建造阶段服务的全部测量工作。 CNPE:指中国核电工程有限公司田湾核电扩建工程项目部(现场)。 BSEM:指北京四达贝克斯工程监理有限公司田核监理部。 项目部:指核工业南京建设集团有限公司田湾核电项目部。

变形监测 对建(构)筑物及其地基、建筑基坑或一定范围内的岩体及土体的位移、沉降、倾斜、挠度、裂缝和相关影响因素(如地下水、温度、应力应变等)进行监测,并提供变形分析预报的过程。

5.职责 5.1工程技术部

5.1.1工程技术部负责本程序编制修改和解释。由项目工程师审核,项目经理批准实施,报BSEM抄送CNPE项目部,经审批后执行。部门测量人员负责本程序的实施。

5.1.2配备在资质、数量上能满足其承担工程所需要的测量技术人员。 投入人员:

THNJ/BOPZ-GZ/CX-03

工程测量工作程序

版次A 6/16

投入主要设备:

5.2测量班组

5.2.1 在首级网或次级网基础上加密控制网或引测控制点,定期对这些控制(网)点进行复测检查,并形成记录。

5.2.2根据工程进度的要求,向施工人员随时提供中线方向和标高位置;在AB库的施工中进行变形监测。

5.2.4完成涉及工程量计算的土方开挖,开挖前和开挖后的测量。

5.2.5对现场测量过程中形成的测量资料进行整理,及时编制合格的测量报告,并根据职责划分送项目部,由项目部审核后报 BSEM 或 CNPE 项目部审批

5.2.6完成项目部委托的其它零星测量工作。

5.2.7接受项目部及 CNPE、BSEM 的检查,并为检查提供一切可以提供的手段,包括人员、设备等。

5.3 测量负责人

5.3.1熟读图纸并了解施工组织计划,将施工中随时下发的有关变更的图纸发到有关测量员手中。

5.3.2对项目部测量人员进行合理分工和日常测量组织工作(特别是各项检查前的准备工作 )

5.3.3负责组织测量人员向内业人员提供外业数据。特别有实际与设计不符合的问题,要及时向总工汇报。

5.3.4负责人做好测量人员的安全教育工作,对测量人员及测量仪器的安全负责,并组织测量人员对仪器进行定期检测及派送维修。

5.3.5对每个测量人员的工作都要复合检查,防止返工现象。

5.3.6归口管理测量工作,负责与CNPE及BSEM接口,对5、6号机组BOP标段00等子项建安工程施工测量工作负责。

5.3.7 负责对测量管理班组的测量工作进行监督。

5.3.8若控制网成果须更新,负责将更新成果书面发送BSEM抄送CNPE。

5.3.9 现场的测量工作,应提前通知CNPE及BSEM项目部进行见证或检查;并对 BSEM、CNPE 的检查提供方便和协助。

5.4、质量过程控制

1、测量人员要按照施工进度和测量方案要求,安排现场测量放线工作,作好施工测量日志。

2、现场使用的测量仪器设备应根据《测量仪器使用管理办法》的规定进行检校维护、保养并作好记录,发现问题后立即将仪器设备送检。

3、本工程的测量放线工作必须符合要求。 4、测量放线作业过程中,要严格执行“三检制”

自检:作业人员在每次测量放线完成后立即进行自检,自检中发现不合格项立即进行改正,直到全部合格,并填好自检记录。

互检:由施工负责人或质量检查员组织进行质量检查,发现不合格项立即改正至合格。 交接检:由施工负责人或质量检查员组织进行,上道工序合格后移交给下道工序,交接双方在交接记录上签字,并注明日期。

5.5其他各部门和施工班组

负责职责范围内的工作,并协助测量班组做好测量工作。 6.测量施工 6.1施工准备

6.1.1 在开工前上报工程测量工作程序,待审批后在进行后续施工。 6.1.2 开工前将人员资质及仪器检定证书报监理公司备案。 6.1.3 测量仪器在检定合格有效期内方可使用。

6.1.4 对施工区的现有控制测量资料进行收集、整理,发现问题要及时反馈给BSEM和CNPE。

6.1.5 对CNPE提供的控制点前应进行检查,确认无误后方可使用。检查应形成记录以备查。当发现控制点有误时,项目部应及时通知监理公司、CNPE项目部。

6.2控制测量 6.2.1 控制网的布设

控制点所选点位之间应通视良好,确保两点通视,以便控制点的定向和检查。控制点应免受施工干扰和影响,便于长期保存、加密、扩展和寻找,并加设栏杆保护。水准点的布设可随着平面控制点,点位选定后应及时埋设,采用C20混凝土浇筑且内嵌Φ20钢筋,钢筋头上划十字丝作为点位标志。

6.2.2 控制网的测设 ⑴ 平面控制

在次级网点的基础上进行加密布设,根据《工程测量规范》3.3.8,相关技术要求要符合(表1)和(表2)

以次级网基础加密建立,根据《工程测量规范》4.3.2:电磁波测距三角高程测量,在平面控制网的基础上布设三角高程网,相关技术要求应符合(表3)、(表4)

(表3)电磁波测距三角高程测量的主要技术要求

2.起讫点的精度等级,四等起不低于三等水准的高程点,五等起讫不低于四等水准的高程点。

3.路线长度不应超过相应等级的水准路线的长度限值

(表4)电磁波测距三角高程观测的主要技术要求

THNJ/BOPZ-GZ/CX-03 工程测量工作程序

版次A 9/16

控制网坐标、高程的计算采用平差易软件计算,平差软件计算后最后结果取位到1mm,平差的结果提供点的坐标、高程、点位精度、观测值改正数和观测值的平差值。

6.3 施工放样

认真熟悉图纸,了解设计意图,了解现场测量坐标与基坑开挖的关系,水准点的位置和高程,根据设计图纸计算出图纸设计高程,及时校对建筑物的平面、剖面的尺寸。要深入现场,了解场地环境,按管线平面图找出管道在地面上的位置,检查设计阶段测设的各种定位标志是否齐全,能否满足施工放线的需要。如果点位太少或被毁,应了解场区控制点分布情况,进行补测。

6.3.1施工放线

(1)根据工程公司提供的测量控制点,首先布设符合现场实际的平面控制网。然后测设建筑物位置,进行建筑物定位测量。测设建筑物轴线的目的是起到检核的作用,最后再根据设计图纸上的坐标或依据图纸计算的坐标来测设管线的位置和标高。

管线起点、终点、转折点坐标计算依据是设计单位提供的施工平面图。方法是根据设计图平面的关系计算出所有需要放样点的坐标数据。得到数据后,必须加强检查工作,经第二个人进行百分之一百的检查,确认无误后才能到现场测设。

需要注意的是:为了便于测量,对于管线较大的管线要从起点开始,标有里程桩。起点桩为0+000(+号前面的数值表示公里数,+号后面数值为米数),以后每100m钉一桩,编号分别为0+10,0+200。如果百米桩之间有重要地物(如穿越道路或地形变化较大处),应增加标桩,称为加桩。加桩的编号按该桩所在位置表示,如1+140表示该桩距起点1140m。

根据设计图纸计算出各桩位的中心点坐标,经监理审核后进行现场施工放样。 (2)现场放样:

放样前,需要先将仪器放置到室外半小时左右,使其与大气温度相一致后,将仪器假设在控制点上,设置测站后,后视另一控制点定向,反测控制点坐标,误差在允许范围内时,定向成功,然后将桩位坐标输入到全站仪中,便可进行测量放样工作。输入时仔细认真,避免出错。在施工现场放样出设计坐标点,根据《工程测量》8.3.12规定。坐标点偏差值不应超过(表3)规定。

(表3 )附属构筑物安装测量的允许偏差

THNJ/BOPZ-GZ/CX-03

工程测量工作程序

版次A 10/16

1.为保证管线标高,每个测区至少布设3 个高程控制点组成高程控制网。根据设计总图给定的±0.000标高的绝对高程,以高程控制点为依据,首先用DS3水准仪对高程控制点进行联测,高程无误后采用符合路线测定±0.000标高控制点,并根据需要定期进行复测。

2.高程控制点的联测。在向基坑内引测标高时,首先联测高程控制网点。经联测确认无误后,方可向基坑内引测所需的标高。

3、基坑标高基准点的引测方法:以现场高程控制点为依据,采用DS3水准仪以中丝读数法往基坑测设附合水准路线,将高程引测到基坑施工面上。标高基准点用红油漆标注在基坑侧面木桩上,并标明数据。

4、管线标高点的测设。管线标高点的测设是以引测到基坑的标高基准点为依据,采用DS3水准仪以中丝读数法进行。

6.3.3变形监测

1. 沉降观测前应在测区范围内,距离建筑物不少于30m之处设置三个基准控制点,基准控制点的位置应在不易碰动,既隐蔽又便于测设的地方。可考虑分别设在建筑物的西北、西南和东南角隐蔽处。

2. 沉降观测应采用附合线路或闭合线路,做到定机、定人、定路线。测设前仪器必须经过检验,符合要求后方可使用。

3. 沉降观测测点设置部位应考虑设置在每个区段的沉降缝两侧,荷载变化比较大的部位,外墙大角及间隔20m设一处,设置高度一般离地50cm。

4. 沉降观测的前后视距应尽可能相等,仪器到水准尺的距离不得大于30m。 5. 测设中,前后视必须采用同一个根水准尺。观测时,水准尺应和地面垂直,不得歪斜。

6. 在同一测站上观测各观测点时,当读完所有观测点的读数后应回测后视点,两次同一后视点的读数差不得超过±1mm。

7. 沉降观测的次数与频率应根据上部结构的作用荷载和作用时间,一般在施工阶段每上一层结构,观测一次,一直到结构封顶。装饰施工完毕观测一次,移交业主前观测一

次。

8. 观测的结果应及时整理成成果资料,及时通报业主或现场监理工程师,工程竣工后,应将成果资料整理归档。

6.4质量保证措施

6.4.1 保证在施工现场有多个控制点供校核。 6.4.2 两个人以上进行检核,防止粗差的发生。 6.4.3 内业计算的成果及上报的资料应当经审核后报送。

6.4.4 加强内业和外业资料的管理,仔细、认真地作好记录,并妥善保存。 6.4.5 加强自检工作,作好自检记录,发现问题及时处理并汇报上级部门。 6.5资料管理

6.5.1测量成果报验工作应按照《5、6号机组工程测量接口管理程》(CNPE-0603-PSB-288 A版)提前24小时通知监理、CNPE项目部。报验单应按照程序规定的格式进行报送,测量成果报验单中相对应表格应有观测人、记录人、审核人等签字。根据职责划分在一日内报送BMES或CNPE项目部审批。上报的测量成果报验单一式三份,项目部、BMES、CNPE各留存一份。

6.5.2测量成果资料提供给工程技术部、商务部可作为施工质量的控制和对外工作量结算依据。

6.5.3测量资料的归档和管理应按照《建设工程文件归档管理规范》(GB-T50238)执行。

6.5.4报验单编号管理

THNJ-CLBY-BOPZ-XX-0001 1 2 3 4 5

(1)表示核工业南京建设集团有限公司; (2)表示测量报验;

(3)表示田湾核电站5、6号机组BOP标段00等子项建安工程; (4)表示子项名称代码 (5)表示流水号。 6.6 竣工测量

根据本工程的特点竣工测量主要包括管线定位坐标测量、沉降监测测量、管线标高控制测量、井室坐标测量、AB仓库放样。

7 .测量工作流程图

8.安全保证措施

使用过程中必须做到“人在仪器在、人去仪器收”。在烈日和小雨的情况下必须撑伞,以免仪器损坏。在大雨和强风的恶劣天气情况下停止测量施工。

8.1仪器在使用过程中应注意的事项:

⑴ 严禁不了解仪器性能的人摆弄仪器,观测者不得擅自离开仪器。 ⑵ 从箱内取出仪器后,应立即固定在脚架底盘上,搬动较远时,应装箱。 ⑶ 仪器在使用和保管过程中,要注意防晒、防淋、防尘、防潮。 ⑷ 仪器操作时应按仪器操作规范正确的操作,注意不要将螺旋旋得过紧。 ⑸ 仪器使用后应将灰尘擦净,若受潮后,应将仪器置于通风处,待干燥后再装箱。 ⑹ 仪器出现异常情况,立即停止使用,直至查明原因或经过维修检定为止。 8.2 仪器的检校:

⑴ 测量仪器要定期(一年)到有资质的计量检定单位进行检定。

⑵ 测量仪器在运输或者使用过程中,如发现异常不能保证应有的精度,从新送到有资质的单位进行检测,从新取得合格证并上报CNPE/BMES审核合格后方可使用。

8.3 测量作业人员注意事项:

(1)临边架设仪器和临边放线时,观测人员和放线人员应正确佩戴和使用安全带。 (2)放线人员在边坡下方放线时应注意边坡上方危石,以防坠落伤人。

(3)高边坡顶面进行测量作业时,首先要检查边坡稳定情况,在没有可靠的方案之前不能在潜在崩塌边顶面进行测量作业,防止高处坠落事故发生。

(4)等高测量时不能随意往下丢物品、工具;在平地测量时不能随意对面使锤子、

不能随意丢掷物品、工具等,防止物品打击事故发生。

(5)禁止在正在进行挖方作业下面进行测量作业,必须在挖方下面进行测量作业时,要安排人员进行警戒,关注边坡异常情况,遇到异常情况人员首先转移,优先确保测量人员人身安全。

9 .附件

附件1 测量成果报验单(CNPE项目部审批) 附件2 测量成果报验单(监理公司审批) 附件3 施工测量示意图 附件4 定位数据记录表

田湾核电站5、6号机组

测量成果报验单

田湾核电站5、6号机组

测量成果报验单

施工测量示意图

田湾核电站扩建工程5、6号机组

定 位 数 据 记 录 表

程序会签

修改审批

文件变更记录表

目 录

1.目的 .......................................................................................................................................... 5 2.适用范围 .................................................................................................................................. 5 3.引用文件 .................................................................................................................................. 5 4.定义及缩略语 .......................................................................................................................... 5 5.职责 .......................................................................................................................................... 5 5.1工程技术部 .............................................................................................................................. 5 5.2测量班组 .................................................................................................................................. 6 5.3 测量负责人 ............................................................................................................................. 6 5.4其他各部门和施工班组 .......................................................................................................... 7 6.测量施工 .................................................................................................................................. 7 6.1施工准备 .................................................................................................................................. 7 6.2控制测量 .................................................................................................................................. 8 6.3 施工放样 ................................................................................................................................. 9 6.4质量保证措施 ........................................................................................................................ 11 6.5资料管理 ................................................................................................................................ 11 6.7安全保证措施 ........................................................................................................................ 12 7 .测量工作流程图 ...................................................................................................................... 12 8 .附件 .......................................................................................................................................... 13

1.目的

本程序旨在明确规范连云港田湾核电厂5、6号机组BOP标段00等子项建安工程工程现场测量工作的管理,在施工现场通过测量技术规范指导施工,同时对施工质量进行控制,以确保工程符合技术、质量安全和进度要求。

2.适用范围

适用于田湾5、6号机组BOP标段00等子项建安工程工程。 3.引用文件

中国核电工程有限公司提供的施工图纸、技术规格书、有关技术文件等 《核电厂工程测量技术规范》(GB50633-2010) 《工程测量规范》(GB50026-2007)

《5、6号机组测量接口管理程序》(CNPE-0603-PSB-288) 《建筑变形测量规范》(JGJ8-2007)

《建筑地基基础工程施工质量验收规范》(GB50202-2002) 《国家三四等水准测量规范》(GBT12898-2009) 4.定义及缩略语

初级网:在工程项目建设勘察阶段在厂区范围及周边布设的测量控制网。 次级网:在电厂主要厂房周围布设的、用于主要厂房施工测量控制的测量控制网。 施工测量:为田湾核电站 5、6号机组建造阶段服务的全部测量工作。 CNPE:指中国核电工程有限公司田湾核电扩建工程项目部(现场)。 BSEM:指北京四达贝克斯工程监理有限公司田核监理部。 项目部:指核工业南京建设集团有限公司田湾核电项目部。

变形监测 对建(构)筑物及其地基、建筑基坑或一定范围内的岩体及土体的位移、沉降、倾斜、挠度、裂缝和相关影响因素(如地下水、温度、应力应变等)进行监测,并提供变形分析预报的过程。

5.职责 5.1工程技术部

5.1.1工程技术部负责本程序编制修改和解释。由项目工程师审核,项目经理批准实施,报BSEM抄送CNPE项目部,经审批后执行。部门测量人员负责本程序的实施。

5.1.2配备在资质、数量上能满足其承担工程所需要的测量技术人员。 投入人员:

THNJ/BOPZ-GZ/CX-03

工程测量工作程序

版次A 6/16

投入主要设备:

5.2测量班组

5.2.1 在首级网或次级网基础上加密控制网或引测控制点,定期对这些控制(网)点进行复测检查,并形成记录。

5.2.2根据工程进度的要求,向施工人员随时提供中线方向和标高位置;在AB库的施工中进行变形监测。

5.2.4完成涉及工程量计算的土方开挖,开挖前和开挖后的测量。

5.2.5对现场测量过程中形成的测量资料进行整理,及时编制合格的测量报告,并根据职责划分送项目部,由项目部审核后报 BSEM 或 CNPE 项目部审批

5.2.6完成项目部委托的其它零星测量工作。

5.2.7接受项目部及 CNPE、BSEM 的检查,并为检查提供一切可以提供的手段,包括人员、设备等。

5.3 测量负责人

5.3.1熟读图纸并了解施工组织计划,将施工中随时下发的有关变更的图纸发到有关测量员手中。

5.3.2对项目部测量人员进行合理分工和日常测量组织工作(特别是各项检查前的准备工作 )

5.3.3负责组织测量人员向内业人员提供外业数据。特别有实际与设计不符合的问题,要及时向总工汇报。

5.3.4负责人做好测量人员的安全教育工作,对测量人员及测量仪器的安全负责,并组织测量人员对仪器进行定期检测及派送维修。

5.3.5对每个测量人员的工作都要复合检查,防止返工现象。

5.3.6归口管理测量工作,负责与CNPE及BSEM接口,对5、6号机组BOP标段00等子项建安工程施工测量工作负责。

5.3.7 负责对测量管理班组的测量工作进行监督。

5.3.8若控制网成果须更新,负责将更新成果书面发送BSEM抄送CNPE。

5.3.9 现场的测量工作,应提前通知CNPE及BSEM项目部进行见证或检查;并对 BSEM、CNPE 的检查提供方便和协助。

5.4、质量过程控制

1、测量人员要按照施工进度和测量方案要求,安排现场测量放线工作,作好施工测量日志。

2、现场使用的测量仪器设备应根据《测量仪器使用管理办法》的规定进行检校维护、保养并作好记录,发现问题后立即将仪器设备送检。

3、本工程的测量放线工作必须符合要求。 4、测量放线作业过程中,要严格执行“三检制”

自检:作业人员在每次测量放线完成后立即进行自检,自检中发现不合格项立即进行改正,直到全部合格,并填好自检记录。

互检:由施工负责人或质量检查员组织进行质量检查,发现不合格项立即改正至合格。 交接检:由施工负责人或质量检查员组织进行,上道工序合格后移交给下道工序,交接双方在交接记录上签字,并注明日期。

5.5其他各部门和施工班组

负责职责范围内的工作,并协助测量班组做好测量工作。 6.测量施工 6.1施工准备

6.1.1 在开工前上报工程测量工作程序,待审批后在进行后续施工。 6.1.2 开工前将人员资质及仪器检定证书报监理公司备案。 6.1.3 测量仪器在检定合格有效期内方可使用。

6.1.4 对施工区的现有控制测量资料进行收集、整理,发现问题要及时反馈给BSEM和CNPE。

6.1.5 对CNPE提供的控制点前应进行检查,确认无误后方可使用。检查应形成记录以备查。当发现控制点有误时,项目部应及时通知监理公司、CNPE项目部。

6.2控制测量 6.2.1 控制网的布设

控制点所选点位之间应通视良好,确保两点通视,以便控制点的定向和检查。控制点应免受施工干扰和影响,便于长期保存、加密、扩展和寻找,并加设栏杆保护。水准点的布设可随着平面控制点,点位选定后应及时埋设,采用C20混凝土浇筑且内嵌Φ20钢筋,钢筋头上划十字丝作为点位标志。

6.2.2 控制网的测设 ⑴ 平面控制

在次级网点的基础上进行加密布设,根据《工程测量规范》3.3.8,相关技术要求要符合(表1)和(表2)

以次级网基础加密建立,根据《工程测量规范》4.3.2:电磁波测距三角高程测量,在平面控制网的基础上布设三角高程网,相关技术要求应符合(表3)、(表4)

(表3)电磁波测距三角高程测量的主要技术要求

2.起讫点的精度等级,四等起不低于三等水准的高程点,五等起讫不低于四等水准的高程点。

3.路线长度不应超过相应等级的水准路线的长度限值

(表4)电磁波测距三角高程观测的主要技术要求

THNJ/BOPZ-GZ/CX-03 工程测量工作程序

版次A 9/16

控制网坐标、高程的计算采用平差易软件计算,平差软件计算后最后结果取位到1mm,平差的结果提供点的坐标、高程、点位精度、观测值改正数和观测值的平差值。

6.3 施工放样

认真熟悉图纸,了解设计意图,了解现场测量坐标与基坑开挖的关系,水准点的位置和高程,根据设计图纸计算出图纸设计高程,及时校对建筑物的平面、剖面的尺寸。要深入现场,了解场地环境,按管线平面图找出管道在地面上的位置,检查设计阶段测设的各种定位标志是否齐全,能否满足施工放线的需要。如果点位太少或被毁,应了解场区控制点分布情况,进行补测。

6.3.1施工放线

(1)根据工程公司提供的测量控制点,首先布设符合现场实际的平面控制网。然后测设建筑物位置,进行建筑物定位测量。测设建筑物轴线的目的是起到检核的作用,最后再根据设计图纸上的坐标或依据图纸计算的坐标来测设管线的位置和标高。

管线起点、终点、转折点坐标计算依据是设计单位提供的施工平面图。方法是根据设计图平面的关系计算出所有需要放样点的坐标数据。得到数据后,必须加强检查工作,经第二个人进行百分之一百的检查,确认无误后才能到现场测设。

需要注意的是:为了便于测量,对于管线较大的管线要从起点开始,标有里程桩。起点桩为0+000(+号前面的数值表示公里数,+号后面数值为米数),以后每100m钉一桩,编号分别为0+10,0+200。如果百米桩之间有重要地物(如穿越道路或地形变化较大处),应增加标桩,称为加桩。加桩的编号按该桩所在位置表示,如1+140表示该桩距起点1140m。

根据设计图纸计算出各桩位的中心点坐标,经监理审核后进行现场施工放样。 (2)现场放样:

放样前,需要先将仪器放置到室外半小时左右,使其与大气温度相一致后,将仪器假设在控制点上,设置测站后,后视另一控制点定向,反测控制点坐标,误差在允许范围内时,定向成功,然后将桩位坐标输入到全站仪中,便可进行测量放样工作。输入时仔细认真,避免出错。在施工现场放样出设计坐标点,根据《工程测量》8.3.12规定。坐标点偏差值不应超过(表3)规定。

(表3 )附属构筑物安装测量的允许偏差

THNJ/BOPZ-GZ/CX-03

工程测量工作程序

版次A 10/16

1.为保证管线标高,每个测区至少布设3 个高程控制点组成高程控制网。根据设计总图给定的±0.000标高的绝对高程,以高程控制点为依据,首先用DS3水准仪对高程控制点进行联测,高程无误后采用符合路线测定±0.000标高控制点,并根据需要定期进行复测。

2.高程控制点的联测。在向基坑内引测标高时,首先联测高程控制网点。经联测确认无误后,方可向基坑内引测所需的标高。

3、基坑标高基准点的引测方法:以现场高程控制点为依据,采用DS3水准仪以中丝读数法往基坑测设附合水准路线,将高程引测到基坑施工面上。标高基准点用红油漆标注在基坑侧面木桩上,并标明数据。

4、管线标高点的测设。管线标高点的测设是以引测到基坑的标高基准点为依据,采用DS3水准仪以中丝读数法进行。

6.3.3变形监测

1. 沉降观测前应在测区范围内,距离建筑物不少于30m之处设置三个基准控制点,基准控制点的位置应在不易碰动,既隐蔽又便于测设的地方。可考虑分别设在建筑物的西北、西南和东南角隐蔽处。

2. 沉降观测应采用附合线路或闭合线路,做到定机、定人、定路线。测设前仪器必须经过检验,符合要求后方可使用。

3. 沉降观测测点设置部位应考虑设置在每个区段的沉降缝两侧,荷载变化比较大的部位,外墙大角及间隔20m设一处,设置高度一般离地50cm。

4. 沉降观测的前后视距应尽可能相等,仪器到水准尺的距离不得大于30m。 5. 测设中,前后视必须采用同一个根水准尺。观测时,水准尺应和地面垂直,不得歪斜。

6. 在同一测站上观测各观测点时,当读完所有观测点的读数后应回测后视点,两次同一后视点的读数差不得超过±1mm。

7. 沉降观测的次数与频率应根据上部结构的作用荷载和作用时间,一般在施工阶段每上一层结构,观测一次,一直到结构封顶。装饰施工完毕观测一次,移交业主前观测一

次。

8. 观测的结果应及时整理成成果资料,及时通报业主或现场监理工程师,工程竣工后,应将成果资料整理归档。

6.4质量保证措施

6.4.1 保证在施工现场有多个控制点供校核。 6.4.2 两个人以上进行检核,防止粗差的发生。 6.4.3 内业计算的成果及上报的资料应当经审核后报送。

6.4.4 加强内业和外业资料的管理,仔细、认真地作好记录,并妥善保存。 6.4.5 加强自检工作,作好自检记录,发现问题及时处理并汇报上级部门。 6.5资料管理

6.5.1测量成果报验工作应按照《5、6号机组工程测量接口管理程》(CNPE-0603-PSB-288 A版)提前24小时通知监理、CNPE项目部。报验单应按照程序规定的格式进行报送,测量成果报验单中相对应表格应有观测人、记录人、审核人等签字。根据职责划分在一日内报送BMES或CNPE项目部审批。上报的测量成果报验单一式三份,项目部、BMES、CNPE各留存一份。

6.5.2测量成果资料提供给工程技术部、商务部可作为施工质量的控制和对外工作量结算依据。

6.5.3测量资料的归档和管理应按照《建设工程文件归档管理规范》(GB-T50238)执行。

6.5.4报验单编号管理

THNJ-CLBY-BOPZ-XX-0001 1 2 3 4 5

(1)表示核工业南京建设集团有限公司; (2)表示测量报验;

(3)表示田湾核电站5、6号机组BOP标段00等子项建安工程; (4)表示子项名称代码 (5)表示流水号。 6.6 竣工测量

根据本工程的特点竣工测量主要包括管线定位坐标测量、沉降监测测量、管线标高控制测量、井室坐标测量、AB仓库放样。

7 .测量工作流程图

8.安全保证措施

使用过程中必须做到“人在仪器在、人去仪器收”。在烈日和小雨的情况下必须撑伞,以免仪器损坏。在大雨和强风的恶劣天气情况下停止测量施工。

8.1仪器在使用过程中应注意的事项:

⑴ 严禁不了解仪器性能的人摆弄仪器,观测者不得擅自离开仪器。 ⑵ 从箱内取出仪器后,应立即固定在脚架底盘上,搬动较远时,应装箱。 ⑶ 仪器在使用和保管过程中,要注意防晒、防淋、防尘、防潮。 ⑷ 仪器操作时应按仪器操作规范正确的操作,注意不要将螺旋旋得过紧。 ⑸ 仪器使用后应将灰尘擦净,若受潮后,应将仪器置于通风处,待干燥后再装箱。 ⑹ 仪器出现异常情况,立即停止使用,直至查明原因或经过维修检定为止。 8.2 仪器的检校:

⑴ 测量仪器要定期(一年)到有资质的计量检定单位进行检定。

⑵ 测量仪器在运输或者使用过程中,如发现异常不能保证应有的精度,从新送到有资质的单位进行检测,从新取得合格证并上报CNPE/BMES审核合格后方可使用。

8.3 测量作业人员注意事项:

(1)临边架设仪器和临边放线时,观测人员和放线人员应正确佩戴和使用安全带。 (2)放线人员在边坡下方放线时应注意边坡上方危石,以防坠落伤人。

(3)高边坡顶面进行测量作业时,首先要检查边坡稳定情况,在没有可靠的方案之前不能在潜在崩塌边顶面进行测量作业,防止高处坠落事故发生。

(4)等高测量时不能随意往下丢物品、工具;在平地测量时不能随意对面使锤子、

不能随意丢掷物品、工具等,防止物品打击事故发生。

(5)禁止在正在进行挖方作业下面进行测量作业,必须在挖方下面进行测量作业时,要安排人员进行警戒,关注边坡异常情况,遇到异常情况人员首先转移,优先确保测量人员人身安全。

9 .附件

附件1 测量成果报验单(CNPE项目部审批) 附件2 测量成果报验单(监理公司审批) 附件3 施工测量示意图 附件4 定位数据记录表

田湾核电站5、6号机组

测量成果报验单

田湾核电站5、6号机组

测量成果报验单

施工测量示意图

田湾核电站扩建工程5、6号机组

定 位 数 据 记 录 表


相关内容

  • 建设工程竣工验收备案管理
  • 建设工程竣工验收备案管 理毕业论文封面书 姓名:简美珍 学号:07114127 专业:07建筑工程管理专业 院系:水利与建筑工程系 指导教师: 刘 萍 张宪明 一.摘要 二.关键词 三.前言 四.第一章 建设工程竣工验收备案管理概述 1.建设工程竣工验收备案的定义 2.建设工程竣工验收备案的目的 3 ...

  • 论建筑工程测量的重要性
  • 论建筑工程测量的重要性 摘 要:建筑工程规划设计.施工与经营管理工作的测量工作是保障建筑质量的关键 ,其是现代建筑工程投资建设.施工.维护管理的重要工作.深刻认识建筑工程测量工作重要性,认识影响其测量质量的各项因素有助于测量工作质量的提高,有助于建筑工程施工质量的提高.文中就建筑工程测量重要性及其对 ...

  • 2016年度勘察设计注册工程师资格考试报考条件
  • 2016年度勘察设计注册工程师资格考试报考条件 一.注册土木工程师(岩土)资格考试条件 (一)参加注册土木工程师(岩土)基础考试,应具备下列条件之一: ⑪取得本专业或相近专业大学本科及以上学历或学位. ⑫取得本专业或相近专业大学专科学历,从事岩土工程专业工作满1年. ⑬取得其他专业大学本科及以上学历 ...

  • 工程施工测量管理实施细则
  • 中铁十局济南铁路工程有限公司 工程施工测量管理实施细则 第一章 总则 第一条 目的和意义 施工测量工作是工程建设的重要环节,是技术管理工作的重要组成部分,为进一步加强施工测量管理工作,明确测量工作的任务和职责,确保测量工作及时地.精确地满足施工生产的需要,特制定本细则. 施工测量是工程开工前.工序作 ...

  • 注册电气工程师报名条件
  • 注册电气工程师(发输变电.供配电). 公用设备工程师(暖通空调.给水排水.动力). 注册化工工程师.注册环保工程师考试报考条件 一.注册电气工程师报考条件 凡中华人民共和国公民,遵守国家法律.法规,恪守职业道德,并具备以下条件之一者,可申请参加基础考试: 1.取得本专业(指电气工程.电气工程自动化专 ...

  • 水利水电工程验收规程
  • 水利水电工程验收规程 1 总 则 1.0.1 为加强水利水电建设工程验收管理,使水利水电建设工程验收制度化.规范化,保证工程验收质量,特制定本规程. 1.0.2 本规程适用于由中央.地方财政全部投资或部分投资建设的大中型水利水电建设工程(含1.2.3 级堤防工程)的验收,其他水利水电建设工程的验收可 ...

  • 建筑类证书条件
  • 建筑类证书报考条件全集 一级建造师报考条件: 1.凡遵守国家法律.法规,具备下列条件之一者,可申请参加一级建造师执业资格考试:(1)取得工程类或工程经济类大学专科学历,工作满6年,其中从事建设工程项目施工管理工作满4年:(2)取得工程类或工程经济类大学本科学历,工作满4年,其中从事建设工程项目施工管 ...

  • 建筑类.工程类证书报考条件大全
  • 本文由taoshong贡献 doc文档可能在WAP端浏览体验不佳.建议您优先选择TXT,或下载源文件到本机查看. 建筑类. 建筑类.工程类证书报考条件大全 一级建造师报考条件: 一级建造师报考条件: 1.凡遵守国家法律.法规,具备下列条件之一者,可申请参加一级建造师执业资格考试: (1)取得工程类或 ...

  • 建设工程质量控制常用流程图
  • 5. 建设工程质量控制常用流程图 建设工程质量控制流程图是控制工程质量的重要步骤或工作分解,围绕工程质量控制流程图是控制来编制控制方案是一种基本方法.见下图: 5.1监理工作总程序 工作要求: ⑴ 委派具有丰富超高层工程施工监理经验的国家注册监理工程师担任项目总 监,并针对本项目特点召集设备.土建方 ...

  • 2013年度全国注册公用设备工程师报考条件
  • 2013年度全国注册公用设备工程师报考条件 (一)凡中华人民共和国公民,遵守国家法律.法规,恪守职业道德,并具备以下条件之一者,可申请参加基础考试: 1.取得本专业(指公用设备专业工程中的暖通空调.动力.给水排水专业)或相近专业大学本科及以上学历或学位. 2.取得本专业或相近专业大学专科学历,累计从 ...